0 Active ViolationsFDNY Report ↗
Flood zone X
Locations of Work
ArchitectureStructuralPlumbingEquipmentLandscapeCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofMcDonald's USA2 filings · 5 docs
Floor 1McDonald's USA4 filings · 9 docs
CellarMcDonald's USA1 filing · 2 docs
Sub-BasementMcDonald's USA3 filings · 7 docs
Filed — no permit issuedMcDonald's USA28p · 6 filings · 12 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Venetian Circle403/21/2026
Waterfalls203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Ggonzalez Bohlereng Company1803/21/2026
Rampulla Associates Architects203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Live Wire Electric 1Electrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Whitestone Associates Engineering8144201/16/2026
Building Lifecycle
All (46)Filed (10)Violation (2)Objection (13)Special Inspection (21)
01/16/2026
Filed — Alteration
S01290717-I1
12/12/2025
Objection raised — Scope
11/18/2025
Objection raised — Scope
11/18/2025
Objection raised — Admin
11/11/2025
Filed — Alteration
Filing plans herewith for the interior build out of a McDonalds restaurant. No change to use, egress, or occupancy.
S01290712-I1
11/03/2025
Filed — Alteration
S01290714-I1
11/03/2025
Filed — Alteration
Filing plans herewith for the building plumbing work related to the interior build out of a McDonalds restaurant. No change to use, egress, or occupancy.
S01290715-I1
11/03/2025
Objection raised — Zoning
11/03/2025
Objection raised — Zoning
11/03/2025
Objection raised — Zoning
11/03/2025
Objection raised — Zoning
11/03/2025
Objection raised — Zoning
11/03/2025
Objection raised — Zoning
10/31/2025
Objection raised — Scope
10/31/2025
Objection raised — Admin
10/23/2025
Special inspection requirement — Interior lighting power
10/23/2025
Special inspection requirement — Fire-Resistance Rated Construction
10/23/2025
Special inspection requirement — Preliminary
10/23/2025
Special inspection requirement — Energy Code Compliance Inspections
10/23/2025
Special inspection requirement — Lighting controls
10/22/2025
Filed — Alteration
S01290710-I1
10/22/2025
Filed — Alteration
Filing plans herewith for the installation of non advertising signage. No change to use, egress, or occupancy.
S01290709-I1
10/10/2025
Filed — Alteration
Application filed for sitework as indicated on plans. No change to use, egress, or occupancy.
S01290705-I1
10/10/2025
Filed — Alteration
Filing plans herewith for the installation of a temporary construction fence. No change to use, egress, or occupancy.
S01290704-I1
10/10/2025
Filed — Alteration
Filing application herewith for the Site plumbing work which includes installation of new on-site inlets, conveyance piping, and underground detention system. No change to use, egress, or occupancy.
