Elevator cooperative
50 PARK TERRACE WEST
MANHATTAN · Inwood · BIN 1065031
💬 Discuss this project
1925Year Built
6Stories
D4Building Class
R7AZoning
47,477 sfGross Floor Area
50Units
LL97 CoveredRent Stabilized42 Open Violations 35 unresolved · 7 paperwork only ▸FISP: SAFEFDNY Report ↗
Elevator cooperative · Owner of record: INWOOD TENANTS CORP · 10,175 sf lot · 4.67 FAR built · Flood zone X
Locations of Work
StructuralElectricalPlumbingEquipmentGeneral
Floor 19p · 2 filings · 17 docs
Site & exterior4p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
BLUE WOODS MANAGEMENT GROUP, INC.1203/22/2026
UNITED KING CONSTRUCTION507/08/2026
ROCK GROUP NY CORP503/22/2026
MATTHEW ADAM PROPERTIES203/21/2026
DEDVUKAJ BUILDING GROUP103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
COLLADO ENGINEERING409/08/2023
ENTHINK ENGINEERS LLC107/06/2021
ASIF JAMIL, RA111/26/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GREEN STUDIO203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
UNITED KING CONSTRUCTIONGeneral Contractor707/08/2026
ROCK GROUP NY CORPGeneral Contractor303/21/2026
CAPE PLUMBING INCPlumbing207/08/2026
CENTURY ELECTRIC CO.Electrical103/22/2026
GOLDMAN ELECTRIC CORP.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
COLLADO ENGINEERING, DPC3432409/08/2023
Building Lifecycle
All (96)Filed (6)Permit Issued (5)Signed Off (1)Facade (FISP) (12)Violation (60)Inspection (7)Objection (2)Special Inspection (3)
12/22/2025
Violation issued (HPD, open)
B
12/22/2025
Violation issued (HPD, open)
C
04/23/2025
Violation issued (HPD, open)
C
01/30/2025
Violation issued (HPD, closed)
C
01/30/2025
Violation issued (HPD, open)
B
01/30/2025
Violation issued (HPD, open)
B
01/30/2025
Violation issued (HPD, open)
B
01/30/2025
Violation issued (HPD, open)
B
01/30/2025
Violation issued (HPD, closed)
C
01/30/2025
Violation issued (HPD, closed)
C
11/22/2024
Violation issued (HPD, closed)
I
03/19/2024
Violation issued (ECB, open)
Construction
02/16/2024
Cycle 9 facade report submitted
12/29/2023
Cycle 9 facade inspection completed
09/29/2023
Signed off — Alteration
Herby filing to replace existing gas piping to gas dryers and install new sprinkler head over gas dryers in laundry room
M00742347-I1
09/11/2023
Special inspection requirement — Post-installed Anchors
Andrew Hlushko
09/08/2023
Filed — Alteration
Herby filing to replace existing gas piping to gas dryers and install new sprinkler head over gas dryers in laundry room
M00742347-P3
07/13/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/29/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/15/2023
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
05/25/2023
Filed — Alteration
Herby filing to replace existing gas piping to gas dryers and install new sprinkler head over gas dryers in laundry room
M00742347-P2
05/25/2023
Special inspection requirement — Post-installed Anchors
Andrew Hlushko
05/17/2023
Objection resolved — Addressed
01/30/2023
Objection raised — Admin
01/17/2023
Filed — Alteration
Herby filing to replace existing gas piping to gas dryers and install new sprinkler head over gas dryers in laundry room
M00742347-P1
01/11/2023
Special inspection requirement — Post-installed Anchors
Andrew Hlushko
12/07/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
11/21/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
09/16/2022
Permit issued — Plumbing
M00742347-I1-PL
07/19/2022
Violation issued (ECB, open)
Construction
07/19/2022
Violation issued (ECB, open)
Construction
07/07/2022
Cycle 9 facade report signed — SAFE
05/31/2022
Filed — Alteration
Herby filing to replace existing gas piping to gas dryers and install new sprinkler head over gas dryers in laundry room
M00742347-I1
05/22/2022
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/19/2022
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/06/2022
Permit issued — Sidewalk Shed
M00551427-I1-SH
03/30/2022
Violation issued (ECB, open)
Boilers
03/28/2022
Violation issued (ECB, open)
Plumbing
