← Back
Elevator cooperative
52 Gramercy Park North
50 GRAMERCY PARK NORTH · Gramercy · BIN 1087279
💬 Discuss this project
1924Year Built
17Stories
D4Building Class
R9AZoning
65,480 sfGross Floor Area
21Units
LL97 CoveredRent Stabilized3 Open Violations ▸FISP: SWARMP
Elevator cooperative · Owner of record: 50 GRAMERCY PARK INVESTORS, LLC · 7,999 sf lot · 8.19 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction11p · 3 filings · 20 docs
BulkheadUnder Construction1p · 1 filing · 10 docs
Floor 174p · 3 filings · 20 docs
Floor 164p · 3 filings · 20 docs
Floor 15
Floor 14
Floor 13
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2Under Construction15p · 1 filing · 14 docs
Floor 1Under Construction24p · 2 filings · 19 docs
CellarUnder Construction7p · 1 filing · 15 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NEW FORCE CONSTRUCTION1807/08/2026
BROWN HARRIS STEVENS1204/09/2026
KINGS GROUP NY CORP503/22/2026
50 GRAMERCY PARK INVESTORS, LLC103/22/2026
NOW FORCE CONSTRUCTION CO103/22/2026
NENFORCE CONSTRUCTION CO.103/22/2026
SATO CONSTRUCTION303/22/2026
JORDAN COOPER & ASSOCIATES303/21/2026
GRAMERCY PARK HOTEL INVESTORS3103/21/2026
EMS ENTERPRISES203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
WSP409/17/2026
BW ARCHITECTS107/21/2026
NOT APPLICABLE203/23/2026
KMA DESIGNS LLC108/14/2025
SETH P. ROYE ARCHITECT PC110/29/2024
HOWARD L ZIMMERMAN ARCH & ENG DPC101/16/2024
ATOZ CONSULTING ENGINEERS, PC303/11/2022
MORALI ARCHITECTURE403/10/2022
PCS ENGINEERING410/24/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
RIGGING CONSULTANTS403/21/2026
HOWARD L ZIMMERMAN ARCHITECTS203/21/2026
ANTHONY MORALI ARCHITECT PLLC1403/21/2026
KMA DESIGNS LLC203/21/2026
NA & PARTNERS BUILDING CONSULTANTS803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NEW FORCE CONSTRUCTION CORPGeneral Contractor707/08/2026
KINGS GROUP NY CORPGeneral Contractor303/21/2026
AP PLUMBING & HVAC LLCPlumbing207/08/2026
CASTCAPA CONSTRUCTION LLCGeneral Contractor204/09/2026
JOSEPH BRAMANElectrical103/21/2026
KONSTANTINOS KOSTARIDISElectrical103/21/2026
METROPOLITAN OPERA ASSOCIElectrical103/21/2026
NYC DISTRICT COUNCIL OF CElectrical103/21/2026
QEC ELECTRICAL SVCE CORPElectrical103/22/2026
RICHARD GRIMAElectrical103/21/2026
CROSSFIELD PLBG.&HTG.CORPFire Protection107/08/2026
A-LINE CONSTRUCTION CORPGeneral Contractor107/08/2026
FILLER CONSTRUCTION MANGeneral Contractor106/28/2026
MJM CONSTR ASSOCIATES LLCGeneral Contractor109/23/2026
SUPERIOR HVAC INCGeneral Contractor104/09/2026
BYPASS MECHANICAL CORPPlumbing107/08/2026
ALEXANDER EUGENEElectrical103/21/2026
F.S. SITE CORPPlumbing109/25/2026
CAMENZULI, CARMINEElectrical103/21/2026
CITI-WIDE ELECTRIC INCElectrical103/22/2026
FINTAN MURRAYElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SHAHRISH SHUVO ENGINEERIN8524509/17/2026
RAAD7727203/23/2026
PCS ENGINEERING3745210/07/2025
SAG ENGINEERING & CONSULT608110/29/2024
SETH P ROYE ARCHITECT PC8554110/29/2024
HOWARD L ZIMMERMAN ARCHIT1712101/16/2024
ATOZ CONSULTING ENGINEERS3303303/11/2022
ANTHONY MORALI ARCHITECT4810403/10/2022
Building Lifecycle
All (142)Filed (23)Permit Issued (19)Signed Off (5)Facade (FISP) (9)Violation (31)Inspection (3)Objection (22)Special Inspection (30)
09/24/2026
Permit issued — Plumbing
M01407404-S2-PL
09/22/2026
Permit issued — General Construction
M01407404-I1-GC
09/17/2026
Filed — Alteration
Interior modifications to existing Plumbing system related to BOH renovations and upgrades. No change in occupancy, use or egress
M01406289-S2
09/03/2026
Special inspection requirement — Post-installed Anchors
Ari Kamo
07/28/2026
Filed — Alteration
Interior modifications to existing Mechanical system related to Lobby and Restrooms renovations and upgrades. No change in occupancy, use or egress.
