← Back
BuildNYC
Gas or electric utility
506 EAST 75TH STREET
MANHATTAN · BIN 1082174
💬 Discuss this project
0Year Built
—Stories
U2Building Class
M3-2Zoning
0 sfGross Floor Area
0Units
3 Active Violations 1 old, status unconfirmed ▸FISP: UNSAFE
Gas or electric utility · Owner of record: Consolidated Edison Co of N.Y · 123,616 sf lot · 0 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalFire ProtectionEquipmentGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
RoofConsolidated Edison, VerizonUnder Construction7p · 3 filings · 9 docs
BulkheadMasonry pinning cornice1p · 1 filing · 7 docs
PenthouseCon Edison Generating Station Facade RepairsUnder Construction1p · 2 filings · 12 docs
Floor 11Verizon5p · 1 filing · 2 docs
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 2
Floor 1
Sub-BasementFuel storage room fireUnder Construction7p · 1 filing · 8 docs
Site & exteriorRelocation of traffic signals and hydrantsUnder Construction25p · 8 filings · 17 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Consolidated Edison Company of New York16110/13/2026
Con Edison Co of N Y103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Eagle Scaffolding ServicesScaffold1107/23/2026
D'Onofrio General ContractorsGeneral Contractor607/04/2026
Sajid ContractingScaffold304/09/2026
M & S Buildings ServicesFire Protection207/08/2026
Westrock Mechanicalspecialty_contractor203/21/2026
M S Buildings ServicesPlumbing203/22/2026
Deboccia Electric ConstructionElectrical203/21/2026
Green Power ElectricElectrical103/21/2026
Safway AtlanticScaffold103/21/2026
Alliance Elevator CompanyElectrical103/21/2026
Proven Electrical ContrngElectrical103/22/2026
Denko MechanicalFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Scherer Design Group7921107/17/2024
Tectonic Engineering Cons106502/06/2024
Building Lifecycle
All (174)Filed (15)Permit Issued (22)Signed Off (6)Facade (FISP) (32)Violation (60)Inspection (3)Objection (20)Special Inspection (16)
09/02/2026
Filed — Alteration
Installation of suspended scaffold for facade repair.
M01442611-I1
09/02/2026
Permit issued — Suspended Scaffold
M01442611-I1-SC
08/31/2026
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01367538-P1
07/22/2026
Permit issued — Sidewalk Shed
M01367538-I1-SH
07/02/2026
Permit issued — General Construction
M00929600-I1-GC-CX
06/02/2026
Permit issued — Sprinklers
M00939650-S1-EW-SP
05/01/2026
Violation issued (ECB, open)
Construction
04/20/2026
Violation issued (ECB, open)
Local Law
04/07/2026
Signed off — Alteration
Con Edison's 74th Street Station facade repairs - as per drawings being submitted: T-001.00, T-002.00, G-001.00, G-002.00, G-003.00, A-101.00, A-102.00, A-202.00, A-201.00, A-203.00, A-301.00, A-302.00, A-303.00, A-304.00, A-305.00, A-306.00.
M00745860-I1
03/06/2026
Permit issued — Sidewalk Shed
M01367538-I1-SH
03/05/2026
Filed — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M01367538-I1
03/03/2026
Violation issued (ECB, open)
Construction
03/03/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
02/04/2026
Cycle 9 facade report submitted
01/22/2026
Signed off — Alteration
Remove and replace roofing material in the areas noted on the drawings being submitted with this application, R - 25. Make additional associated repairs as required.
M00997556-I1
01/22/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
01/22/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
01/21/2026
Permit issued — Sprinklers
M00939650-S1-EW-SP
01/13/2026
Cycle 9 facade inspection completed
07/15/2025
Permit issued — General Construction
M00745860-I1-GC-CX
07/15/2025
Permit issued — Sidewalk Shed
M01223399-I1-SH
05/20/2025
Permit issued — Sidewalk Shed
M01223399-I1-SH
05/19/2025
Filed — Alteration
Installation of temporary heavy duty sidewalk shed per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01223399-I1
04/29/2025
Signed off — Alteration
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
M00689601-I1
03/12/2025
Permit issued — General Construction
M00997556-I1-GC-CX
03/03/2025
Permit issued — Sidewalk Shed
M00689601-I1-SH
12/27/2024
Cycle 9 facade report submitted
12/17/2024
Cycle 9 facade inspection completed
12/16/2024
Permit issued — Sprinklers
M00939650-S1-EW-SP
12/16/2024
Cycle 9 facade report signed — UNSAFE
08/16/2024
Permit issued — Mechanical Systems
M01040223-I1-MS
07/17/2024
Filed — Alteration
M01040223-I1
07/11/2024
Permit issued — Structural
M00745860-I1-GC-CX
03/12/2024
Cycle 9 facade report submitted
03/11/2024
Permit issued — Structural
M00745860-I1-GC-CX
03/06/2024
Permit issued — Sidewalk Shed
M00689601-I1-SH
03/06/2024
Cycle 9 facade report signed — UNSAFE
02/16/2024
Objection raised — Other
02/16/2024
Objection resolved — Addressed
02/09/2024
Objection raised — Scope
02/09/2024
Objection resolved — Addressed
02/09/2024
Objection raised — Scope
02/09/2024
Objection resolved — Addressed
02/09/2024
Objection raised — Scope
02/09/2024
Objection resolved — Addressed
02/08/2024
Objection resolved — Addressed
02/06/2024
Filed — Alteration
Remove and replace roofing material in the areas noted on the drawings being submitted with this application, R - 25. Make additional associated repairs as required.
M00997556-I1
01/23/2024
Cycle 9 facade inspection completed
01/23/2024
Objection resolved — Addressed
01/11/2024
Objection resolved — Addressed
01/11/2024
Objection resolved — Addressed
01/10/2024
Objection resolved — Addressed
01/10/2024
Objection resolved — Addressed
01/04/2024
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
GEORGE GHEBRYAL
12/28/2023
Objection raised — Scope
12/28/2023
Objection raised — Structural
12/28/2023
Objection raised — Structural
12/28/2023
Objection raised — Other
12/28/2023
Objection raised — Energy
12/28/2023
Objection raised — Scope
Latest 60 of 174 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSuspended ScaffoldPermit IssuedSajid Contracting09/02/2026
DOB NOWSidewalk ShedPermit IssuedEagle Scaffolding Services07/22/2026
DOB NOWGeneral ConstructionPermit IssuedD'Onofrio General Contractors07/02/2026
DOB NOWSprinklersPermit IssuedDenko Mechanical06/02/2026
DOB NOWSidewalk ShedPermit IssuedEagle Scaffolding Services03/06/2026
DOB NOWSprinklersPermit IssuedM & S Buildings Services01/21/2026
DOB NOWGeneral ConstructionSigned-offD'Onofrio General Contracting07/15/2025
DOB NOWSidewalk ShedPermit IssuedSajid Contracting07/15/2025
DOB NOWSidewalk ShedPermit IssuedSajid Contracting05/20/2025
DOB NOWGeneral ConstructionSigned-offD'Onofrio General Contracting03/12/2025
DOB NOWSidewalk ShedSigned-offEagle Scaffolding Services03/03/2025
DOB NOWSprinklersPermit IssuedM & S Buildings Services12/16/2024
DOB NOWMechanical SystemsPermit IssuedWestrock Mechanical08/16/2024
DOB NOWStructuralSigned-offD'Onofrio General Contracting07/11/2024
DOB NOWStructuralSigned-offD'Onofrio General Contracting03/11/2024
DOB NOWSidewalk ShedSigned-offEagle Scaffolding Services03/06/2024
DOB NOWGeneral ConstructionSigned-offD'Onofrio General Contracting04/17/2023
DOB NOWSidewalk ShedSigned-offEagle Scaffolding Services03/10/2023
DOB NOWSidewalk ShedSigned-offEagle Scaffolding Services03/16/2022
DOB NOWSidewalk ShedSigned-offEagle Scaffolding Services11/19/2020
DOB NOWSidewalk ShedSigned-offEagle Scaffolding Services06/02/2020
DOB NOWSidewalk ShedSigned-offSafway Atlantic01/31/2018
BISSPISSUEDSKH Mechanical11/02/2018
BISEQISSUEDSafway Atlantic08/28/2018
BISEQISSUEDSafway Atlantic02/23/2018
BISOTISSUEDD'Onofrio General Contractors09/29/2017
BISEQISSUEDSafway Atlantic08/31/2017
BISMHISSUEDDurr Mechanical Construction07/11/2017
BISFSISSUEDApex Mechanical01/25/2017
BISOTISSUEDD'Onofrio General Contractors11/04/2016
BISPLISSUEDAmr Mechanical09/23/2016
BISOTISSUEDRosenwach Tank Co09/23/2016
BISEQISSUEDSafway Atlantic09/12/2016
BISEQISSUEDSafway Atlantic09/06/2016
BISMHISSUEDD'Onofrio General Contractors07/12/2016
BISOTISSUEDD'Onofrio General Contractors07/11/2016
BISOTISSUEDD'Onofrio General Contractors07/11/2016
BISOTISSUEDD'Onofrio General Contractors07/11/2016
BISOTISSUEDD'Onofrio General Contractors07/08/2016
BISEQISSUEDD'Onofrio General Contractors07/08/2016
+ 32 more permits on file
1 project · most recent 12/19/2023
Others
FiledStatusContractorScope
12/19/2023——Others
1 project · most recent 12/19/2023
FiledStatusContractorScope
12/19/2023Permit IssuedDenko Mechanical60 heads
8 projects · most recent 03/04/2026
General Wiring
FiledStatusContractorScope
03/04/2026Permit IssuedCorporate Electric Group—
12/02/2025CompleteDeboccia Electric ConstructionGeneral Wiring
05/28/2025Permit IssuedGreen Power Electric—
03/02/2022CompleteCorporate Electric Group—
03/02/2022CompleteCorporate Electric Group—
11/18/2020Permit IssuedProven Electrical ContrngGeneral Wiring
11/06/2020CompleteCorporate Electric Group—
01/30/2018CompleteStar-Delta Electric—
1 project · most recent 10/27/2023
Masonry
FiledStatusContractorScope
10/27/2023Permit IssuedD'Onofrio General ContractingMasonry
2 projects · most recent 08/31/2026
Sidewalk Shed
FiledStatusContractorScope
08/31/2026Permit IssuedEagle Scaffolding ServicesSidewalk Shed
05/19/2025Permit IssuedSajid ContractingSidewalk Shed
1 project · most recent 09/02/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
09/02/2026Permit IssuedSajid ContractingSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
03/03/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/22/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
01/22/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
01/04/2024Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)GEORGE GHEBRYALspecial
12/19/2023Fire-Resistant Penetrations and JointsGEORGE GHEBRYALspecial
10/20/2023Structural Steel - DetailsGEORGE GHEBRYALspecial
09/26/2023Sprinkler SystemsGEORGE GHEBRYALspecial
09/26/2023Mechanical SystemsGEORGE GHEBRYALspecial
09/26/2023FinalGEORGE GHEBRYALprogress
09/06/2023MasonryGEORGE GHEBRYALspecial
09/06/2023Structural Steel - WeldingGEORGE GHEBRYALspecial
09/06/2023FinalRobert Kornfeldprogress
09/06/2023Structural Stability – Alterations of existing buildingsGEORGE GHEBRYALspecial
09/06/2023Post-installed AnchorsGEORGE GHEBRYALspecial
05/30/2022MasonryGEORGE GHEBRYALspecial
05/30/2022Post-installed AnchorsGEORGE GHEBRYALspecial
05/30/2022Structural Stability – Alterations of existing buildingsGEORGE GHEBRYALspecial
05/25/2022FinalGEORGE GHEBRYALprogress
01/26/2018FinalPAUL PERDEKprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
VerizonTelecom siteFloor 11, Roof
Project M01040223 Alteration · Permit Entire · 07/17/2024
Consolidated EdisonIndustrial / WarehouseRoof
Project M00997556 Alteration · LOC Issued · 02/06/2024
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 750 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch12
10/13/2026M01442611-I1Request digital key ↗
09/06/2026M00014608-I1Request digital key ↗
09/02/2026M00745860-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed2
09/04/2026M00352987-I1Request digital key ↗
09/04/2026M00425095-I1Request digital key ↗
▸Applications & Permits194
▸BISPLAN / WORK APPROVAL APPLICATION92
10/22/2019123125340Open ↗
09/26/2019123125340Open ↗
10/31/2018123125340Open ↗
Showing 3 of 92 on file for this type
▸BISWORK PERMIT APPLICATION80
11/02/2018123125340Open ↗
02/22/2018140742070Open ↗
10/02/2017123106977Open ↗
Showing 3 of 80 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸Seals & Professional Certifications167
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION88
10/31/2018123125340Open ↗
10/31/2018123125340Open ↗
08/21/2018122440830Open ↗
Showing 3 of 88 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST19
10/31/2018123125340Open ↗
08/21/2018122440830Open ↗
08/21/2018122440858Open ↗
Showing 3 of 19 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT18
10/31/2018123125340Open ↗
10/31/2018123125340Open ↗
10/31/2018123125340Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature15
10/14/2026M01367538-P1Open ↗
09/10/2026M01442611-I1Open ↗
09/04/2026M00425095-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/27/2026M00929600-I1Open ↗
09/27/2026M00929600-I1Open ↗
09/01/2026M00939650-S1Open ↗
Showing 3 of 8 on file for this type
▸BISAPPLICANT OWNER SIGNATURE7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/27/2026M00929600-I1Open ↗
08/27/2026M00939650-I1Open ↗
08/24/2026M00745860-I1Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
02/22/2018140742070Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/22/2018140742070Open ↗
▸Trade Schedules & Equipment39
▸BISSELF-CERT PLUMBING NOTICE8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT8
04/27/2016122550355Open ↗
04/19/2016122550355Open ↗
04/18/2016122550355Open ↗
Showing 3 of 8 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT8
03/22/2017140253311Open ↗
03/22/2017140253311Open ↗
10/14/2016122550355Open ↗
Showing 3 of 8 on file for this type
