← Back
Office with commercial, 7-19 stories
5 EAST 38 STREET
MANHATTAN · Midtown-Times Square · BIN 1017227
💬 Discuss this project
1920Year Built
12Stories
O6Building Class
C5-2.5Zoning
82,878 sfGross Floor Area
28Units
LL97 Covered4 Open Violations ▸FISP: SWARMP
Office with commercial, 7-19 stories · Owner of record: 6 EAST 39TH ST. HOLDINGS LLC · 7,406 sf lot · 11.19 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalFire ProtectionEquipment
Permit Issued — active, not yet Signed-off
Roof2p · 2 filings · 6 docs
Floor 14p · 1 filing · 12 docs
MezzanineUnder Construction15p · 3 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SOHO CONTRACTING1507/08/2026
EJMB REALTY4107/08/2026
BK CONSTRUCTIONDBA SRT CONSTRUCTION304/09/2026
6 EAST 39TH ST. HOLDINGS LLC3303/22/2026
OWNER OF 6 EAST 39 ST103/22/2026
THE OWNER OF103/22/2026
OWNER OF 5 E 38 ST103/22/2026
WINTER MANAGEMENT203/22/2026
TRIAL HOUSE LEASING CORP103/22/2026
TAKOME ENTERPRISES103/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GREEN LIGHT EXPEDITING LLC603/21/2026
CARLOS RAMIREZ303/21/2026
MUNICIPAL BUILDING CONSULTANTS303/21/2026
SPRING SCAFFOLDING LLC403/21/2026
J SIBAJA KITCHEN VENTILATION203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SPRING SCAFFOLDING LLCGeneral Contractor1307/08/2026
SOHO CONTRACTING CORPGeneral Contractor1007/08/2026
ISTATS MAINTENANCE CORPGeneral Contractor603/21/2026
J. SIBAJA KITCHEN AND VE*General Contractor507/08/2026
FIRE ZONE VENTILATION & SGeneral Contractor307/08/2026
PREMIER SANITATION LLCGeneral Contractor303/21/2026
DICAPUA, JOHNElectrical203/21/2026
JOHN DICAPUAElectrical203/21/2026
ACCURATE MECHANICAL INCFire Protection107/08/2026
P & D MECHANICAL CORPFire Protection107/08/2026
BELLET CONSTRUCTION CO.INGeneral Contractor104/09/2026
BK CONSTRUCTION SVCS INCGeneral Contractor104/09/2026
ALEXANDER EUGENEElectrical103/21/2026
UNIQUE MECHANICAL CORPGeneral Contractor107/08/2026
CHETRAM, RISHIRAMElectrical103/21/2026
GREEN, JElectrical103/21/2026
IRVING BAPTISTEElectrical103/21/2026
JOSEPH CASSESE, JR.Electrical103/21/2026
MOHABIR, JOSEPHElectrical103/21/2026
P&H ELECT D/B/A MAGE ELECElectrical103/22/2026
QUINTANA, DAVIDElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SALAMON ENGINEERING PLLC1264201/22/2026
GIOVANNI ZAPATA R.A.3882311/30/2023
BKH ARCHITECT, PLLC6255102/27/2023
MCEVOY ARCHTECTS PC7037209/07/2022
STARTECH ENGINEERING P.C.1041109/07/2022
Building Lifecycle
All (166)Filed (19)Permit Issued (30)Signed Off (8)Facade (FISP) (15)Violation (60)Inspection (2)Objection (2)Special Inspection (30)
01/26/2026
Signed off — Alteration
Facade repair
M01269778-I1
01/26/2026
Special inspection requirement — Masonry
David Salamon
01/26/2026
Special inspection requirement — Final
David Salamon
01/22/2026
Filed — Alteration
Facade repair
M01269778-P1
01/19/2026
Special inspection requirement — Final
David Salamon
01/19/2026
Special inspection requirement — Masonry
David Salamon
12/19/2025
Cycle 9 facade report signed — SWARMP
12/17/2025
Cycle 9 facade inspection completed
12/11/2025
Signed off — Alteration
INSTALLATION OF A NEW SIDEWALK SHED AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION
M01246675-I1
10/29/2025
Cycle 9 facade report submitted
10/21/2025
Permit issued — Sprinklers
M00550709-S2-EW-SP
09/02/2025
Permit issued — General Construction
M01269778-I1-GC
08/19/2025
Filed — Alteration
Facade repair
M01269778-I1
08/11/2025
Permit issued — Suspended Scaffold
M01268891-I1-SC
08/08/2025
Filed — Alteration
M01268891-I1
06/26/2025
Permit issued — Sidewalk Shed