M01407404-S2
07/23/2026
Filed — Alteration
Interior modifications to existing Mechanical system related to Lobby and Restrooms renovations and upgrades. No change in occupancy, use or egress.
M01407404-S1
07/23/2026
Filed — Alteration
Modifications to existing Sprinkler system related to Lobby/restroom renovations and upgrades.
M01407423-I1
07/21/2026
Filed — Alteration
Interior modifications to existing Mechanical system related to Lobby and Restrooms renovations and upgrades. No change in occupancy, use or egress.
M01407404-I1
07/21/2026
Special inspection requirement — Post-installed Anchors
07/15/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/13/2026
Special inspection requirement — Sprayed fire-resistant materials
Ari Kamo
07/13/2026
Special inspection requirement — Interior lighting power
Ari Kamo
07/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ari Kamo
07/13/2026
Special inspection requirement — Energy Code Compliance Inspections
Ari Kamo
07/13/2026
Special inspection requirement — Preliminary
Ari Kamo
07/13/2026
Special inspection requirement — Fire-Resistance Rated Construction
Ari Kamo
06/01/2026
Permit issued — General Construction
M01374581-I1-GC
06/01/2026
Permit issued — Plumbing
M01374581-S1-PL
05/26/2026
Special inspection requirement — Sprinkler Systems
05/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
Shahrish Shuvo
05/26/2026
Special inspection requirement — Final
05/26/2026
Special inspection requirement — Mechanical Systems
05/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
Shahrish Shuvo
05/26/2026
Special inspection requirement — Final
Ari Kamo
05/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
Shahrish Shuvo
05/26/2026
Special inspection requirement — Tenant Protection Plan Compliance
Shahrish Shuvo
05/22/2026
Special inspection requirement — Tenant Protection Plan Compliance
Shahrish Shuvo
05/05/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
05/01/2026
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
05/01/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
04/17/2026
Objection resolved — Addressed
04/17/2026
Objection resolved — Addressed
04/17/2026
Objection resolved — Resolved
04/17/2026
Objection resolved — Addressed
04/14/2026
Objection raised — Accessibility
04/13/2026
Objection raised — Scope
04/13/2026
Objection raised — Plumbing
04/13/2026
Objection raised — Scope
03/23/2026
Filed — Alteration
Interior renovation of apartment 2A on the second floor as indicated on plans to add a new bedroom and a new bathroom with new interior partitions and new plumbing fixtures. No change in use, egress, or occupancy is proposed under this application.
M01374581-I1
03/23/2026
Filed — Alteration
Interior renovation of apartment 2A on the second floor as indicated on plans to add a new bedroom and a new bathroom with new interior partitions and new plumbing fixtures. No change in use, egress, or occupancy is proposed under this application.
M01374581-S1
03/18/2026
Special inspection requirement — Lighting in dwelling units
Benjamin Hochberg
03/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NICHOLAS AZADIAN
03/18/2026
Special inspection requirement — Energy Code Compliance Inspections
Benjamin Hochberg
03/18/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Benjamin Hochberg
03/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NICHOLAS AZADIAN
03/18/2026
Special inspection requirement — Energy Code Compliance Inspections
Benjamin Hochberg
03/18/2026
Special inspection requirement — Fire-Resistance Rated Construction
Benjamin Hochberg
03/18/2026
Special inspection requirement — Final
Benjamin Hochberg
02/26/2026
Permit issued — General Construction
M01046766-I1-GC
11/19/2025
Permit issued — Suspended Scaffold
M01108722-I1-SC
10/14/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Walsh
10/14/2025
Special inspection requirement — Post-installed Anchors
Michael Walsh
10/07/2025
Filed — Alteration
Facade Restoration Via Suspended Scaffolding
M01108722-P1
10/01/2025
Special inspection requirement — Post-installed Anchors
Michael Walsh
10/01/2025
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Michael Walsh
08/15/2025
Permit issued — Sidewalk Shed
M01271751-I1-SH
08/15/2025
Permit issued — General Construction
M01046766-I1-GC
08/14/2025
Filed — Alteration
INSTALLATION OF HEAVY DUTY SIDEWALK SHED. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION, ALL WORK TO COMPLY WITH CHAPTER 33 OF NYCBC.
M01271751-I1
02/10/2025
Permit issued — Mechanical Systems
M00980257-I1-MS
11/18/2024
Permit issued — Suspended Scaffold
M01108722-I1-SC
Latest 60 of 142 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedF.S. SITE CORP09/24/2026
DOB NOWGeneral ConstructionPermit IssuedMJM CONSTR ASSOCIATES LLC09/22/2026
DOB NOWGeneral ConstructionPermit IssuedFILLER CONSTRUCTION MAN06/01/2026
DOB NOWPlumbingPermit IssuedBYPASS MECHANICAL CORP06/01/2026
DOB NOWGeneral ConstructionPermit IssuedCASTCAPA CONSTRUCTION02/26/2026
DOB NOWSuspended ScaffoldPermit IssuedSPD CONSTRUCTION CORP11/19/2025
DOB NOWSidewalk ShedPermit IssuedKINGS GROUP NY CORP08/15/2025
DOB NOWGeneral ConstructionPermit IssuedCASTCAPA CONSTRUCTION08/15/2025
DOB NOWMechanical SystemsPermit IssuedSUPERIOR HVAC INC02/10/2025
DOB NOWSuspended ScaffoldPermit IssuedSPD CONSTRUCTION CORP11/18/2024
DOB NOWPlumbingSigned-offCROSSFIELD PLBG.&HTG02/01/2022
DOB NOWMechanical SystemsSigned-offA-LINE CONSTRUCTION CORP10/04/2021
DOB NOWSprinklersSigned-offCROSSFIELD PLBG.&HTG.CORP12/01/2020
DOB NOWPlumbingSigned-offCROSSFIELD PLBG.&HTG11/12/2020
DOB NOWSidewalk ShedSigned-offNEW FORCE CONSTRUCTION CO12/03/2019
DOB NOWSupported ScaffoldSigned-offNEW FORCE CONSTRUCTION CO12/03/2019
DOB NOWSupported ScaffoldSigned-offNEW FORCE CONSTRUCTION CO04/04/2019
DOB NOWSidewalk ShedSigned-offNEW FORCE CONSTRUCTION CO12/05/2018
DOB NOWSidewalk ShedSigned-offNEW FORCE CONSTRUCTION CO07/16/2018
BISOTISSUEDA-LINE CONSTRUCTION CORP02/08/2021
BISOTISSUEDA-LINE CONSTRUCTION CORP12/14/2020
BISOTISSUEDA-LINE CONSTRUCTION CORP09/15/2020
BISOTISSUEDNEW FORCE CONSTRUCTION CORP12/02/2019
BISPLISSUEDEVERYDAY MECHANICAL CORP03/18/2019
BISOTISSUEDHESCO CONSTRUCTION CORP03/08/2019
BISOTISSUEDNEW FORCE CONSTRUCTION CORP02/07/2019
BISMHISSUEDRIGHT TEMP MECHANICAL INC09/25/2014
BISOTISSUEDCARTER HUDSON, INC08/13/2009
BISPLISSUEDPAR PLUMBING CO., INC04/07/2008
BISMHISSUEDSILVERLINING INTERIORS03/07/2008
BISOTISSUEDS. DONADIC INC04/17/2007
BISOTISSUEDSILVERLINING INTERIORS01/19/2007
BISOTISSUEDSILVERLINING INTERIORS01/16/2007
BISFPISSUEDCHIEF FIRE PREVENTION & MECH COR09/26/2006
BISSPISSUEDSKH MECHANICAL CORP07/14/2006
BISOTISSUEDSHAWMUT WOODWORKING & SUPPLY07/10/2006
BISSPISSUEDRAEL AUTOMATIC SPR. CO.IN07/10/2006
BISMHISSUEDSHAWMUT WOODWORKING & SUPPLY07/10/2006
BIS—ISSUEDLENDLEASE(US)CONSTRUCTION06/30/2006
BISOTISSUEDSHAWMUT WOODWORKING & SUPPLY06/21/2006
+ 5 more permits on file
2 projects · most recent 09/17/2026
Air Conditioning Systems Cooling Towers
FiledStatusContractorScopeMake / Model / Capacity
09/17/2026——Air Conditioning Systems
Cooling
Ice Air 8HHPW18 2 tons ×1
8HHPW24 2 tons ×1
01/16/2024Permit IssuedSUPERIOR HVAC INCCooling Towers
Cooling Tower
Evapco LPT-859D 200 tons · Cooling Tower ×1
1 project · most recent 07/23/2026
FiledStatusContractorScope