03/28/2022
Violation issued (ECB, open)
Plumbing
03/28/2022
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/28/2022
Violation issued (ECB, open)
Plumbing
03/28/2022
Violation issued (ECB, open)
Construction
03/28/2022
Violation issued (ECB, open)
Construction
12/09/2021
Violation issued (HPD, open)
A
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
A
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
C
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
A
12/09/2021
Violation issued (HPD, open)
A
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
12/09/2021
Violation issued (HPD, open)
B
Latest 60 of 96 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCAPE PLUMBING INC09/16/2022
DOB NOWSidewalk ShedPermit IssuedUNITED KING CONSTRUCTION05/06/2022
DOB NOWSidewalk ShedPermit IssuedUNITED KING CONSTRUCTION11/04/2021
DOB NOWSidewalk ShedPermit IssuedUNITED KING CONSTRUCTION07/06/2021
DOB NOWSidewalk ShedPermit IssuedROCK GROUP NY CORP11/26/2019
BISOTISSUEDJRR CONTRACTING INC05/22/2023
BISOTISSUEDJRR CONTRACTING INC03/24/2022
BISOTISSUEDJRR CONTRACTING INC09/27/2021
BISOTISSUEDDEDVUKAJ BUILDERS GROUP05/01/2019
BISPLISSUEDCAPE PLUMBING INC08/20/2018
BISOTISSUEDDEDVUKAJ BUILDERS GROUP07/23/2018
BISPLISSUEDCAPE PLUMBING INC04/17/2018
BISOTISSUEDDEDVUKAJ BUILDERS GROUP04/02/2018
BISOTISSUEDMICHAEL DEFINIS ALL PRO C02/08/2018
BISOTISSUEDBUILT IN BROOKLYN CONSTRU05/25/2017
BISOTISSUEDECOTECH CONTRACTING INC05/19/2016
BISOTISSUEDHOME IMPROVEMENT CONSTRUCTION09/16/2015
BISOTISSUEDTITAN CONSTRUCTION SERVIC06/25/2015
BISOTISSUEDSTANDARD WATERPROOFING C03/08/2012
BISEQISSUEDARSENAL SCAFFOLD INC03/01/2012
BISOTISSUEDSTANDARD WATERPROOFING C09/26/2011
BISOTISSUEDSTANDARD WATERPROOFING C07/26/2011
BISEQISSUEDARSENAL SCAFFOLD INC03/09/2011
BISFSISSUEDC C CONTROLLED COMBUSTION03/25/2008
BISOTISSUEDACCURA RESTORATION09/12/2006
BISOTISSUEDACCURA RESTORATION04/07/2006
BISEQISSUEDROCKLEDGE SCAFFOLD CORP01/10/2006
BISEQISSUEDCOLGATE SCAFFOLDING06/16/1998
BISEQISSUEDLEE MARK08/27/1990
4 projects · most recent 03/22/2022
General Wiring
FiledStatusContractorScope
03/22/2022CompleteCENTURY ELECTRIC LLCGeneral Wiring
07/06/2021Permit IssuedRICHARD NEU—
11/20/2019Permit IssuedILLUMINOUS ELECTRIC CORP.—
08/30/2018Permit IssuedGOLDMAN ELECTRIC CORP.General Wiring
1 project · most recent 07/06/2021
Sidewalk Shed
FiledStatusContractorScope
07/06/2021Permit IssuedUNITED KING CONSTRUCTIONSidewalk Shed
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
07/13/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/29/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/15/2023Fail-Final PL - Up to 3 Requested FloorsFailView ↗
12/07/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
11/21/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
05/22/2022Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/19/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
09/11/2023Post-installed AnchorsAndrew Hlushkospecial
05/25/2023Post-installed AnchorsAndrew Hlushkospecial
01/11/2023Post-installed AnchorsAndrew Hlushkospecial
▾Documents — 196 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch5
09/03/2026M00551427-I1Request digital key ↗
09/02/2026M00742347-I1Request digital key ↗
09/02/2026M00742347-P2Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/05/2026M00269128-I1Request digital key ↗
▸Applications & Permits42
▸BISPLAN / WORK APPROVAL APPLICATION23
08/23/2022141000486Open ↗
04/13/2021141000486Open ↗
03/25/2021141000486Open ↗
Showing 3 of 23 on file for this type
▸BISWORK PERMIT APPLICATION17
05/23/2023141000486Open ↗
05/16/2023141000486Open ↗
09/28/2021141000486Open ↗
Showing 3 of 17 on file for this type
▸BISPARTIAL DEMO: 10-DAY NOTICE (FOR AL/EW-OT PERMITS)1
09/13/2021141000486Open ↗
▸BISPARTIAL DEMO PLAN & DS1 (FOR AL/EW-OT PERMITS)1
09/21/2021141000486Open ↗
▸Seals & Professional Certifications45
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION19
05/06/2019123488289Open ↗
05/06/2019123488289Open ↗