▸BISSCHEDULE B - PLUMBING4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸BISEQUIPMENT USE PERMITS3
10/14/2016122550355Open ↗
10/14/2016122550355Open ↗
Showing 2 of 3 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
10/31/2018123125340Open ↗
09/29/2016122892860Open ↗
Showing 2 of 3 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT2
02/21/2017140253311Open ↗
Showing 1 of 2 on file for this type
▸BISPLUMBING - SUPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISGAS CUT-OFF1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos62
▸BISASBESTOS: CERTIFICATION (DEP ACP5)27
08/15/2017123106977Open ↗
06/30/2017123100768Open ↗
Showing 2 of 27 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISASBESTOS INSPECTION REPORT4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/28/2026M00939650-S1Open ↗
08/28/2026M00997556-I1Open ↗
08/26/2026M01040223-I1Open ↗
Showing 3 of 4 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form1
09/02/2026M00745860-I1Open ↗
▸Energy Compliance41
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS25
08/15/2017123106977Open ↗
08/15/2017123106977Open ↗
06/30/2017123100768Open ↗
Showing 3 of 25 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS7
06/19/2017122481803Open ↗
06/01/2017122627979Open ↗
10/14/2016122550355Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISTR8: Energy Code Progress Inspections3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸Inspections & Test Reports38
▸BISTECHNICAL REPORT: RESPONSIBILITY15
02/22/2018140742070Open ↗
10/04/2017140253142Open ↗
10/04/2017140253142Open ↗
Showing 3 of 15 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX11
10/02/2017123106977Open ↗
10/02/2017123106977Open ↗
07/28/2016122627942Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER9
10/02/2017123106977Open ↗
04/01/2016140263480Open ↗
02/19/2016122627951Open ↗
Showing 3 of 9 on file for this type
▸BISCONCRETE DESIGN MIX (TR-3) 27-6052
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISConcrete Design Mix - 2008 CODE1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Approvals, Objections & Sign-offs54
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST21
03/06/2018140742070Open ↗
06/19/2017122481803Open ↗
06/01/2017122627979Open ↗
Showing 3 of 21 on file for this type
▸BISADMINISTRATIVE OBJECTIONS18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter5
10/14/2026M01367538-P1Open ↗
09/04/2026M00425095-I1Open ↗
08/18/2026M01367538-I1Open ↗
Showing 3 of 5 on file for this type
▸BISSUPERSEDING LETTER3
09/21/2016122440858Open ↗
07/21/2016122627951Open ↗
Showing 2 of 3 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
06/01/2017122627979Open ↗
10/14/2016122550355Open ↗
Showing 2 of 3 on file for this type
▸DOB NOWDEP Variance (V5) letter2
09/02/2026M00745860-I1Open ↗
08/28/2026M00929600-I1Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸BISLETTERS - APPRVD FAB CERT-INTENT1
06/19/2017122481803Open ↗
▸Cost, Insurance & Ownership61
▸BISCOST AFFIDAVIT61
10/31/2018123125340Open ↗
10/31/2018123125340Open ↗
10/03/2017140253240Open ↗
Showing 3 of 61 on file for this type
▸Filing & Intake Forms76
▸BISADDITIONAL INFORMATION32
11/13/2019123125340Open ↗
10/24/2018122440858Open ↗
10/24/2018122440830Open ↗
Showing 3 of 32 on file for this type
▸BISEFILING COVER SHEET27
10/31/2018123125340Open ↗
08/15/2017123106977Open ↗
06/30/2017123100768Open ↗
Showing 3 of 27 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET11
02/22/2018140742070Open ↗
Showing 1 of 11 on file for this type
▸BISBOROUGH INTAKE FORM6
10/22/2019123125340Open ↗
09/26/2019123125340Open ↗
08/21/2018122440830Open ↗
Showing 3 of 6 on file for this type
▸Other Documents4
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWManufacturer's Specifications1
09/10/2026M01442611-I1Open ↗
▸DOB NOWCalculations1
09/10/2026M01442611-I1Open ↗