07/23/2026———
2 projects · most recent 09/17/2026
Water/Sanitary
FiledStatusContractorScope
09/17/2026——Water/Sanitary
03/23/2026Permit IssuedPLUMBING WORKS CORPWater/Sanitary
9 projects · most recent 07/06/2026
General Wiring
FiledStatusContractorScope
07/06/2026Permit IssuedAMSTERDAM ELECTRIC CORPGeneral Wiring
08/15/2025Permit IssuedHIGH QUALITY ELEC.OF NYC—
04/07/2025Permit IssuedNEE ELECTRICAL, LLC—
03/27/2025CompleteQEC ELECTRICAL SVCE CORPGeneral Wiring
12/10/2024CompleteP.S. MARCATO ELEV. CO INC—
04/19/2021CompleteASSET ELECTRIC CORP—
11/06/2020CompleteVALENTIS ELECTRIC, INC.General Wiring
03/19/2019CompleteCITI-WIDE ELECTRIC INCGeneral Wiring
07/09/2018Permit IssuedACCURATE ELEC'L CORP.—
1 project · most recent 09/17/2026
Steel Concrete
FiledStatusContractorScope
09/17/2026——Steel, Concrete
1 project · most recent 08/14/2025
Sidewalk Shed
FiledStatusContractorScope
08/14/2025Permit IssuedKINGS GROUP NY CORPSidewalk Shed
1 project · most recent 10/07/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
10/07/2025Permit IssuedSPD CONSTRUCTION CORPSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
05/05/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
05/01/2026Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
05/01/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 43
DateRequirementInspectorRole
09/03/2026Post-installed AnchorsAri Kamospecial
07/21/2026Post-installed Anchors—special
07/15/2026Fire-Resistant Penetrations and Joints—special
07/13/2026Sprayed fire-resistant materialsAri Kamospecial
07/13/2026Interior lighting powerAri Kamoenergy_progress
07/13/2026Fire-Resistant Penetrations and JointsAri Kamospecial
07/13/2026Energy Code Compliance InspectionsAri Kamoprogress
07/13/2026PreliminaryAri Kamoprogress
07/13/2026Fire-Resistance Rated ConstructionAri Kamoprogress
05/26/2026Sprinkler Systems—special
05/26/2026Tenant Protection Plan ComplianceShahrish Shuvospecial
05/26/2026Final—progress
05/26/2026Mechanical Systems—special
05/26/2026Tenant Protection Plan ComplianceShahrish Shuvospecial
05/26/2026FinalAri Kamoprogress
05/26/2026Tenant Protection Plan ComplianceShahrish Shuvospecial
05/26/2026Tenant Protection Plan ComplianceShahrish Shuvospecial
05/22/2026Tenant Protection Plan ComplianceShahrish Shuvospecial
03/18/2026Lighting in dwelling unitsBenjamin Hochbergenergy_progress
03/18/2026Fire-Resistant Penetrations and JointsNICHOLAS AZADIANspecial
03/18/2026Energy Code Compliance InspectionsBenjamin Hochbergprogress
03/18/2026HVAC-R and service water piping design and insulationBenjamin Hochbergenergy_progress
03/18/2026Fire-Resistant Penetrations and JointsNICHOLAS AZADIANspecial
03/18/2026Energy Code Compliance InspectionsBenjamin Hochbergprogress
03/18/2026Fire-Resistance Rated ConstructionBenjamin Hochbergprogress
Latest 25 of 43.