S01290707-I1
10/10/2025
Special inspection requirement — Exterior lighting power
10/10/2025
Special inspection requirement — Concrete - Cast-In-Place
10/10/2025
Special inspection requirement — Concrete - Precast
10/09/2025
Special inspection requirement — Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities
Mudar Khantamr
10/09/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Mudar Khantamr
10/09/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Mudar Khantamr
10/06/2025
Special inspection requirement — Final
10/03/2025
Special inspection requirement — Maintenance information
Mudar Khantamr
10/03/2025
Special inspection requirement — Duct leakage testing, insulation and design
Mudar Khantamr
10/03/2025
Special inspection requirement — Shutoff dampers
Mudar Khantamr
10/03/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Mudar Khantamr
10/03/2025
Special inspection requirement — HVAC-R and service water heating equipment
Mudar Khantamr
10/03/2025
Special inspection requirement — HVAC-R and service water heating system controls
Mudar Khantamr
09/29/2025
Special inspection requirement — Final
09/19/2025
Special inspection requirement — Mechanical Systems
Mudar Khantamr
09/19/2025
Special inspection requirement — Final
Mudar Khantamr
09/09/2025
Objection raised — Other
09/05/2025
Objection raised — Scope
08/20/2025
Filed — New Building
S01267805-I1
02/05/1998
Violation issued (ECB, closed)
Construction
12/03/1994
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDPaul Toth Excavation03/31/2015
BISEQISSUEDPaul Toth Excavation03/26/2015
2 projects · most recent 11/03/2025
Storm Water/Sanitary Gas
FiledStatusContractorScope
11/03/2025——Gas, Storm, Water/Sanitary
10/10/2025——Storm, Water/Sanitary
1 project · most recent 10/10/2025
Fence
FiledStatusContractorScope
10/10/2025——Fence
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
10/23/2025Interior lighting power—energy_progress
10/23/2025Fire-Resistance Rated Construction—progress
10/23/2025Preliminary—progress
10/23/2025Energy Code Compliance Inspections—progress
10/23/2025Lighting controls—energy_progress
10/10/2025Exterior lighting power—energy_progress
10/10/2025Concrete - Cast-In-Place—special
10/10/2025Concrete - Precast—special
10/09/2025Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention FacilitiesMudar Khantamrspecial
10/09/2025Subsurface Investigations (Borings/Test Pits)Mudar Khantamrspecial
10/09/2025Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationMudar Khantamrspecial
10/06/2025Final—progress
10/03/2025Maintenance informationMudar Khantamrenergy_progress
10/03/2025Duct leakage testing, insulation and designMudar Khantamrenergy_progress
10/03/2025Shutoff dampersMudar Khantamrenergy_progress
10/03/2025HVAC-R and service water piping design and insulationMudar Khantamrenergy_progress
10/03/2025HVAC-R and service water heating equipmentMudar Khantamrenergy_progress
10/03/2025HVAC-R and service water heating system controlsMudar Khantamrenergy_progress
09/29/2025Final—progress
09/19/2025Mechanical SystemsMudar Khantamrspecial
09/19/2025FinalMudar Khantamrprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
McDonald's USARestaurant / Food ServiceCellar, Sub-basement, Floor 1, Roof
Project S01290717 Alteration · Objections · 01/16/2026
Project S01290712 Alteration · Plan Examiner Review · 11/11/2025
Project S01290714 Alteration · Objections · 11/03/2025
Project S01290715 Alteration · Objections · 11/03/2025
Project S01290709 Alteration · Objections · 10/22/2025
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 36 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/18/2026S01290705-I1Request digital key ↗
08/18/2026S01290704-I1Request digital key ↗
08/18/2026S01290707-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Applications & Permits4
▸BISPLAN / WORK APPROVAL APPLICATION2
03/05/2015520193503Open ↗
04/29/2014520193503Open ↗
▸BISWORK PERMIT APPLICATION2
04/03/2015520193503Open ↗
04/01/2015520193503Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISTAX LOT- TENTATIVE LOT NUMBER ISSUED1
04/29/2014520193503Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026S01267805-I1Open ↗
▸Seals & Professional Certifications14
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/18/2026S01290705-I1Open ↗
08/17/2026S01290712-I1Open ↗
08/17/2026S01290717-I1Open ↗
Showing 3 of 9 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION3
03/05/2015520193503Open ↗
03/05/2015520193503Open ↗
04/29/2014520193503Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
04/29/2014520193503Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
04/29/2014520193503Open ↗
▸Inspections & Test Reports4
▸DOB NOWSOIL REPORT2
08/13/2026S01290707-I1Open ↗
08/13/2026S01290717-I1Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
04/01/2015520193503Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
04/01/2015520193503Open ↗
▸Approvals, Objections & Sign-offs1
▸BISADMINISTRATIVE OBJECTIONS1
04/29/2014520193503Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
04/29/2014520193503Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET1
04/29/2014520193503Open ↗
▸BISADDITIONAL INFORMATION1
03/05/2015520193503Open ↗
▸Other Documents1
▸DOB NOWSite Survey: Initial1
08/13/2026S01267805-I1Open ↗