M01246675-I1-SH
06/25/2025
Filed — Alteration
INSTALLATION OF A NEW SIDEWALK SHED AS INDICATED ON PLANS. THERE WILL BE NO CHANGE IN THE USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION
M01246675-I1
05/22/2025
Signed off — Alteration
M00273770-I1
05/20/2025
Filed — Alteration
M01214496-I1
04/30/2025
Permit issued — Mechanical Systems
M00716217-I1-MS
02/17/2025
Inspection — Certified StandPipe - SD - Alarm Sys 64/09 - Finish
Certified
View inspection ↗
02/17/2025
Inspection — Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)
Certified
View inspection ↗
01/23/2025
Signed off — Alteration
M00992311-I1
06/21/2024
Permit issued — Sidewalk Shed
M00273770-I1-SH
03/25/2024
Permit issued — Mechanical Systems
M00716217-I1-MS
03/25/2024
Violation issued (ECB, closed)
Construction
01/19/2024
Filed — Alteration
M00992311-I1
01/19/2024
Permit issued — Suspended Scaffold
M00992311-I1-SC
12/01/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
GIOVANNI ZAPATA
12/01/2023
Special inspection requirement — Final
GIOVANNI ZAPATA
12/01/2023
Special inspection requirement — Mechanical Systems
GIOVANNI ZAPATA
11/30/2023
Filed — Alteration
HEREWITH TO PROPOSE INSTALL NEW PRECIPITATOR FOR EXHAUST SYST. AND VENT SYSTEM, AS PER PLANS FOR EXISTING EATING AND DRINKING ESTABLISHMENT. FILED UNDER APPL. # 123009564 NO CHANGES IN OCCUPANCY, USE, GROUP OR EGRESS UNDER THIS APPLICATION.
M00716217-P1
11/22/2023
Violation issued (ECB, closed)
Construction
11/22/2023
Violation issued (ECB, closed)
Unknown
11/15/2023
Special inspection requirement — Final
GIOVANNI ZAPATA
11/15/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
GIOVANNI ZAPATA
11/15/2023
Special inspection requirement — Mechanical Systems
GIOVANNI ZAPATA
09/21/2023
Permit issued — Mechanical Systems
M00716217-I1-MS
08/22/2023
Permit issued — Construction Fence
M00550709-S4-FN
08/13/2023
Filed — Alteration
Installation of temporary construction fence
M00550709-S4
08/10/2023
Permit issued — Sprinklers
M00550709-S2-EW-SP
06/21/2023
Permit issued — Sidewalk Shed
M00273770-I1-SH
03/06/2023
Signed off — Alteration
DIRECT REPLACE TWO A/C CONDENSERS ON ROOF SERVING SUITE 1200 ON 12th FLOOR
M00834985-I1
03/04/2023
Permit issued — Mechanical Systems
M00834985-I1-MS
02/27/2023
Filed — Alteration
DIRECT REPLACE TWO A/C CONDENSERS ON ROOF SERVING SUITE 1200 ON 12th FLOOR
M00834985-I1
10/02/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
OWEN MCEVOY
10/02/2022
Special inspection requirement — Final
OWEN MCEVOY
10/02/2022
Special inspection requirement — Insulation placement and R values
OWEN MCEVOY
10/02/2022
Special inspection requirement — Permanent certificate
OWEN MCEVOY
10/02/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
OWEN MCEVOY
09/26/2022
Objection resolved — Addressed
09/21/2022
Permit issued — General Construction
M00550709-I1-GC
09/18/2022
Objection raised — Admin
09/07/2022
Filed — Alteration
Installation of temporary construction fence
M00550709-P1
09/07/2022
Filed — Alteration
Installation of temporary construction fence
M00550709-S1
09/07/2022
Filed — Alteration
Installation of temporary construction fence
M00550709-S2
09/06/2022
Filed — Alteration
Installation of temporary construction fence
M00550709-S3
08/12/2022
Special inspection requirement — Structural Steel - Welding
08/12/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
08/12/2022
Special inspection requirement — Post-installed Anchors
Latest 60 of 166 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedACCURATE MECHANICAL INC10/21/2025
DOB NOWGeneral ConstructionSigned-offBELLET CONSTRUCTION CO.IN09/02/2025
DOB NOWSuspended ScaffoldPermit IssuedSAFEGUARD INSTALLATION IN08/11/2025
DOB NOWSidewalk ShedSigned-offBK CONSTRUCTION SVCS INC06/26/2025
DOB NOWMechanical SystemsPermit IssuedJ. SIBAJA KITCHEN AND VE*04/30/2025
DOB NOWSidewalk ShedSigned-offSOHO CONTRACTING CORP06/21/2024
DOB NOWMechanical SystemsPermit IssuedJ. SIBAJA KITCHEN AND VE*03/25/2024
DOB NOWSuspended ScaffoldSigned-offSOHO CONTRACTING CORP01/19/2024
DOB NOWMechanical SystemsPermit IssuedJ. SIBAJA KITCHEN AND VE*09/21/2023
DOB NOWConstruction FencePermit IssuedISTATS MAINTENANCE CORP08/22/2023
DOB NOWSprinklersPermit IssuedP & D MECHANICAL CORP08/10/2023
DOB NOWSidewalk ShedSigned-offSOHO CONTRACTING CORP06/21/2023
DOB NOWMechanical SystemsSigned-offUNIQUE MECHANICAL CORP03/04/2023
DOB NOWGeneral ConstructionPermit IssuedISTATS MAINTENANCE CORP09/21/2022
DOB NOWSidewalk ShedSigned-offSOHO CONTRACTING CORP07/07/2022
DOB NOWMechanical SystemsPermit IssuedFIRE ZONE VENTILATION S06/06/2022
DOB NOWGeneral ConstructionPermit IssuedPREMIER SANITATION LLC02/25/2022
DOB NOWSidewalk ShedSigned-offSOHO CONTRACTING CORP06/25/2021
DOB NOWMechanical SystemsSigned-offFIRE ZONE VENTILATION S02/04/2021
DOB NOWSidewalk ShedSigned-offSOHO CONTRACTING CORP02/02/2021
DOB NOWSidewalk ShedSigned-offSOHO CONTRACTING CORP06/24/2020
DOB NOWSidewalk ShedSigned-offSOHO CONTRACTING CORP01/10/2020
DOB NOWSidewalk ShedSigned-offSOHO CONTRACTING CORP12/02/2019
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC12/26/2018
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC12/26/2018
DOB NOWSupported ScaffoldSigned-offSPRING SCAFFOLDING LLC03/28/2018
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC03/01/2018
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC02/07/2018
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC01/08/2018
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC10/26/2017
BISOTISSUEDSOHO CONTRACTING CORP01/11/2023
BISOTISSUEDSOHO CONTRACTING CORP01/11/2022
BISOTISSUEDSOHO CONTRACTING CORP01/28/2021
BISOTISSUEDSOHO CONTRACTING CORP06/25/2020
BISEQISSUEDSPRING SCAFFOLDING LLC03/23/2020
BISOTISSUEDSOHO CONTRACTING CORP06/24/2019
BISEQISSUEDSPRING SCAFFOLDING LLC03/28/2019
BISOTISSUEDSOHO CONTRACTING CORP06/25/2018
BISOTISSUEDSOHO CONTRACTING CORP05/25/2018
BISEQISSUEDSPRING SCAFFOLDING LLC03/29/2018
+ 40 more permits on file
1 project · most recent 08/13/2023
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/13/2023Permit IssuedISTATS MAINTENANCE CORPHeating and Air Conditioning Systems
Heat / Cool
Daikin DZ14SA0241A 24,000 BTU · Condensing Unit ×2
3 projects · most recent 07/22/2025
General Wiring
FiledStatusContractorScope
07/22/2025Permit IssuedHIGH QUALITY ELEC.OF NYC—
05/01/2025Permit IssuedP&H ELECT D/B/A MAGE ELECGeneral Wiring
11/29/2023Permit IssuedPALANT ELEC'L CONTR'G COR—
1 project · most recent 08/13/2023
Fence
FiledStatusContractorScope
08/13/2023Permit IssuedACCURATE MECHANICAL INCFence
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
02/17/2025Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
02/17/2025Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet)CertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 33
DateRequirementInspectorRole
01/26/2026MasonryDavid Salamonspecial
01/26/2026FinalDavid Salamonprogress
01/19/2026FinalDavid Salamonprogress
01/19/2026MasonryDavid Salamonspecial
12/01/2023Fire-Resistant Penetrations and JointsGIOVANNI ZAPATAspecial
12/01/2023FinalGIOVANNI ZAPATAprogress
12/01/2023Mechanical SystemsGIOVANNI ZAPATAspecial
11/15/2023FinalGIOVANNI ZAPATAprogress
11/15/2023Fire-Resistant Penetrations and JointsGIOVANNI ZAPATAspecial
11/15/2023Mechanical SystemsGIOVANNI ZAPATAspecial
10/02/2022Fenestration and door U-factor and product ratingsOWEN MCEVOYenergy_progress
10/02/2022FinalOWEN MCEVOYprogress
10/02/2022Insulation placement and R valuesOWEN MCEVOYenergy_progress
10/02/2022Permanent certificateOWEN MCEVOYenergy_progress
10/02/2022Fire-Resistant Penetrations and JointsOWEN MCEVOYspecial
08/12/2022Structural Steel - Welding—special
08/12/2022Structural Stability – Alterations of existing buildings—special
08/12/2022Post-installed Anchors—special
08/12/2022Final—progress
08/12/2022Structural Steel - Details—special
08/12/2022Structural Steel - High Strength Bolting—special
08/10/2022Fenestration and door U-factor and product ratingsOWEN MCEVOYenergy_progress
08/10/2022Fire-Resistant Penetrations and JointsOWEN MCEVOYspecial
08/10/2022Permanent certificateOWEN MCEVOYenergy_progress
08/10/2022Insulation placement and R valuesOWEN MCEVOYenergy_progress
Latest 25 of 33.
▾Documents — 318 on file (BIS + DOB NOW)
▸Plans & Drawings19
▸DOB NOWPlans/Sketch17
09/06/2026M00001153-I1Request digital key ↗
09/06/2026M00030308-I1Request digital key ↗
09/01/2026M00550709-I1Request digital key ↗
Showing 3 of 17 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00273770-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/04/2026M00460212-I1Request digital key ↗
▸Applications & Permits69
▸BISPLAN / WORK APPROVAL APPLICATION38
02/11/2026121577515Open ↗
02/10/2026121577515Open ↗
02/06/2026121577515Open ↗
Showing 3 of 38 on file for this type
▸BISWORK PERMIT APPLICATION25
06/25/2019121577515Open ↗
06/27/2018121577515Open ↗
05/29/2018121577515Open ↗
Showing 3 of 25 on file for this type
▸BISPLACE OF ASSEMBLY5
10/05/2023123025092Open ↗
10/26/2021123025092Open ↗
01/10/2020123025092Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
06/11/2020121577515Open ↗
▸Seals & Professional Certifications87
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION17
03/06/2023123025092Open ↗
03/27/2020140751639Open ↗
09/01/2017120318548Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature17
09/05/2026M00273770-I1Open ↗
09/01/2026M00550709-I1Open ↗
09/01/2026M00550709-S1Open ↗
Showing 3 of 17 on file for this type
▸DOB NOWProgress Inspector Seal & Signature15
09/02/2026M00716217-P1Open ↗
09/01/2026M00550709-P1Open ↗
09/01/2026M00550709-P1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature12
09/02/2026M00716217-P1Open ↗
09/02/2026M00716217-P1Open ↗
09/01/2026M00550709-P1Open ↗
Showing 3 of 12 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT8
03/28/2018140751639Open ↗
05/24/2017123064851Open ↗
04/13/2017123025092Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST7
05/24/2017123064851Open ↗
02/15/2017123009564Open ↗
03/17/2015122333698Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM5
03/25/2013121577515Open ↗
03/25/2013121577515Open ↗
09/05/2012121360133Open ↗
Showing 3 of 5 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
03/28/2018140751639Open ↗
09/09/2015140400581Open ↗
09/09/2015140400616Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY3
03/28/2018140751639Open ↗
09/09/2015140400581Open ↗
09/09/2015140400616Open ↗
▸Trade Schedules & Equipment11
▸BISSCHEDULE B - PLUMBING4
09/27/2012120318548Open ↗
07/30/2012120318548Open ↗
Showing 2 of 4 on file for this type
▸BISSELF-CERT PLUMBING NOTICE4
02/11/2013120318548Open ↗
01/10/2013120318548Open ↗
12/18/2012120318548Open ↗
Showing 3 of 4 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA2
05/15/2018123120737Open ↗
12/28/2017123120737Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
09/29/2014122138686Open ↗
▸Safety & Tenant Protection5
▸BISTenant Protection Plan and Notes2
04/27/2018123213209Open ↗
02/15/2017123009564Open ↗
▸BISDS1-Demolition Submittal Certification Form2
11/07/2014122138686Open ↗
Showing 1 of 2 on file for this type
▸BISANTI-HARASSMENT CHECKLIST: CLINTON1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos24
▸DOB NOWDEP ACP-5: Asbestos Assessment Report12
09/01/2026M00550709-I1Open ↗
09/01/2026M00550709-S1Open ↗
09/01/2026M00550709-S2Open ↗
Showing 3 of 12 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)9
05/24/2017123064851Open ↗
02/15/2017123009564Open ↗
03/17/2015122333698Open ↗
Showing 3 of 9 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
04/27/2018123213209Open ↗
07/31/2017120947761Open ↗
02/15/2017123009564Open ↗
Showing 3 of 6 on file for this type
▸BISEMERGENCY LIGHTING - PA1
01/11/2024123025092Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
02/11/2026121577515Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
07/31/2017120947761Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
02/11/2026121577515Open ↗
▸BISTECHNICAL REPORT: ENERGY1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026M00460212-I1Open ↗
▸Inspections & Test Reports6
▸BISTECHNICAL REPORT: RESPONSIBILITY3
03/28/2018140751639Open ↗
09/09/2015140400581Open ↗
09/09/2015140400616Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
07/31/2017120947761Open ↗
04/09/2014120947761Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
04/09/2014120947761Open ↗
▸Approvals, Objections & Sign-offs20
▸BISADMINISTRATIVE OBJECTIONS6
12/19/2022104253004Open ↗
03/25/2013121577515Open ↗
09/05/2012121360133Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
02/12/2026121577515Open ↗
03/27/2020140751639Open ↗
05/15/2018123120737Open ↗
Showing 3 of 6 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE2
03/06/2023123213209Open ↗
04/27/2018123213209Open ↗
▸BISSUPERSEDING LETTER2
05/29/2018121577515Open ↗
06/06/2013121360133Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
03/06/2023123025092Open ↗
03/06/2023123025092Open ↗
▸BISSHED LETTER1
06/06/2013121360133Open ↗
▸BISFINAL1
02/11/2026121577515Open ↗
▸Cost, Insurance & Ownership23
▸BISCOST AFFIDAVIT22
02/11/2026121577515Open ↗
03/06/2023123025092Open ↗
12/19/2022104253004Open ↗
Showing 3 of 22 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
02/11/2026121577515Open ↗
▸Filing & Intake Forms28
▸BISEFILING COVER SHEET11
04/27/2018123213209Open ↗
08/24/2017123120737Open ↗
05/24/2017123064851Open ↗
Showing 3 of 11 on file for this type
▸BISADDITIONAL INFORMATION10
02/11/2026121577515Open ↗
12/19/2024123025092Open ↗
01/17/2023123025092Open ↗
Showing 3 of 10 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET4
03/28/2018140751639Open ↗
09/09/2015140400581Open ↗
09/09/2015140400616Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
03/27/2020140751639Open ↗
05/15/2018123120737Open ↗
12/04/2017121577515Open ↗
▸Other Documents14
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION10
09/18/2017120947761Open ↗
07/31/2017120947761Open ↗
07/31/2017120947761Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWManufacturer's Specifications2
08/13/2026M00992311-I1Open ↗
08/13/2026M01268891-I1Open ↗
▸DOB NOWCalculations2
08/13/2026M00992311-I1Open ↗
08/13/2026M01268891-I1Open ↗