← Back
Old law tenement
493 EAST 166 STREET
BRONX · Morrisania · BIN 2001309
💬 Discuss this project
1920Year Built
5Stories
C4Building Class
M1-1/R7-2Zoning
11,090 sfGross Floor Area
10Units
Rent Stabilized44 Open Violations ▸
Old law tenement · Owner of record: BEULAH CLUSTER HOUSING DEVELOPMENT FUND COMPANY · 3,321 sf lot · 3.34 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingEquipmentGeneral
Roof2p · 1 filing · 20 docs
Floor 51p · 1 filing · 20 docs
Floor 41p · 1 filing · 20 docs
Floor 31p · 1 filing · 20 docs
Floor 21p · 1 filing · 20 docs
Floor 11p · 1 filing · 20 docs
Cellar4p · 1 filing · 20 docs
Site & exterior6p · 2 filings · 6 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BEULAH HDFC2107/08/2026
TRIERA CONTRACTING INC503/22/2026
SUTHERTON CONSTRUCTION407/08/2026
BEULAH CLUSTER HDFC403/21/2026
BEULAH CLUSTER HOUSING DEVELOPMENT FUND COMPANY103/22/2026
HPD CITY OF NEW YORK103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
OCV ARCHITECTS703/20/2025
PAUL PERDEK, PROF. ENG. PLLC108/28/2023
ENTHINK ENGINEERS LLC102/17/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
OCV ARCHITECTS703/21/2026
A1 EXPEDITING SERVICE203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CONROCK CONSTRUCTION LLCGeneral Contractor507/08/2026
TRIERA CONTRACTING INCGeneral Contractor303/21/2026
GBL MECHANICAL INCPlumbing207/08/2026
SUTHERTON CNSTRN CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SKYLINE ENGINEERING, PLLC267603/20/2025
Building Lifecycle
All (119)Filed (9)Permit Issued (7)Signed Off (5)Violation (60)Inspection (4)Objection (12)Special Inspection (22)
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
B
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
B
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
B
06/29/2026
Violation issued (HPD, open)
C
06/29/2026
Violation issued (HPD, open)
C
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
B
06/29/2026
Violation issued (HPD, open)
A
06/29/2026
Violation issued (HPD, open)
A
04/30/2026
Violation issued (HPD, closed)
A
03/18/2026
Violation issued (HPD, open)
A
03/18/2026
Violation issued (HPD, open)
A
03/18/2026
Violation issued (HPD, open)
A
02/02/2026
Violation issued (HPD, open)
C
12/18/2025
Violation issued (HPD, closed)
A
12/18/2025
Violation issued (HPD, open)
A
12/18/2025
Violation issued (HPD, open)
B
12/18/2025
Violation issued (HPD, open)
B
09/02/2025
Signed off — Alteration
BOILER REPLACEMENT FILED IN CONJUNCTION WITH ALTERATION APPLICATION #X00606975-I1
X00606975-S2
07/15/2025
Signed off — Alteration
BOILER REPLACEMENT FILED IN CONJUNCTION WITH ALTERATION APPLICATION #X00606975-I1
X00606975-S1
07/15/2025
Signed off — Alteration
BOILER REPLACEMENT FILED IN CONJUNCTION WITH ALTERATION APPLICATION #X00606975-I1
X00606975-I1
06/24/2025
Violation issued (HPD, closed)
B
06/01/2025
Violation issued (HPD, open)
A
06/01/2025
Violation issued (HPD, open)
B
06/01/2025
Violation issued (HPD, closed)
C
06/01/2025
Violation issued (HPD, closed)
C
05/18/2025
Violation issued (HPD, closed)
C
05/18/2025
Violation issued (HPD, closed)
C
05/18/2025
Violation issued (HPD, closed)
C
05/18/2025
Violation issued (HPD, open)
B
05/18/2025
Violation issued (HPD, open)
A
04/17/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/16/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. LIVE LOAD 300PSF.
