| Owner | Filings | Most Recent |
|---|---|---|
| VAJA GROUP | 69 | 07/08/2026 |
| CITY WIDE BUILDER GRP | 20 | 07/08/2026 |
| LIC HOTEL PROPERTY MH, LLC | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/07/2018 | $300K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| S. WIEDER ARCHITECT P.C. | 7 | 04/09/2024 |
| ADVANCED ENGINEERING & INSPECT. PLL | 5 | 11/09/2023 |
| FL&M ENGINEERING DESIGN &INSPECTION | 4 | 06/15/2023 |
| STRUCTURAL ENGINEERING TECHNOLOGIES | 5 | 04/18/2023 |
| AT-DESIGN | 2 | 01/20/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 10 | 03/21/2026 |
| SUNSHINE PLAZA LLC | 9 | 03/21/2026 |
| GREEN STUDIO | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CITY WIDE BUILDERS GRP IN | General Contractor | 35 | 07/08/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 7 | 07/08/2026 |
| ELIEZER ROSENBERG | Electrical | 1 | 03/21/2026 |
| EP ELECTRIC NY LLC | Electrical | 1 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 16 | 04/09/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | CITY WIDE BUILDERS GRP IN | 10/31/2023 |
| DOB NOW | Support of Excavation | Signed-off | CITY WIDE BUILDERS GRP IN | 07/03/2023 |
| DOB NOW | Construction Fence | Signed-off | CITY WIDE BUILDERS GRP IN | 05/12/2023 |
| DOB NOW | Structural | Signed-off | CITY WIDE BUILDERS GRP IN | 05/11/2023 |
| DOB NOW | Mechanical Systems | Signed-off | CITY WIDE BUILDERS GRP IN | 04/18/2023 |
| DOB NOW | General Construction | Permit Issued | CITY WIDE BUILDERS GRP IN | 04/18/2023 |
| DOB NOW | Foundation | Signed-off | CITY WIDE BUILDERS GRP IN | 04/05/2023 |
| DOB NOW | Foundation | Signed-off | CITY WIDE BUILDERS GRP IN | 04/05/2023 |
| DOB NOW | General Construction | Permit Issued | CITY WIDE BUILDERS GRP IN | 04/05/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | MANHATTAN D ENTERPRISES | 03/06/2023 |
| DOB NOW | Supported Scaffold | Signed-off | MANHATTAN D ENTERPRISES | 01/25/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 01/25/2023 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 01/11/2023 |
| DOB NOW | Plumbing | Signed-off | PRIME PIPING & HEATING IN | 12/30/2022 |
| DOB NOW | General Construction | Permit Issued | CITY WIDE BUILDERS GRP IN | 09/09/2022 |
| DOB NOW | Support of Excavation | Signed-off | CITY WIDE BUILDERS GRP IN | 07/27/2022 |
| DOB NOW | Foundation | Signed-off | CITY WIDE BUILDERS GRP IN | 07/27/2022 |
| DOB NOW | Earth Work | Signed-off | CITY WIDE BUILDERS GRP IN | 05/24/2022 |
| DOB NOW | Support of Excavation | Signed-off | CITY WIDE BUILDERS GRP IN | 05/18/2022 |
| DOB NOW | Construction Fence | Signed-off | CITY WIDE BUILDERS GRP IN | 05/13/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/09/2024 | Signed-off | CITY WIDE BUILDERS GRP IN | Heating and Air Conditioning Systems | Heat / Cool Amana Amana 14,700 BTU ×92 Mitsubishi Electric PUZ-A24NHA7-BS 24,000 BTU · Condensing Unit ×1 SUZ-KA24NA2 24,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2024 | Signed-off | PRIME PIPING & HEATING IN | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2024 | Signed-off | PRIME PIPING & HEATING IN | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2025 | Complete | EP ELECTRIC NY LLC | General Wiring |
| 11/30/2023 | Complete | ACCURATE ELEC'L CORP. | General Wiring |
| 07/25/2023 | Complete | POWER DIRECT ELECTRIC INC | — |
| 05/19/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2024 | Signed-off | CITY WIDE BUILDERS GRP IN | 7 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2024 | Signed-off | CITY WIDE BUILDERS GRP IN | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/01/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/30/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/07/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 11/21/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/09/2023 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 09/12/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/28/2023 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 06/08/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/11/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/21/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/21/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/27/2023 | Pass-Final House Connection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/09/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 04/09/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 04/09/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 04/09/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 04/09/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 04/09/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 04/09/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 04/09/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 04/09/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 04/09/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 04/09/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 04/09/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 04/09/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 04/09/2024 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 04/09/2024 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 04/09/2024 | Metering | FAHAD FATEH | energy_progress |
| 04/09/2024 | Lighting controls | FAHAD FATEH | energy_progress |
| 03/26/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 03/26/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 03/26/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 03/26/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 03/26/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 03/26/2024 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 03/26/2024 | Metering | FAHAD FATEH | energy_progress |
| 03/26/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |