← Back
Predominantly retail with other uses
50 GRAHAM AVENUE
BROOKLYN · East Williamsburg · BIN 3071565
💬 Discuss this project
1931Year Built
3Stories
K4Building Class
C4-3Zoning
5,250 sfGross Floor Area
1Units
1 Open Violation ▸FDNY Report ↗
Predominantly retail with other uses · 2,500 sf lot · 2.1 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingCivilGeneralOther
Permit Issued — active, not yet Signed-off
RoofUnder Construction17p · 2 filings · 20 docs
Floor 3Under Construction33p · 2 filings · 20 docs
Floor 2Under Construction33p · 2 filings · 20 docs
Floor 1Under Construction32p · 2 filings · 20 docs
CellarUnder Construction32p · 2 filings · 20 docs
Basement1p · 1 filing · 6 docs
Site & exteriorUnder Construction40p · 1 filing · 20 docs
Filed — no permit issued50p · 4 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
50 GRAHAM AVENUE1909/15/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/16/2025$1.1M—Private party → Private party$219/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NAPHTALI DEUTSCH ARCHITECTURE503/21/2026
BRICOLAGE DESIGNS303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JB CONSTRUCTION & DESIGNGeneral Contractor507/08/2026
A. M. PLUMBING COMPANYPlumbing208/12/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SHAHRISH SHUVO ENGINEERIN8524705/29/2026
DEMERARA ENGINEERING, PLL4248103/23/2023
DAVID KATZ, P.E.6087112/12/2022
Building Lifecycle
All (75)Filed (13)Permit Issued (6)Violation (2)Inspection (6)Objection (18)Special Inspection (30)
09/03/2026
Filed — Alteration CO
THIS APPLICATION IS BEING FILED FOR GENERAL CONSTRUCTION WORK ONLY TO RENOVATE EXISTING 3-STORY BUILDING AT THE CELLAR, FIRST, SECOND & THIRD FLOORS, ROOF AND FACADE; ADD TWO ADDITIONAL DWELLING UNITS AND TO OBTAIN NEW CERTIFICATE OF OCCUPANCY.
B01447602-I1
08/24/2026
Special inspection requirement — Lighting controls
08/24/2026
Special inspection requirement — Insulation placement and R values
08/24/2026
Special inspection requirement — Air barrier - visual inspection
08/24/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
08/24/2026
Special inspection requirement — Fenestration air leakage
08/24/2026
Special inspection requirement — Fenestration areas
08/24/2026
Special inspection requirement — Lighting in dwelling units
08/24/2026
Special inspection requirement — Metering
08/18/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
08/18/2026
Special inspection requirement — Energy Code Compliance Inspections
08/18/2026
Special inspection requirement — Final
08/18/2026
Special inspection requirement — Structural Steel - Welding
08/18/2026
Special inspection requirement — Structural Steel - High Strength Bolting
08/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/18/2026
Special inspection requirement — Structural Steel - Details
08/11/2026
Permit issued — Plumbing
B01172355-S3-PL
06/17/2026
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/05/2026
Permit issued — Mechanical Systems
B01388923-I1-MS
05/29/2026
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK AT THE CELLAR, FIRST, SECOND & THIRD FLOORS. NO CHANGE TO EXISTING BULK, FLOOR AREA USE OR OCCUPANCY.
B01172355-P4
05/29/2026
Special inspection requirement — Maintenance information
Shahrish Shuvo
05/29/2026
Special inspection requirement — HVAC-R and service water heating system controls
Shahrish Shuvo
05/29/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Shahrish Shuvo
05/29/2026
Special inspection requirement — Energy Code Compliance Inspections
Shahrish Shuvo
05/29/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
05/20/2026
Special inspection requirement — Maintenance information
Shahrish Shuvo
05/20/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Shahrish Shuvo
05/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
05/20/2026
Special inspection requirement — HVAC-R and service water heating system controls
Shahrish Shuvo
05/20/2026
Special inspection requirement — Energy Code Compliance Inspections
Shahrish Shuvo
05/04/2026
Filed — Alteration
MECHANICAL APPLICATION NEW MECHANICAL SYSTEMS THROUGHOUT BUILDING
B01388923-I1
05/04/2026
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK AT THE CELLAR, FIRST, SECOND & THIRD FLOORS. NO CHANGE TO EXISTING BULK, FLOOR AREA USE OR OCCUPANCY.
