← Back
Two family converted from one family
50-38 64 STREET
QUEENS · BIN 4054052
💬 Discuss this project
1940Year Built
2Stories
B3Building Class
R4BZoning
1,400 sfGross Floor Area
2Units
0 Open ViolationsFDNY Report ↗
Two family converted from one family · 2,000 sf lot · 0.7 FAR built · Flood zone X
Locations of Work
Electrical
Permit Issued — active, not yet Signed-off
RoofUnder Construction1 filing · 9 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/09/2022$900K—MEK CHAI INC. → Private party$643/sf building
07/23/2021$610K—Private party → MEK CHAI INC.$436/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR101/30/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281101/30/2026
Building Lifecycle
All (10)Filed (1)Permit Issued (1)Violation (1)Special Inspection (7)
02/02/2026
Permit issued — Solar
Q01353542-I1-SL
01/30/2026
Filed — Alteration
Q01353542-I1
01/30/2026
Special inspection requirement — Adhesive-Based Solar Pedestal Bonding Systems
Mina Makar
01/30/2026
Special inspection requirement — Post-installed Anchors
Mina Makar
01/30/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
01/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
01/30/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
01/30/2026
Special inspection requirement — Final
Mina Makar
01/30/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
07/14/1994
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR02/02/2026
1 job · most recent 03/04/2026
FiledStatusContractorScope
03/04/2026CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
01/30/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
01/30/2026Post-installed AnchorsMina Makarspecial
01/30/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
01/30/2026Fire-Resistant Penetrations and JointsMina Makarspecial
01/30/2026Energy Code Compliance InspectionsMina Makarprogress
01/30/2026FinalMina Makarprogress
01/30/2026Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026Q01353542-I1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026Q01353542-I1Open ↗
09/01/2026Q01353542-I1Open ↗
09/01/2026Q01353542-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/01/2026Q01353542-I1Open ↗
09/01/2026Q01353542-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01353542-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01353542-I1Open ↗