| Owner | Filings | Most Recent |
|---|---|---|
| TCH 10TH STREET | 22 | 03/22/2026 |
| NICKEY KEHOE | 8 | 07/08/2026 |
| CORCORAN GROUP | 3 | 03/21/2026 |
| HH PROPERTY MANAGEMENT SERVICES | 2 | 03/21/2026 |
| 49 EAST 10TH LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RAAD | 2 | 03/12/2024 |
| JANSON SCURO LLP | 1 | 03/08/2024 |
| GRASSO-MENZIUSO ARCHITECTS | 3 | 08/24/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| PAUL FUSCO CONSULTING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RICHARD ESPOSITO | Electrical | 3 | 03/21/2026 |
| FABRIZZIO CONSTRUCTION IN | General Contractor | 3 | 07/08/2026 |
| ALL WAYS ELECTRIC CORP.W | Electrical | 1 | 03/22/2026 |
| ARIANA CONTRACTING INC | Plumbing | 1 | 07/08/2026 |
| URBAN MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RAAD | 7727 | 2 | 03/12/2024 |
| METROPOLITAN MECHANICAL C | 2277 | 1 | 03/08/2024 |
| GRASSO-MENZIUSO ARCHITECT | 1279 | 1 | 12/15/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | URBAN MECHANICAL CORP | 04/10/2024 |
| DOB NOW | Mechanical Systems | Signed-off | FABRIZZIO CONSTRUCTION IN | 04/09/2024 |
| DOB NOW | General Construction | Signed-off | FABRIZZIO CONSTRUCTION IN | 03/21/2024 |
| DOB NOW | Plumbing | Signed-off | ARIANA CONTRACTING INC | 02/09/2021 |
| BIS | OT | ISSUED | ARBEN REMODELING INC | 02/04/2021 |
| BIS | PL | ISSUED | ALL HOUR SEWER SERVICE CO. | 03/27/2019 |
| BIS | OT | ISSUED | ARBEN REMODELING INC | 03/15/2019 |
| BIS | PL | ISSUED | CODE MECHANICAL INC | 01/25/2018 |
| BIS | OT | ISSUED | APPLE RENOVATORS INC | 01/03/2018 |
| BIS | EQ | ISSUED | ARSENAL SCAFFOLD INC | 08/09/2017 |
| BIS | PL | ISSUED | WATERFIRE INC | 07/29/2011 |
| BIS | OT | ISSUED | SCHOENBACH CONSTRUCTION | 07/26/2011 |
| BIS | PL | ISSUED | PILATO BROS PLBG & HTG CO | 02/02/2001 |
| BIS | OT | ISSUED | M,R. CHOENBACH INC | 12/27/2000 |
| BIS | EQ | RE-ISSUED | ATLANTIC SCAFFOLDING | 05/18/1994 |
| BIS | BL | ISSUED | PIOLET ENERGY CORP DBA P GS&HTCP | 03/18/1992 |
| BIS | PL | ISSUED | WASOFF PLBG & UTILITY CO | 03/18/1992 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/15/2020 | Signed-off | ARIANA CONTRACTING INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/07/2025 | Permit Issued | COACHMEN SOLUTIONS CORP | 1 meters, 1 new_meters |
| 07/23/2024 | Complete | ALL WAYS ELECTRIC CORP.W | General Wiring |
| 01/29/2024 | Permit Issued | ALL WAYS ELECTRIC CORP.W | General Wiring |
| 03/04/2021 | Complete | E & M ELECTRICAL NY CORP | General Wiring |
| 06/05/2019 | Complete | E & M ELECTRICAL NY CORP | General Wiring |
| 02/02/2018 | Complete | LEWIN ELECTRIC CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/26/2024 | HVAC-R and service water heating equipment | NICHOLAS AZADIAN | energy_progress |
| 02/26/2024 | HVAC-R and service water piping design and insulation | NICHOLAS AZADIAN | energy_progress |
| 02/26/2024 | HVAC-R and service water heating system controls | NICHOLAS AZADIAN | energy_progress |
| 02/26/2024 | Fire-Resistant Penetrations and Joints | NICHOLAS AZADIAN | special |
| 02/26/2024 | Energy Code Compliance Inspections | NICHOLAS AZADIAN | progress |
| 02/26/2024 | HVAC-R and service water heating equipment | NICHOLAS AZADIAN | energy_progress |
| 02/26/2024 | HVAC-R and service water piping design and insulation | NICHOLAS AZADIAN | energy_progress |
| 02/26/2024 | HVAC-R and service water heating system controls | NICHOLAS AZADIAN | energy_progress |
| 02/23/2024 | Final | Steven Scuro | progress |
| 02/23/2024 | Tenant Protection Plan Compliance | PATRICK MCDONALD | special |
| 08/22/2023 | Lighting in dwelling units | — | energy_progress |
| 08/22/2023 | Fenestration air leakage | — | energy_progress |
| 08/22/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 08/22/2023 | Energy Code Compliance Inspections | — | progress |
| 08/22/2023 | Fire-Resistance Rated Construction | — | progress |
| 08/22/2023 | Structural Stability – Alterations of existing buildings | — | special |
| 08/02/2023 | Tenant Protection Plan Compliance | — | special |
| 08/19/2021 | Final | — | progress |
| 12/15/2020 | Fire-Resistant Penetrations and Joints | Christopher Menziuso | special |