X00821425-I1
04/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Matthew Wavro
04/10/2025
Special inspection requirement — Maintenance information
Matthew Wavro
04/10/2025
Special inspection requirement — Tenant Protection Plan Compliance
Matthew Wavro
04/02/2025
Signed off — Alteration
TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
X00924514-I1
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, open)
A
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, closed)
C
03/21/2025
Violation issued (HPD, open)
C
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, open)
B
03/21/2025
Violation issued (HPD, closed)
C
03/21/2025
Violation issued (HPD, open)
A
Latest 60 of 119 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offLIQUID TECH PLBG&HTG,INC11/27/2024
DOB NOWGeneral ConstructionSigned-offCONROCK CONSTRUCTION LLC09/17/2024
DOB NOWBoiler EquipmentSigned-offLIQUID TECH PLBG&HTG,INC07/03/2024
DOB NOWGeneral ConstructionSigned-offCONROCK CONSTRUCTION LLC04/11/2024
DOB NOWSupported ScaffoldSigned-offSUTHERTON CNSTRN CORP08/29/2023
DOB NOWGeneral ConstructionSigned-offCONROCK CONSTRUCTION LLC05/01/2023
DOB NOWSidewalk ShedSigned-offTRIERA CONTRACTING INC02/17/2023
BISEQISSUEDNOTIAS CONSTRUCTION INC04/14/2004
BIS—ISSUEDNOTIAS CONSTRUCTION INC04/14/2004
BISPLISSUEDCEGF & G PLUMBING CORP10/03/2003
BIS—ISSUEDNOTIAS CONSTRUCTION INC06/13/2003
BISEQISSUEDNOTIAS CONSTRUCTION INC06/13/2003
1 project · most recent 02/17/2023
FiledStatusContractorScope
02/17/2023CompleteRICHARD NEU—
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
04/17/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/23/2024Pass-Final Boiler Equipment InspectionPassView ↗
07/26/2024Pass-Final Boiler Equipment InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
04/10/2025Fire-Resistant Penetrations and JointsMatthew Wavrospecial
04/10/2025Maintenance informationMatthew Wavroenergy_progress
04/10/2025Tenant Protection Plan ComplianceMatthew Wavrospecial
10/10/2024HVAC-R and service water piping design and insulationMatthew Wavroenergy_progress
10/10/2024Tenant Protection Plan ComplianceMatthew Wavrospecial
10/10/2024Heating SystemsMatthew Wavrospecial
10/10/2024Maintenance informationMatthew Wavroenergy_progress
10/10/2024HVAC-R and service water heating equipmentMatthew Wavroenergy_progress
10/10/2024HVAC-R and service water heating system controlsMatthew Wavroenergy_progress
10/01/2024HVAC-R and service water piping design and insulationMatthew Wavroenergy_progress
10/01/2024Heating SystemsMatthew Wavrospecial
10/01/2024Tenant Protection Plan Compliance—special
10/01/2024Maintenance informationMatthew Wavroenergy_progress
10/01/2024HVAC-R and service water heating system controlsMatthew Wavroenergy_progress
10/01/2024HVAC-R and service water heating equipmentMatthew Wavroenergy_progress
09/05/2024Heating SystemsMatthew Wavrospecial
09/05/2024HVAC-R and service water heating system controlsMatthew Wavroenergy_progress
09/05/2024Tenant Protection Plan Compliance—special
09/05/2024HVAC-R and service water heating equipmentMatthew Wavroenergy_progress
09/05/2024HVAC-R and service water piping design and insulationMatthew Wavroenergy_progress
09/05/2024Maintenance informationMatthew Wavroenergy_progress
10/06/2021FinalJOHN COOGANprogress
▾Documents — 55 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/23/2026X00821425-I1Request digital key ↗
08/22/2026X00924514-I1Request digital key ↗
08/21/2026X00606975-P4Request digital key ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications28
▸DOB NOWProgress Inspector Seal & Signature14
09/23/2026X00606975-S1Open ↗
09/23/2026X00606975-S1Open ↗
09/23/2026X00606975-S1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/23/2026X00821425-I1Open ↗
08/22/2026X00924514-I1Open ↗
08/21/2026X00606975-S1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/23/2026X00606975-P1Open ↗
09/23/2026X00606975-S1Open ↗
09/23/2026X00606975-S1Open ↗
Showing 3 of 5 on file for this type
▸Environmental & Asbestos7
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/21/2026X00606975-P4Open ↗
08/21/2026X00606975-P3Open ↗
08/21/2026X00606975-P2Open ↗
Showing 3 of 7 on file for this type
▸Energy Compliance2
▸DOB NOWPreliminary Commissioning Report Certification2
08/13/2026X00606975-S1Open ↗
08/13/2026X00606975-S2Open ↗
▸Approvals, Objections & Sign-offs9
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter9
08/13/2026X00606975-P3Open ↗
08/13/2026X00606975-P4Open ↗
08/13/2026X00606975-I1Open ↗
Showing 3 of 9 on file for this type