← Back
Over six families without stores
506 EASTERN PARKWAY
BROOKLYN · BIN 3032900
💬 Discuss this project
1914Year Built
4Stories
C1Building Class
R6Zoning
18,200 sfGross Floor Area
16Units
Rent Stabilized8 Open Violations ▸FDNY Report ↗
Over six families without stores · Owner of record: PEACE & QUIET REALTY · 6,600 sf lot · 2.76 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
89-08 48TH AVE109/15/2026
PRESPECTIVE GENERAL CONSTRUCTION IN407/08/2026
PEACE & QUIET REALTY403/22/2026
RJ PARKER CORP103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
XIUCHENG LI109/01/2026
MUMTAZ ENTERPRISES206/03/2025
BANGASH ASSOCIATES INC.111/09/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SHEIKH EXPEDITING603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LAXU8 INCGeneral Contractor407/08/2026
PERSPECTIVE GENERAL CONSTGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MUMTAZ ENTERPRISES9459206/03/2025
Building Lifecycle
All (81)Filed (4)Permit Issued (3)Signed Off (2)Violation (60)Special Inspection (12)
09/01/2026
Filed — Alteration
B01445576-I1
08/19/2026
Special inspection requirement — Fire-Resistance Rated Construction
08/18/2026
Special inspection requirement — Tenant Protection Plan Compliance
08/18/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
08/13/2026
Special inspection requirement — Final
11/20/2025
Violation issued (HPD, closed)
I
11/17/2025
Signed off — Alteration
EXTEROR FACADE REPAIR AS EXTERIOR FACADE REPAIR RE-POINTING AND REPLACE WINDOW LINTELS AND REMOVE & REBUILD PARAPET WALL AT FRON ELEVATION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01129838-I1
11/17/2025
Signed off — Alteration
EXTEROR FACADE REPAIR AS EXTERIOR FACADE REPAIR RE-POINTING AND REPLACE WINDOW LINTELS AND REMOVE & REBUILD PARAPET WALL AT FRON ELEVATION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01129838-S1
06/03/2025
Filed — Alteration
EXTEROR FACADE REPAIR AS EXTERIOR FACADE REPAIR RE-POINTING AND REPLACE WINDOW LINTELS AND REMOVE & REBUILD PARAPET WALL AT FRON ELEVATION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01129838-P1
06/03/2025
Special inspection requirement — Final
Mumtaz Hussain
06/03/2025
Special inspection requirement — Masonry
Mumtaz Hussain
06/03/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mumtaz Hussain
06/03/2025
Special inspection requirement — Tenant Protection Plan Compliance
Mumtaz Hussain
06/02/2025
Special inspection requirement — Masonry
Mumtaz Hussain
06/02/2025
Special inspection requirement — Final
Mumtaz Hussain
06/02/2025
Special inspection requirement — Tenant Protection Plan Compliance
Mumtaz Hussain
06/02/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mumtaz Hussain
04/01/2025
Permit issued — General Construction
B01129838-S1-GC
03/21/2025
Filed — Alteration
EXTEROR FACADE REPAIR AS EXTERIOR FACADE REPAIR RE-POINTING AND REPLACE WINDOW LINTELS AND REMOVE & REBUILD PARAPET WALL AT FRON ELEVATION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01129838-S1
03/11/2025
Permit issued — Supported Scaffold
B01129838-I1-SF
01/22/2025
Violation issued (HPD, closed)
C
01/22/2025
Violation issued (HPD, open)
C
01/22/2025
Violation issued (HPD, open)
B
01/22/2025
Violation issued (HPD, closed)
C
01/22/2025
Violation issued (HPD, open)
B
01/22/2025
Violation issued (HPD, open)
C
11/13/2024
Permit issued — Supported Scaffold
B01129838-I1-SF
11/09/2024
Filed — Alteration
EXTEROR FACADE REPAIR AS EXTERIOR FACADE REPAIR RE-POINTING AND REPLACE WINDOW LINTELS AND REMOVE & REBUILD PARAPET WALL AT FRON ELEVATION AS PER PLAN. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
