| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/29/2019 | $1.9M | — | Private party → Private party | $910/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| DM ENGINEERS PLLC | 6 | 07/28/2025 |
| MARTOS ENGINEERING | 2 | 07/20/2025 |
| FABRICA ARCHITECTURE STUDIO | 4 | 04/08/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| FABRICA ARCHITECTURE STUDIO | 9 | 03/21/2026 |
| KUSHNER STUDIOS | 3 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CARY P O'BRIEN DESIGN LLC | General Contractor | 12 | 07/08/2026 |
| ANTONIO CERIELLO ELEC INC | Electrical | 2 | 03/22/2026 |
| MEGA PLBG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RHL ENGINEERING, LLC | 712 | 9 | 07/28/2025 |
| CHRISTIAN L. MARTOS ENGIN | 5965 | 4 | 07/20/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Signed-off | CARY P O'BRIEN DESIGN LLC | 04/13/2026 |
| DOB NOW | Mechanical Systems | Signed-off | CARY P O'BRIEN DESIGN LLC | 04/13/2026 |
| DOB NOW | Structural | Signed-off | CARY P O'BRIEN DESIGN LLC | 04/13/2026 |
| DOB NOW | General Construction | Signed-off | CARY P O'BRIEN DESIGN LLC | 08/08/2025 |
| DOB NOW | Foundation | Signed-off | CARY P O'BRIEN DESIGN LLC | 05/01/2025 |
| DOB NOW | Structural | Signed-off | CARY P O'BRIEN DESIGN LLC | 05/01/2025 |
| DOB NOW | Plumbing | Signed-off | MEGA PLBG CORP | 04/28/2025 |
| DOB NOW | Foundation | Signed-off | CARY P O'BRIEN DESIGN LLC | 03/17/2025 |
| DOB NOW | Structural | Signed-off | CARY P O'BRIEN DESIGN LLC | 03/11/2025 |
| DOB NOW | General Construction | Signed-off | CARY P O'BRIEN DESIGN LLC | 03/10/2025 |
| BIS | OT | ISSUED | BROOKLYN SOLARWORKS LLC | 02/25/2020 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/28/2025 | Signed-off | CARY P O'BRIEN DESIGN LLC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric PEAD-A36AA9 33,000 BTU · Vrf Indoor ×4 SUZ-KA36NAHZ 33,000 BTU · Heat Pump Outdoor ×4 MSZ-GL12NA-U2 12,000 BTU · Fan Coil Indoor ×2 MXZ-SM42NAMHZ 42,000 BTU · Heat Pump Outdoor ×2 SVZ-KP30NA 27,000 BTU · Fan Coil Indoor ×2 MSZ-EF12NA(X)-U2 21,600 BTU · Ahu ×3 PEAD-A30AA7 32,000 BTU · Ahu ×2 PUZ-A30NHA7 32,000 BTU · Heat Pump Outdoor ×2 MXZ-5C42NA2 45,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2026 | Permit Issued | PW & SONS ELECTRICAL CORP | General Wiring |
| 07/29/2025 | Complete | ANTONIO CERIELLO ELEC INC | 2 meters, 2 new_meters |
| 04/09/2025 | Cancelled | PW & SONS ELECTRICAL CORP | General Wiring |
| 07/15/2020 | Complete | BROOKYLN SOLARWORKS, LLC | — |
| 02/14/2020 | Complete | ANTONIO CERIELLO ELEC INC | — |
| 02/10/2020 | Complete | ANTONIO CERIELLO ELEC INC | 2 meters, 2 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/06/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/08/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/07/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/07/2025 | HVAC-R and service water piping design and insulation | RICHARD LEMANSKY | energy_progress |
| 08/07/2025 | Maintenance information | RICHARD LEMANSKY | energy_progress |
| 08/07/2025 | Fire-Resistant Penetrations and Joints | Vincent Gentile | special |
| 07/29/2025 | Structural Steel - Welding | Christian Martos | special |
| 07/29/2025 | Structural Cold-Formed Steel | Christian Martos | special |
| 07/29/2025 | Structural Steel - Details | Christian Martos | special |
| 07/29/2025 | Masonry | Christian Martos | special |
| 07/29/2025 | Structural Stability – Alterations of existing buildings | Christian Martos | special |
| 07/29/2025 | Concrete - Cast-In-Place | Christian Martos | special |
| 07/29/2025 | Structural Wood Frame | Christian Martos | progress |
| 07/29/2025 | Final | Christian Martos | progress |
| 07/29/2025 | Construction Utilizing CLT or SCL, Type IV | Christian Martos | special |
| 07/29/2025 | Post-installed Anchors | Christian Martos | special |
| 07/29/2025 | Structural Steel - High Strength Bolting | Christian Martos | special |
| 07/22/2025 | Fire-Resistant Penetrations and Joints | Vincent Gentile | special |
| 07/22/2025 | Maintenance information | RICHARD LEMANSKY | energy_progress |
| 07/22/2025 | HVAC-R and service water piping design and insulation | RICHARD LEMANSKY | energy_progress |
| 07/22/2025 | Fire-Resistant Penetrations and Joints | Vincent Gentile | special |
| 07/22/2025 | HVAC-R and service water piping design and insulation | RICHARD LEMANSKY | energy_progress |
| 07/22/2025 | Maintenance information | RICHARD LEMANSKY | energy_progress |
| 07/22/2025 | HVAC-R and service water heating equipment | RICHARD LEMANSKY | energy_progress |
| 07/22/2025 | Final | RICHARD LEMANSKY | progress |
| 07/22/2025 | Mechanical Systems | Vincent Gentile | special |
| 07/15/2025 | Structural Steel - High Strength Bolting | Christian Martos | special |
| 07/15/2025 | Concrete - Cast-In-Place | Christian Martos | special |