▾Documents — 247 on file (BIS + DOB NOW)
▸Plans & Drawings26
▸DOB NOWPlans/Sketch16
09/21/2026M01406289-S1Request digital key ↗
09/21/2026M01406289-S2Request digital key ↗
09/21/2026M01406289-I1Request digital key ↗
Showing 3 of 16 on file for this type
▸DOB NOWPlans/Sketch - Plumbing4
09/05/2026M00219992-I1Request digital key ↗
09/05/2026M00219992-P3Request digital key ↗
09/05/2026M00219992-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold3
09/05/2026M00141076-I1Request digital key ↗
09/05/2026M00141076-P1Request digital key ↗
09/05/2026M00141076-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
09/04/2026M00412853-P1Request digital key ↗
09/04/2026M00412853-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/04/2026M00412829-I1Request digital key ↗
▸Applications & Permits23
▸BISPLAN / WORK APPROVAL APPLICATION14
10/07/2020123773899Open ↗
09/01/2020123773899Open ↗
09/09/2019123773899Open ↗
Showing 3 of 14 on file for this type
▸BISWORK PERMIT APPLICATION9
02/08/2021123773899Open ↗
12/14/2020123773899Open ↗
09/15/2020123773899Open ↗
Showing 3 of 9 on file for this type
▸Seals & Professional Certifications102
▸DOB NOWSpecial Inspector Seal & Signature25
09/23/2026M01406289-S1Open ↗
09/23/2026M01406289-I1Open ↗
09/23/2026M01406289-I1Open ↗
Showing 3 of 25 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature24
09/21/2026M01406289-S1Open ↗
09/21/2026M01406289-S3Open ↗
09/21/2026M01406289-S2Open ↗
Showing 3 of 24 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION20
09/09/2019123853589Open ↗
09/09/2019123853589Open ↗
09/09/2019123773899Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWProgress Inspector Seal & Signature16
09/23/2026M01406289-S1Open ↗
09/23/2026M01406289-I1Open ↗
09/23/2026M01406289-S3Open ↗
Showing 3 of 16 on file for this type
▸BISPC FULL REPORT6
11/21/2007110011889Open ↗
11/16/2007110026034Open ↗
11/15/2007110025749Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST6
08/02/2019123688875Open ↗
05/29/2018123421010Open ↗
06/02/2008110011870Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM3
11/16/2007110026034Open ↗
11/01/2007110011870Open ↗
11/01/2007110011870Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
08/02/2019123688875Open ↗
05/29/2018123421010Open ↗
▸Trade Schedules & Equipment4
▸BISEQUIPMENT USE PERMITS2
10/28/2014121792097Open ↗
10/28/2014121792097Open ↗
▸BISPLUMBING - SUPPORTING DOCUMENTATION1
10/18/2021123773899Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
03/01/2019123853589Open ↗
▸Safety & Tenant Protection11
▸DOB NOWTenant Protection Plan7
09/05/2026M00219992-P3Open ↗
09/05/2026M00219992-P2Open ↗
09/05/2026M00219992-P1Open ↗
Showing 3 of 7 on file for this type
▸BISTenant Protection Plan and Notes4
09/09/2019123773899Open ↗
08/02/2019123688875Open ↗
03/01/2019123853589Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos32
▸DOB NOWDEP ACP-5: Asbestos Assessment Report22
09/21/2026M01406289-S2Open ↗
09/21/2026M01406289-S1Open ↗
09/21/2026M01406289-I1Open ↗
Showing 3 of 22 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
09/09/2019123773899Open ↗
03/01/2019123853589Open ↗
12/12/2018123421010Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS INSPECTION REPORT4
11/21/2007110011889Open ↗
11/16/2007110026034Open ↗
11/15/2007110025749Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
11/01/2007110011870Open ↗
▸Energy Compliance8
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
09/09/2019123773899Open ↗
08/29/2019123853589Open ↗
03/01/2019123853589Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS1
08/29/2019123853589Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
02/03/2022123773899Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
02/03/2022123773899Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
02/03/2022123773899Open ↗
▸Approvals, Objections & Sign-offs12
▸BISADMINISTRATIVE OBJECTIONS6
11/16/2007110026034Open ↗
11/15/2007110025749Open ↗
11/01/2007110011870Open ↗
Showing 3 of 6 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
02/07/2022123773899Open ↗
09/09/2019123853589Open ↗
06/15/2010110025749Open ↗
Showing 3 of 4 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION2
02/08/2021123773899Open ↗
12/14/2020123773899Open ↗
▸Cost, Insurance & Ownership10
▸BISCOST AFFIDAVIT9
02/05/2022123773899Open ↗
09/09/2019123853589Open ↗
09/09/2019123773899Open ↗
Showing 3 of 9 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
02/03/2022123773899Open ↗
▸Filing & Intake Forms13
▸BISBOROUGH INTAKE FORM5
02/08/2021123773899Open ↗
12/14/2020123773899Open ↗
07/05/2019104746768Open ↗
Showing 3 of 5 on file for this type
▸BISEFILING COVER SHEET5
09/09/2019123773899Open ↗
08/02/2019123688875Open ↗
03/01/2019123853589Open ↗
Showing 3 of 5 on file for this type
▸BISADDITIONAL INFORMATION3
10/18/2021123773899Open ↗
09/30/2020123773899Open ↗
12/12/2018123421010Open ↗
▸Other Documents5
▸DOB NOWManufacturer's Specifications2
08/13/2026M01108722-P1Open ↗
08/13/2026M01108722-I1Open ↗
▸DOB NOWCalculations2
08/13/2026M01108722-P1Open ↗
08/13/2026M01108722-I1Open ↗
▸BISSupporting Document: Fee Exempt1