| Owner | Filings | Most Recent |
|---|---|---|
| JOSEPH P DAY REALTY | 141 | 03/21/2026 |
| 50 COURT STREET ASSOCIATES | 29 | 03/22/2026 |
| IMA GROUP | 13 | 07/08/2026 |
| BUILDWELL GROUP | 13 | 07/08/2026 |
| 50 COURT ST ASSOC C O JOSEPH P | 13 | 03/21/2026 |
| JOSEPH P. DAY REALTY GROUP | 9 | 03/21/2026 |
| 44 COURT | 7 | 03/21/2026 |
| NEW FORCE CONSTRUCTION | 5 | 03/21/2026 |
| HONEYGROW | 2 | 03/21/2026 |
| JP DAY REALTY | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SOMMER ENGINEERING, PLLC | 1 | 07/22/2026 |
| THE MCGUIRE GROUP ARCHITECTS | 1 | 02/06/2026 |
| LORING CONSULTING ENGINEERS, INC. | 2 | 02/05/2026 |
| ZIMMERMAN WEINTRAUB ASSOCIATES, LLC | 1 | 01/21/2026 |
| JASON M. SCATES, PE | 1 | 01/21/2026 |
| ASHRAF CORP | 1 | 05/20/2024 |
| JACK GREEN ASSOCIATES | 8 | 08/09/2023 |
| KAHN ARCHITECTURE & DESIGN PC | 5 | 11/15/2022 |
| FL&M ENGINEERING DESIGN &INSPECTION | 1 | 10/04/2022 |
| TITAN ENGINEERS PC | 3 | 09/23/2022 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 07/09/2021 |
| SYED ENGINEERING, P.C. | 2 | 12/16/2020 |
| SERMAN ENGINEERING | 1 | 01/17/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 18 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 2 | 03/21/2026 |
| BOYD CONSULTING | 4 | 03/21/2026 |
| GREEN STUDIO | 4 | 03/21/2026 |
| SAFE RISE | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| A.W. & S. CONSTRUCTION CO | General Contractor | 13 | 07/08/2026 |
| TOPLINE GC INC | General Contractor | 11 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 6 | 03/21/2026 |
| CUAN CORP | General Contractor | 4 | 07/04/2026 |
| EL-ROC CONTRACTING OF BK | Plumbing | 3 | 07/08/2026 |
| BUILDWELL GROUP INC | General Contractor | 3 | 03/21/2026 |
| EL-ROC CONTG OF BKLYN INC | Fire Protection | 2 | 07/08/2026 |
| CELTIC GENERAL CONTRACT | General Contractor | 2 | 03/21/2026 |
| LAWRENCE EXTERIOR RESTORATION | General Contractor | 2 | 03/21/2026 |
| BENJAMIN DREBIN | Electrical | 1 | 03/21/2026 |
| EL-ROC CONTG OF BKLYN | Plumbing | 1 | 03/22/2026 |
| MELVYN ZWEBNER | Electrical | 1 | 03/21/2026 |
| A + SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| PLATINUM SERVICES NY LLC | General Contractor | 1 | 07/08/2026 |
| FRANK LA GREGA | Electrical | 1 | 03/21/2026 |
| WILTON CONSTRUCTION MNGRS | General Contractor | 1 | 04/09/2026 |
| ULTIMATE ELECTL CONTG INC | Electrical | 1 | 03/22/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| COLE TECHNOLOGIES/CONTROL | 1290 | 1 | 07/22/2026 |
| SE INSPECTIONS | 7486 | 2 | 02/05/2026 |
| SKYLINE ENGINEERING, PLLC | 267 | 1 | 01/21/2026 |
| CONCRETE SOLUTIONS LAB CO | 5344 | 1 | 01/21/2026 |
| JACK GREEN ASSOCIATES | 422 | 7 | 08/09/2023 |
| LAWRENCE SHACTEL. PE | 1496 | 7 | 11/15/2022 |
| RICHARD H. BALSER ENGINEE | 3028 | 3 | 09/23/2022 |
| SERMAN ENGINEERING | 4685 | 1 | 01/17/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | WILTON CONSTRUCTION MNGRS | 09/01/2026 |
| DOB NOW | General Construction | Permit Issued | CUAN CORP | 07/02/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CUAN CORP | 07/02/2026 |
| DOB NOW | Plumbing | Permit Issued | EL-ROC CONTG OF BKLYN INC | 02/27/2026 |
| DOB NOW | Sprinklers | Signed-off | EL-ROC CONTRACTING OF BK | 02/27/2026 |
| DOB NOW | General Construction | Signed-off | WILTON CONSTRUCTION MNGRS | 02/24/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CUAN | 02/19/2026 |
| DOB NOW | General Construction | Permit Issued | CUAN | 01/29/2026 |
| DOB NOW | Suspended Scaffold | Signed-off | LAWRENCE EXTERIOR REST CO | 12/03/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATINUM SERVICES NY LLC | 05/21/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | LAWRENCE EXTERIOR REST CO | 12/07/2023 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 09/29/2023 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 06/29/2023 |
| DOB NOW | Plumbing | Signed-off | EL-ROC CONTRACTING OF BK | 06/23/2023 |
| DOB NOW | Sprinklers | Signed-off | EL-ROC CONTG OF BKLYN INC | 06/23/2023 |
| DOB NOW | Mechanical Systems | Signed-off | A.W. & S. CONSTRUCTION CO | 04/24/2023 |
| DOB NOW | Structural | Permit Issued | A.W. & S. CONSTRUCTION CO | 04/03/2023 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 03/21/2023 |
| DOB NOW | General Construction | Permit Issued | A.W. & S. CONSTRUCTION CO | 03/21/2023 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 03/21/2023 |
| DOB NOW | Plumbing | Signed-off | A + SPRINKLER CORP | 01/05/2023 |
| DOB NOW | Plumbing | Signed-off | EL-ROC CONTRACTING OF BK | 12/30/2022 |
| DOB NOW | Mechanical Systems | Signed-off | A.W. & S. CONSTRUCTION CO | 11/28/2022 |
| DOB NOW | Mechanical Systems | Signed-off | A.W. & S. CONSTRUCTION CO | 11/17/2022 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 11/16/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | TOPLINE GC INC | 10/17/2022 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 10/05/2022 |
| DOB NOW | Mechanical Systems | Signed-off | A.W. & S. CONSTRUCTION CO | 04/20/2022 |
| DOB NOW | Structural | Permit Issued | A.W. & S. CONSTRUCTION CO | 03/21/2022 |
| DOB NOW | General Construction | Permit Issued | A.W. & S. CONSTRUCTION CO | 02/04/2022 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 02/03/2022 |
| DOB NOW | General Construction | Signed-off | A.W. & S. CONSTRUCTION CO | 02/03/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | TOPLINE GC INC | 10/20/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | TOPLINE GC INC | 08/19/2021 |
| DOB NOW | Supported Scaffold | Permit Issued | LAWRENCE EXTERIOR RESTORA | 07/09/2021 |
| DOB NOW | Supported Scaffold | Permit Issued | TOPLINE GC INC | 12/21/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | TOPLINE GC INC | 10/26/2020 |
| DOB NOW | Mechanical Systems | Permit Issued | CELTIC GENERAL CONTRACT | 02/06/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | BUILDWELL GROUP INC | 01/09/2020 |
| BIS | OT | ISSUED | LAWRENCE EXTERIOR RESTORATION | 03/26/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/13/2026 | Permit Issued | WCK ELECTRIC CORP. | General Wiring |
| 03/06/2026 | Permit Issued | INNER CITY ELEC'L CONTR'S | General Wiring |
| 05/15/2024 | Complete | ILLUMINOUS ELECTRIC CORP. | — |
| 03/01/2023 | Complete | INNER CITY ELEC'L CONTR'S | General Wiring |
| 09/21/2022 | Complete | R.C.M. ELECTRIC CORP. | — |
| 05/26/2020 | Permit Issued | INNER CITY ELEC'L CONTR'S | 11 meters, 1 new_meters |
| 01/08/2020 | Complete | RICHARD NEU | — |
| 05/23/2019 | Permit Issued | INNER CITY ELEC'L CONTR'S | General Wiring |
| 10/21/2018 | Permit Issued | ULTIMATE ELECTL CONTG INC | General Wiring |
| 10/21/2018 | Permit Issued | ULTIMATE ELECTL CONTG INC | General Wiring |
| 09/06/2018 | Permit Issued | ULTIMATE ELECTL CONTG INC | General Wiring |
| 08/03/2018 | Complete | ASTER ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/22/2026 | — | — | 1 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/01/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/27/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/27/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/27/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 06/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/28/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/21/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 11/21/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 11/21/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/21/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 09/09/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/09/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 09/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/15/2025 | Fail-Final Boiler Equipment Inspection | Fail | View ↗ |
| 03/14/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/28/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/25/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/24/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/18/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/18/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/13/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/02/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/25/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/04/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/22/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/06/2026 | Structural Steel - Details | GEORGE ANDERSEN | special |
| 07/06/2026 | Final | GEORGE ANDERSEN | progress |
| 07/06/2026 | Structural Steel - Welding | GEORGE ANDERSEN | special |
| 07/06/2026 | Structural Steel - High Strength Bolting | GEORGE ANDERSEN | special |
| 07/06/2026 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 02/01/2026 | HVAC-R and service water heating equipment | Spencer Goroff | energy_progress |
| 02/01/2026 | Fire-Resistant Penetrations and Joints | Spencer Goroff | special |
| 02/01/2026 | HVAC-R and service water heating system controls | Spencer Goroff | energy_progress |
| 02/01/2026 | Energy Code Compliance Inspections | Spencer Goroff | progress |
| 02/01/2026 | Maintenance information | Spencer Goroff | energy_progress |
| 02/01/2026 | HVAC-R and service water piping design and insulation | Spencer Goroff | energy_progress |
| 01/15/2026 | Duct leakage testing, insulation and design | MINA HANNA | energy_progress |
| 01/15/2026 | Ventilation and air distribution system | MINA HANNA | energy_progress |
| 12/03/2025 | Sprinkler Systems | Spencer Goroff | special |
| 11/20/2025 | Final | Spencer Goroff | progress |
| 09/16/2025 | Final | MINA HANNA | progress |
| 09/16/2025 | Mechanical Systems | MINA HANNA | special |
| 08/14/2023 | Fire-Resistant Penetrations and Joints | JACK GREEN | special |
| 08/14/2023 | Sprinkler Systems | JACK GREEN | special |
| 08/04/2023 | Fire-Resistant Penetrations and Joints | JACK GREEN | special |
| 08/04/2023 | Sprinkler Systems | JACK GREEN | special |
| 09/23/2022 | Subgrade Inspections | LAWRENCE SHACTEL | special |
| 09/23/2022 | Structural Steel - Welding | LAWRENCE SHACTEL | special |
| 09/23/2022 | Demolition | Balser Richard | special |