| Owner | Filings | Most Recent |
|---|---|---|
| 499 J WYONA IGB LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/11/2019 | $565K | — | Private party → 499 J WYONA IGB LLC | $221/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AG ENGINEERING PLLC | 10 | 06/04/2026 |
| VASILIOS ARTEMIOU PE | 1 | 09/03/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 11 | 03/21/2026 |
| ZV Drafting | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJH CONSTRUCTION CORP | General Contractor | 4 | 07/08/2026 |
| QUALITY PIPING, INC | Fire Protection | 1 | 07/08/2026 |
| NESS MECHANICAL P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 10 | 06/04/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | MJH CONSTRUCTION CORP | 01/23/2026 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 01/15/2026 |
| DOB NOW | Sprinklers | Signed-off | QUALITY PIPING, INC | 01/14/2026 |
| DOB NOW | Plumbing | Signed-off | NESS MECHANICAL P & H INC | 01/14/2026 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 01/13/2026 |
| DOB NOW | Construction Fence | Signed-off | MJH CONSTRUCTION CORP | 12/26/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/04/2026 | Signed-off | QUALITY PIPING, INC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/04/2026 | Signed-off | QUALITY PIPING, INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/24/2025 | Permit Issued | S&R ELECTRICAL & MECHANIC | General Wiring |
| 08/18/2022 | Complete | POWER DIRECT ELECTRIC INC | General Wiring |
| 06/15/2022 | Cancelled | POWER DIRECT ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/23/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/19/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/30/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/23/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/22/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/22/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/30/2024 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 08/01/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 06/21/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 02/21/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| 02/08/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/08/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 07/08/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 07/08/2026 | HVAC-R and service water piping design and insulation | SHAHRIAR QUAYYUM | energy_progress |
| 07/08/2026 | HVAC-R and service water heating equipment | SHAHRIAR QUAYYUM | energy_progress |
| 07/08/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 07/08/2026 | HVAC-R and service water heating system controls | SHAHRIAR QUAYYUM | energy_progress |
| 06/18/2026 | Metering | SHAHRIAR QUAYYUM | energy_progress |
| 06/18/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 06/18/2026 | Energy Code Compliance Inspections | SHAHRIAR QUAYYUM | progress |
| 06/18/2026 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |
| 06/18/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 06/18/2026 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 06/18/2026 | Structural Stability – Alterations of existing buildings | SHAHRIAR QUAYYUM | special |
| 06/18/2026 | Interior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 06/18/2026 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 06/18/2026 | Air barrier - visual inspection | SHAHRIAR QUAYYUM | energy_progress |
| 06/02/2026 | Maintenance information | SHAHRIAR QUAYYUM | energy_progress |
| 06/02/2026 | Structural Stability – Alterations of existing buildings | SHAHRIAR QUAYYUM | special |
| 06/02/2026 | Air barrier - visual inspection | SHAHRIAR QUAYYUM | energy_progress |
| 06/02/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 06/02/2026 | Metering | SHAHRIAR QUAYYUM | energy_progress |
| 06/02/2026 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 06/02/2026 | Interior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 06/02/2026 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 06/02/2026 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |