| Owner | Filings | Most Recent |
|---|---|---|
| TWO TREES | 78 | 07/08/2026 |
| DOMINO A LLC DOMINO B | 60 | 03/21/2026 |
| PLATINUM SERVICES NY | 9 | 03/22/2026 |
| Two Trees Management | 8 | 03/22/2026 |
| OWNERS REP | 4 | 07/08/2026 |
| DOMINO A PARTNERS | 4 | 03/21/2026 |
| COLGATE ENTERPRISES | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KEITH BURNS ARCHITECT | 2 | 09/18/2025 |
| A M ENGINEERING SERVICES PC | 1 | 09/03/2025 |
| ARQUITECTURA VARELA | 3 | 06/10/2025 |
| GEORGE J. XERAKIAS, PE | 1 | 05/16/2025 |
| COSENTINI ASSOCIATES | 9 | 12/11/2024 |
| DENCITYWORKS ARCHITECTURE PLLC. | 5 | 10/29/2024 |
| ASHRAF CORP | 16 | 07/31/2024 |
| LOMBARDO PROFESSIONAL ENGINEERING | 8 | 07/18/2024 |
| GREEN RIVER ENVIRONMENTAL ENGINEERI | 1 | 12/13/2023 |
| TOHFAZ UDDIN PE PC | 7 | 05/15/2023 |
| MJ ENGINEERING & DESIGN | 3 | 02/03/2023 |
| ALBER CAMARGO | 2 | 01/26/2023 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 10/21/2022 |
| MCLAREN ENGINEERING GROUP | 1 | 09/07/2021 |
| LAWLESS AND MANGIONE ARCHITECTS AND | 1 | 08/30/2021 |
| ANDREW FORMICHELLA | 1 | 06/05/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| DVA Advisors | 14 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 3 | 03/21/2026 |
| PLATINUM SERVICES NY | 4 | 03/21/2026 |
| SYNCHRON EXPEDITING | 4 | 03/21/2026 |
| KD DESIGNS | 15 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 6 | 03/21/2026 |
| GALLAGHER BASSETT SERVICES | 2 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 8 | 03/21/2026 |
| 4444 PPPP CORP | 6 | 03/21/2026 |
| HIERARCH-E | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ARSENAL SCAFFOLD INC | General Contractor | 20 | 07/08/2026 |
| 316 KENT CONSTRUCTION LLC | General Contractor | 11 | 07/08/2026 |
| ELICC AMERICAS CORPORATION | General Contractor | 10 | 07/08/2026 |
| TRISTATE FIRE SPRINK INC | Fire Protection | 7 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 6 | 03/21/2026 |
| DEFALCO CONSTRUCTION INC | General Contractor | 5 | 07/08/2026 |
| PACE PLUMBING CORP | Plumbing | 3 | 07/08/2026 |
| INNOVATIVE VENTURES TEAM | General Contractor | 2 | 04/09/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 2 | 07/08/2026 |
| JPC CONTRACTING INC | General Contractor | 2 | 07/08/2026 |
| WINICK PRODUCTIONS, LLC | General Contractor | 2 | 03/21/2026 |
| NASH ELECTRIC SERVICES IN | Electrical | 1 | 03/22/2026 |
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 1 | 07/02/2026 |
| J. SIBAJA KITCHEN AND VE* | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RYAN SPECIAL ENGINEERING | 2018 | 2 | 09/18/2025 |
| AM ENGINEERING SERVICES P | 7975 | 1 | 09/03/2025 |
| THE RAJIV INC | 9613 | 3 | 06/10/2025 |
| GEORGE J. XERAKIAS, PE | 1658 | 1 | 05/16/2025 |
| BIG APPLE GROUP NY, LLC | 1258 | 5 | 12/11/2024 |
| BIG APPLE GROUP NY A RMA | 9168 | 5 | 10/29/2024 |
| LOMBARDO PROF ENGINEERING | 8566 | 7 | 07/18/2024 |
| DOMANI INSPECTION SERVICE | 843 | 2 | 04/26/2024 |
| TOHFAZ UDDIN P.E. | 2001 | 7 | 05/15/2023 |
| MJ ENGINEERING & DESIGN | 5546 | 1 | 01/26/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | INNOVATIVE VENTURES TEAM | 03/20/2026 |
| DOB NOW | Mechanical Systems | Signed-off | J. SIBAJA KITCHEN AND VE* | 10/07/2025 |
| DOB NOW | Plumbing | Permit Issued | A&H EXPRESS PLBG&HTG CORP | 07/31/2025 |
| DOB NOW | General Construction | Signed-off | JPC CONTRACTING INC | 06/17/2025 |
| DOB NOW | General Construction | Permit Issued | INNOVATIVE VENTURES TEAM | 06/11/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | ELM SUSPENSION SYSTEMS | 05/19/2025 |
| DOB NOW | General Construction | Signed-off | JPC CONTRACTING INC | 04/01/2025 |
| DOB NOW | Sprinklers | Signed-off | TRISTATE FIRE SPRINK INC | 12/09/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ARSENAL SCAFFOLD INC | 08/22/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 07/16/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ARSENAL SCAFFOLD INC | 07/02/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 06/06/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 06/06/2024 |
| DOB NOW | Earth Work | Signed-off | 316 KENT CONSTRUCTION LLC | 05/29/2024 |
| DOB NOW | General Construction | Permit Issued | 316 KENT CONSTRUCTION LLC | 05/07/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ARSENAL SCAFFOLD INC | 03/04/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 03/04/2024 |
| DOB NOW | Construction Fence | Signed-off | PLATINUM SERVICES NY LLC | 03/04/2024 |
| DOB NOW | Construction Fence | Signed-off | 316 KENT CONSTRUCTION LLC | 02/28/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ARSENAL SCAFFOLD INC | 01/31/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ARSENAL SCAFFOLD INC | 01/31/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ARSENAL SCAFFOLD INC | 01/16/2024 |
| DOB NOW | Standpipe | Signed-off | TRISTATE FIRE SPRINK INC | 12/12/2023 |
| DOB NOW | Sprinklers | Signed-off | TRISTATE FIRE SPRINK INC | 12/12/2023 |
| DOB NOW | Boiler Equipment | Signed-off | PACE PLUMBING CORP | 12/08/2023 |
| DOB NOW | Standpipe | Signed-off | TRISTATE FIRE SPRINK INC | 11/29/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ARSENAL SCAFFOLD INC | 10/27/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 10/16/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 09/06/2023 |