05/02/2019123425258Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST7
07/18/2018123488289Open ↗
07/18/2018123488289Open ↗
03/28/2018123425258Open ↗
Showing 3 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT6
07/18/2018123488289Open ↗
07/18/2018123488289Open ↗
03/28/2018123425258Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
09/05/2026M00269128-I1Open ↗
09/02/2026M00742347-P2Open ↗
09/02/2026M00742347-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/27/2026M00742347-I1Open ↗
08/29/2026M00742347-P1Open ↗
08/24/2026M00742347-P2Open ↗
▸BISAPPLICANT OWNER SIGNATURE2
03/25/2021141000486Open ↗
06/04/2014140176958Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/25/2021141000486Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
10/20/2010120497168Open ↗
▸Trade Schedules & Equipment5
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
07/18/2018123488289Open ↗
03/28/2018123425258Open ↗
05/24/2017123095523Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
03/15/2008110097234Open ↗
▸BISSCHEDULE B - PLUMBING1
06/04/2014140176958Open ↗
▸Safety & Tenant Protection8
▸BISTenant Protection Plan and Notes4
07/18/2018123488289Open ↗
03/28/2018123425258Open ↗
02/08/2018123212479Open ↗
Showing 3 of 4 on file for this type
▸BISSTREET TREE CHECKLIST2
06/01/2016122738243Open ↗
02/24/2015140176958Open ↗
▸BISTPP1: TENANT PROTECTION PLAN1
05/03/2021141000486Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026M00269128-I1Open ↗
▸Environmental & Asbestos15
▸BISASBESTOS: CERTIFICATION (DEP ACP5)7
03/25/2021141000486Open ↗
07/18/2018123488289Open ↗
03/28/2018123425258Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
09/02/2026M00742347-P2Open ↗
09/02/2026M00742347-I1Open ↗
09/02/2026M00742347-P3Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'2
06/16/2011120720032Open ↗
03/17/2008110097234Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP20/21/5)1
07/15/2015122238587Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
10/20/2010120497168Open ↗
▸Energy Compliance16
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS10
05/06/2019123488289Open ↗
07/24/2018123488289Open ↗
07/18/2018123488289Open ↗
Showing 3 of 10 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
05/06/2019123488289Open ↗
10/17/2016122738243Open ↗
04/14/2016122238587Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
03/25/2021141000486Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
03/25/2021141000486Open ↗
▸BISTECHNICAL REPORT: ENERGY1
06/16/2011120720032Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
03/25/2021141000486Open ↗
02/24/2015140176958Open ↗
▸Approvals, Objections & Sign-offs12
▸BISLETTERS - SUPPORTING DOCUMENTATION4
05/23/2023141000486Open ↗
04/29/2021141000486Open ↗
07/15/2015122238587Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
05/06/2019123488289Open ↗
05/02/2019123425258Open ↗
04/14/2016122238587Open ↗
Showing 3 of 4 on file for this type
▸BISADMINISTRATIVE OBJECTIONS3
06/16/2011120720032Open ↗
10/20/2010120497168Open ↗
02/21/2008110097234Open ↗
▸BISSHED LETTER1
05/30/2014120497168Open ↗
▸Cost, Insurance & Ownership17
▸BISCOST AFFIDAVIT15
03/25/2021141000486Open ↗
05/06/2019123488289Open ↗
05/06/2019123488289Open ↗
Showing 3 of 15 on file for this type
▸BISPROJECT-SPECIFIC GL INSURANCE1
09/13/2021141000486Open ↗
▸BISHIC LICENSE OR AFFIDAVIT1
05/01/2019123488289Open ↗
▸Filing & Intake Forms26
▸BISEFILING COVER SHEET9
07/18/2018123488289Open ↗
07/18/2018123488289Open ↗
03/28/2018123425258Open ↗
Showing 3 of 9 on file for this type
▸BISBOROUGH INTAKE FORM9
05/23/2023141000486Open ↗
05/17/2023141000486Open ↗
09/28/2021141000486Open ↗
Showing 3 of 9 on file for this type
▸BISADDITIONAL INFORMATION6
09/28/2021141000486Open ↗
04/29/2021141000486Open ↗
07/18/2018123488289Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET2
03/25/2021141000486Open ↗
06/04/2014140176958Open ↗
▸Other Documents2
▸BISPLOT DIAGRAM1
02/08/2018123212479Open ↗
▸BISGAS WELDER ANNUAL CERT : GAS-WELD1
04/02/2018123425258Open ↗