| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/07/2023 | Signed-off | JOSEPH MOEHLENHOFF P&H IN | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/21/2025 | Complete | INDY ELECTRIC CORP. | General Wiring |
| 01/20/2023 | Complete | FRIED ELECTRIC CO. | General Wiring |
| Owner | Filings | Most Recent |
|---|---|---|
| GREENLINE BLDG CONSULTANTS | 6 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ADB ASSOCIATES | 2 | 01/06/2026 |
| LESLIE M. GOOD ARCHITECTS | 1 | 11/07/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| ACDE GROUP | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CIMA CONTRACTOR INC | General Contractor | 3 | 03/21/2026 |
| JOSEPH MOEHLENHOFF P&H IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SHAHRISH SHUVO ENGINEERIN | 8524 | 1 | 11/07/2023 |
| AURORA BUILDING CONSULTAN | 9710 | 1 | 08/18/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | JOSEPH MOEHLENHOFF P&H IN | 05/30/2025 |
| DOB NOW | General Construction | Permit Issued | CIMA CONTRACTOR INC | 09/06/2024 |
| BIS | — | ISSUED | L&T CONSULTANTS LLC | 02/27/2023 |
| BIS | PL | ISSUED | AL PLUMBING & CONT. INC | 02/21/2023 |
| BIS | PL | ISSUED | ZARA PLUMBING CORP | 07/24/2003 |
| BIS | — | ISSUED | GENCO BUILDERS | 07/02/2003 |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/18/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/28/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/11/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 07/07/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/02/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/12/2026 | Insulation placement and R values | NOEL WONG | energy_progress |
| 01/12/2026 | Tenant Protection Plan Compliance | NOEL WONG | special |
| 01/12/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | NOEL WONG | special |
| 01/12/2026 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 01/12/2026 | Fire-Resistance Rated Construction | NOEL WONG | progress |
| 01/12/2026 | Lowest Floor Elevation | NOEL WONG | progress |
| 01/12/2026 | Energy Code Compliance Inspections | NOEL WONG | progress |
| 01/12/2026 | Interior lighting power | NOEL WONG | energy_progress |
| 01/12/2026 | Fenestration and door U-factor and product ratings | NOEL WONG | energy_progress |
| 01/12/2026 | Fenestration air leakage | NOEL WONG | energy_progress |
| 01/06/2026 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | NOEL WONG | special |
| 01/06/2026 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 01/06/2026 | Tenant Protection Plan Compliance | — | special |
| 01/06/2026 | Energy Code Compliance Inspections | NOEL WONG | progress |
| 01/06/2026 | Fire-Resistance Rated Construction | NOEL WONG | progress |
| 01/06/2026 | Lowest Floor Elevation | NOEL WONG | progress |
| 01/06/2026 | Fenestration air leakage | NOEL WONG | energy_progress |
| 01/06/2026 | Interior lighting power | NOEL WONG | energy_progress |
| 01/06/2026 | Insulation placement and R values | NOEL WONG | energy_progress |
| 01/06/2026 | Fenestration and door U-factor and product ratings | NOEL WONG | energy_progress |
| 11/07/2023 | Tenant Protection Plan Compliance | Shahrish Shuvo | special |