| DOB NOW | Plumbing | Signed-off | PACE PLUMBING CORP | 06/28/2023 |
| DOB NOW | Construction Fence | Signed-off | ARSENAL SCAFFOLD INC | 05/26/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | ARSENAL SCAFFOLD INC | 05/16/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 04/14/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 04/14/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ELICC AMERICAS CORPORATIO | 04/14/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ARSENAL SCAFFOLD INC | 03/11/2023 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | ARSENAL SCAFFOLD INC | 03/10/2023 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | DEFALCO CONSTRUCTION | 03/01/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ARSENAL SCAFFOLD INC | 02/02/2023 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | DEFALCO CONSTRUCTION | 02/02/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/11/2024 | Signed-off | TRISTATE FIRE SPRINK INC | 30,260 heads, 848 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2025 | Permit Issued | DEPENDABLE MECH CORP | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/30/2026 | Complete | MARKS ELECTRIC CORP | General Wiring |
| 04/27/2026 | Complete | MUM ELECTRICAL CORP | — |
| 12/23/2025 | Complete | DAVEN ELECTRIC CORP | — |
| 07/14/2025 | Complete | N.Z. PILGRIM ELECTRIC INC | General Wiring |
| 04/09/2025 | Complete | ELPO ELECTRICAL CONTG INC | General Wiring |
| 01/27/2025 | Permit Issued | USIS ELECTRIC INC | 3 meters, 3 new_meters |
| 06/20/2024 | Complete | USIS ELECTRIC INC | General Wiring |
| 06/20/2024 | Complete | USIS ELECTRIC INC | General Wiring |
| 04/24/2024 | Complete | USIS ELECTRIC INC | General Wiring |
| 04/24/2024 | Complete | USIS ELECTRIC INC | General Wiring |
| 03/04/2024 | Permit Issued | ILLUMINOUS ELECTRIC CORP. | — |
| 05/16/2023 | Complete | NASH ELECTRIC SERVICES IN | — |
| 04/03/2023 | Complete | USIS ELECTRIC INC | — |
| 01/24/2023 | Complete | NASH ELECTRIC SERVICES IN | — |
| 01/24/2023 | Complete | NASH ELECTRIC SERVICES IN | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/27/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/07/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 12/11/2025 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/27/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 06/10/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/24/2024 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/20/2024 | Pass-Final SP - More than 10 Requested Floors | Pass | View ↗ |
| 05/14/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/13/2024 | Pass-Final SD - More than 10 Requested Floors | Pass | View ↗ |
| 05/11/2024 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 05/10/2024 | Pass-Final SD - Fire Pump | Pass | View ↗ |
| 05/10/2024 | Pass-Final SP - More than 10 Requested Floors | Pass | View ↗ |
| 05/08/2024 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 05/07/2024 | Pass-Final SD - More than 10 Requested Floors | Pass | View ↗ |
| 05/02/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/01/2024 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 04/12/2024 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 02/22/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 10/19/2022 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 10/14/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/06/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/30/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/16/2025 | Lighting in dwelling units | Keith Burns | energy_progress |
| 09/16/2025 | Metering | Keith Burns | energy_progress |
| 09/16/2025 | Final | Keith Burns | progress |
| 09/16/2025 | Fire-Resistance Rated Construction | Keith Burns | progress |
| 09/16/2025 | Maintenance information | Keith Burns | energy_progress |
| 09/16/2025 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 09/16/2025 | Post-installed Anchors | William Ryan | special |
| 09/16/2025 | Tenant Protection Plan Compliance | William Ryan | special |
| 09/16/2025 | Energy Code Compliance Inspections | Keith Burns | progress |
| 08/27/2025 | Tenant Protection Plan Compliance | Albert Munoz | special |
| 08/25/2025 | Final | Albert Munoz | progress |
| 08/25/2025 | Mechanical Systems | Albert Munoz | special |
| 04/02/2025 | Energy Code Compliance Inspections | Vicente Varela | progress |
| 04/02/2025 | Fire-Resistant Penetrations and Joints | Rajiv Fernandez | special |
| 04/02/2025 | Lighting controls | Vicente Varela | energy_progress |
| 04/02/2025 | Interior lighting power | Vicente Varela | energy_progress |
| 04/02/2025 | Tenant Protection Plan Compliance | Rajiv Fernandez | special |
| 12/13/2024 | Sprinkler Systems | Soorjbally Harilall | special |
| 12/13/2024 | Fire-Resistant Penetrations and Joints | Soorjbally Harilall | special |
| 12/13/2024 | Standpipe Systems | Soorjbally Harilall | special |
| 10/30/2024 | Fire-Resistance Rated Construction | Soorjbally Harilall | progress |
| 10/30/2024 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 10/17/2024 | Fire-Resistance Rated Construction | Soorjbally Harilall | progress |
| 10/17/2024 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |
| 09/13/2024 | Fire-Resistant Penetrations and Joints | SOORJBALLY HARILALL | special |