B01172355-P3
05/04/2026
Special inspection requirement — Wood – Seismic Resistance
Shahrish Shuvo
05/04/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Shahrish Shuvo
05/04/2026
Special inspection requirement — Structural Wood Frame
Shahrish Shuvo
05/04/2026
Special inspection requirement — Final
Shahrish Shuvo
04/24/2026
Special inspection requirement — Wood – Seismic Resistance
03/05/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
03/02/2026
Violation issued (ECB, closed)
Construction
02/25/2026
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK AT THE CELLAR, FIRST, SECOND & THIRD FLOORS. NO CHANGE TO EXISTING BULK, FLOOR AREA USE OR OCCUPANCY.
B01172355-P1
02/10/2026
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
01/02/2026
Permit issued — Plumbing
B01172355-S3-PL
12/31/2025
Permit issued — Structural
B01172355-S1-ST
12/29/2025
Permit issued — General Construction
B01172355-I1-GC
12/29/2025
Permit issued — Construction Fence
B01172355-S2-FN
04/02/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK AT THE CELLAR, FIRST, SECOND & THIRD FLOORS. NO CHANGE TO EXISTING BULK, FLOOR AREA USE OR OCCUPANCY.
B01172355-S2
03/10/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK AT THE CELLAR, FIRST, SECOND & THIRD FLOORS. NO CHANGE TO EXISTING BULK, FLOOR AREA USE OR OCCUPANCY.
B01172355-S3
02/04/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK AT THE CELLAR, FIRST, SECOND & THIRD FLOORS. NO CHANGE TO EXISTING BULK, FLOOR AREA USE OR OCCUPANCY.
B01172355-S1
01/30/2025
Filed — Alteration
THIS APPLICATION IS BEING FILED FOR PLUMBING WORK AT THE CELLAR, FIRST, SECOND & THIRD FLOORS. NO CHANGE TO EXISTING BULK, FLOOR AREA USE OR OCCUPANCY.
B01172355-I1
11/03/2023
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
11/03/2023
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/28/2023
Objection raised — Other
03/28/2023
Objection resolved — Addressed
03/28/2023
Objection resolved — Addressed
03/28/2023
Objection resolved — Addressed
03/28/2023
Objection resolved — Addressed
03/28/2023
Objection resolved — Addressed
03/28/2023
Objection resolved — Addressed
03/24/2023
Objection raised — Other
03/24/2023
Objection raised — Other
Latest 60 of 75 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedA. M. PLUMBING COMPANY08/11/2026
DOB NOWMechanical SystemsSigned-offJB CONSTRUCTION & DESIGN06/05/2026
DOB NOWPlumbingPermit IssuedA. M. PLUMBING COMPANY01/02/2026
DOB NOWStructuralSigned-offJB CONSTRUCTION DESIGN12/31/2025
DOB NOWGeneral ConstructionPermit IssuedJB CONSTRUCTION DESIGN12/29/2025
DOB NOWConstruction FencePermit IssuedJB CONSTRUCTION DESIGN12/29/2025
BISPLISSUEDNYC WATER MAIN WORKS INC01/13/1999
BISSPISSUEDCAPITOL FIRE SPKL CO,INC08/11/1998
2 projects · most recent 05/04/2026
Heating and Air Conditioning Systems Air Conditioning Systems Associated Ducts and Piping Heating Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
05/04/2026Signed-offJB CONSTRUCTION & DESIGNHeating and Air Conditioning Systems
Heat / Cool
Fujitsu AOU36RLAVM 42,000 BTU · Heat Pump Outdoor ×4
AOU60RLAVM 60,000 BTU · Heat Pump Outdoor ×1
12/12/2022——Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems
Cooling
Carrier 48TCED12 4,000 CFM · Rooftop Unit ×1
Heating
Carrier 48TCED12 224,000 BTU · Rooftop Unit ×1
Ventilation
Carrier 48TCED12 4,000 CFM · Rooftop Unit ×1
Ducts & Piping
1 project · most recent 05/29/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
05/29/2026Permit IssuedA. M. PLUMBING COMPANYGas, Storm, Water/Sanitary
1 project · most recent 01/05/2026
General Wiring