B01129838-I1
04/10/2024
Violation issued (HPD, closed)
A
09/08/2023
Violation issued (HPD, closed)
B
09/08/2023
Violation issued (HPD, closed)
B
09/08/2023
Violation issued (HPD, closed)
A
02/24/2022
Violation issued (HPD, closed)
A
02/24/2022
Violation issued (HPD, closed)
I
04/08/2021
Violation issued (HPD, closed)
A
10/30/2019
Violation issued (HPD, closed)
I
10/04/2019
Violation issued (HPD, open)
B
10/04/2019
Violation issued (HPD, closed)
C
10/04/2019
Violation issued (HPD, closed)
C
10/04/2019
Violation issued (HPD, closed)
C
10/04/2019
Violation issued (HPD, open)
B
06/20/2017
Violation issued (HPD, closed)
A
06/20/2017
Violation issued (HPD, closed)
A
06/20/2017
Violation issued (HPD, closed)
A
06/20/2017
Violation issued (HPD, closed)
A
10/08/2015
Violation issued (HPD, closed)
I
06/17/2015
Violation issued (HPD, closed)
A
11/14/2014
Violation issued (HPD, closed)
B
06/25/2014
Violation issued (HPD, closed)
A
06/25/2014
Violation issued (HPD, closed)
C
03/17/2013
Violation issued (HPD, closed)
B
11/13/2012
Violation issued (HPD, closed)
A
11/13/2012
Violation issued (HPD, closed)
A
11/13/2012
Violation issued (HPD, closed)
C
11/13/2012
Violation issued (HPD, closed)
A
11/13/2012
Violation issued (HPD, closed)
C
11/13/2012
Violation issued (HPD, closed)
C
11/13/2012
Violation issued (HPD, closed)
C
11/13/2012
Violation issued (HPD, closed)
C
11/13/2012
Violation issued (HPD, closed)
A
Latest 60 of 81 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offLAXU8 INC04/01/2025
DOB NOWSupported ScaffoldSigned-offLAXU8 INC03/11/2025
DOB NOWSupported ScaffoldSigned-offPERSPECTIVE GENERAL CONST11/13/2024
BISBLISSUEDAPRA FUEL OIL BYRS GRP IN01/26/2005
BISBLISSUEDAPRA FUEL OIL BYRS GRP IN10/08/2003
BISPLISSUEDJ.JEKOWSKY & SON INC08/28/1998
BISBLISSUEDJ.JEKOWSKY & SON INC08/28/1998
2 projects · most recent 08/17/2026
General Wiring
FiledStatusContractorScope
08/17/2026Permit IssuedCOMBINED ELECL CONTNG INCGeneral Wiring
08/17/2026Permit IssuedCOMBINED ELECL CONTNG INCGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 12
DateRequirementInspectorRole
08/19/2026Fire-Resistance Rated Construction—progress
08/18/2026Tenant Protection Plan Compliance—special
08/18/2026Fire-Resistant Penetrations and Joints—special
08/13/2026Final—progress
06/03/2025FinalMumtaz Hussainprogress
06/03/2025MasonryMumtaz Hussainspecial
06/03/2025Structural Stability – Alterations of existing buildingsMumtaz Hussainspecial
06/03/2025Tenant Protection Plan ComplianceMumtaz Hussainspecial
06/02/2025MasonryMumtaz Hussainspecial
06/02/2025FinalMumtaz Hussainprogress
06/02/2025Tenant Protection Plan ComplianceMumtaz Hussainspecial
06/02/2025Structural Stability – Alterations of existing buildingsMumtaz Hussainspecial
▾Documents — 17 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/15/2026B01445576-I1Request digital key ↗
08/22/2026B01129838-P1Request digital key ↗
08/22/2026B01129838-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications11
▸DOB NOWSpecial Inspector Seal & Signature5
08/27/2026B01129838-P1Open ↗
08/27/2026B01129838-P1Open ↗
08/25/2026B01129838-S1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/15/2026B01445576-I1Open ↗
08/22/2026B01129838-S1Open ↗
08/13/2026B01129838-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026B01129838-P1Open ↗
08/25/2026B01129838-S1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/22/2026B01129838-S1Open ↗
08/13/2026B01129838-P1Open ↗