| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/01/2018 | $1.9M | — | 502 PRESIDENT ST LLC → Private party | $724/sf building |
| 04/13/2017 | $1.5M | — | Private party → 502 PRESIDENT ST LLC | $571/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Wellworth Consulting | 1 | 12/15/2023 |
| HRP Associates | 1 | 09/01/2023 |
| Ashraf | 1 | 10/28/2019 |
| Syed Engineering | 1 | 10/09/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Expediting | 2 | 03/21/2026 |
| United Safety Consultants | 1 | 03/21/2026 |
| Nexus Consulting NYC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Topline NYC Contracting | Scaffold | 7 | 07/08/2026 |
| Long Island Environmental | General Contractor | 4 | 07/08/2026 |
| Spring Scaffolding | Scaffold | 1 | 07/08/2026 |
| DPH Plumbing & Heating | Plumbing | 1 | 09/30/2020 |
| Hatchet Works | General Contractor | 5 | 09/28/2020 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Fidato Consultants | 8834 | 1 | 09/01/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | Long Island Environmental | 01/09/2024 |
| DOB NOW | Supported Scaffold | Signed-off | Spring Scaffolding | 12/15/2023 |
| DOB NOW | General Construction | Signed-off | Long Island Environmental | 09/27/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | Topline NYC Contracting | 12/23/2019 |
| DOB NOW | Construction Fence | Signed-off | Topline NYC Contracting | 10/29/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | Topline NYC Contracting | 10/09/2019 |
| BIS | PL | ISSUED | DPH Plumbing & Heating | 09/30/2020 |
| BIS | MH | ISSUED | Hatchet Works | 09/28/2020 |
| BIS | OT | ISSUED | Hatchet Works | 09/23/2020 |
| BIS | OT | ISSUED | Hatchet Works | 09/27/2019 |
| BIS | OT | ISSUED | Hatchet Works | 05/06/2019 |
| BIS | OT | ISSUED | Hatchet Works | 12/11/2018 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/11/2020 | Complete | KJK Electric | General Wiring |
| 10/08/2019 | Complete | Richard Neu | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/02/2023 | Fire-Resistant Penetrations and Joints | ROMIT GAJJAR | special |
| 07/28/2023 | Final | GLENN NETUSCHIL | progress |