FiledStatusContractorScope
01/05/2026Permit IssuedM.R. ELEC'L SERVICE LLCGeneral Wiring
3 projects · most recent 09/03/2026
Steel Wood Masonry
FiledStatusContractorScope
09/03/2026——Steel
05/29/2026Permit IssuedA. M. PLUMBING COMPANYWood
03/23/2023——Steel, Masonry
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
03/05/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
02/10/2026Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/03/2023Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/03/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
11/03/2021Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/15/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 76
DateRequirementInspectorRole
08/24/2026Lighting in dwelling units—energy_progress
08/24/2026Insulation placement and R values—energy_progress
08/24/2026Air barrier - visual inspection—energy_progress
08/24/2026Lighting controls—energy_progress
08/24/2026Fenestration air leakage—energy_progress
08/24/2026Fenestration areas—energy_progress
08/24/2026Metering—energy_progress
08/24/2026Fenestration and door U-factor and product ratings—energy_progress
08/18/2026Final—progress
08/18/2026Fire-Resistant Penetrations and Joints—special
08/18/2026Structural Steel - High Strength Bolting—special
08/18/2026Structural Steel - Welding—special
08/18/2026Structural Stability – Alterations of existing buildings—special
08/18/2026Energy Code Compliance Inspections—progress
08/18/2026Structural Steel - Details—special
05/29/2026Fire-Resistant Penetrations and JointsShahrish Shuvospecial
05/29/2026Energy Code Compliance InspectionsShahrish Shuvoprogress
05/29/2026HVAC-R and service water piping design and insulationShahrish Shuvoenergy_progress
05/29/2026HVAC-R and service water heating system controlsShahrish Shuvoenergy_progress
05/29/2026Maintenance informationShahrish Shuvoenergy_progress
05/20/2026Fire-Resistant Penetrations and JointsShahrish Shuvospecial
05/20/2026HVAC-R and service water heating system controlsShahrish Shuvoenergy_progress
05/20/2026HVAC-R and service water piping design and insulationShahrish Shuvoenergy_progress
05/20/2026Maintenance informationShahrish Shuvoenergy_progress
05/20/2026Energy Code Compliance InspectionsShahrish Shuvoprogress
Latest 25 of 76.
▾Documents — 72 on file (BIS + DOB NOW)
▸Plans & Drawings15
▸DOB NOWPlans/Sketch15
09/15/2026B01447602-I1Request digital key ↗
08/28/2026B00793578-S1Request digital key ↗
08/28/2026B08032633-I1Request digital key ↗
Showing 3 of 15 on file for this type
▸Seals & Professional Certifications37
▸DOB NOWDPL-1: Design Professional Seal & Signature15
09/15/2026B01447602-I1Open ↗
08/28/2026B00793578-S1Open ↗
08/28/2026B00793578-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWProgress Inspector Seal & Signature13
09/30/2026B01172355-P1Open ↗
09/30/2026B01172355-P1Open ↗
09/05/2026B01172355-S1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/30/2026B01172355-P1Open ↗
09/05/2026B01172355-S1Open ↗
09/05/2026B01172355-S1Open ↗
Showing 3 of 9 on file for this type
▸Safety & Tenant Protection4
▸DOB NOWStreet Tree Checklist3
09/15/2026B01447602-I1Open ↗
08/28/2026B00793578-S1Open ↗
08/15/2026B00793578-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00793578-I1Open ↗
▸Environmental & Asbestos14
▸DOB NOWDEP ACP-5: Asbestos Assessment Report14
09/15/2026B01447602-I1Open ↗
08/28/2026B00793578-S1Open ↗
08/28/2026B08044159-I1Open ↗
Showing 3 of 14 on file for this type
▸Other Documents2
▸DOB NOWProperty Ownership Certification2
09/15/2026B01447602-I1Open ↗
08/15/2026B00793578-I1Open ↗