1932Year Built
1Stories
E1Building Class
M1-2Zoning
5,345 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
General warehouse · Owner of record: CHIOS MANAGEMENT CORP. · 5,345 sf lot · 1 FAR built · Flood zone X500
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof23p · 1 filing · 20 docs
Floor 126p · 2 filings · 20 docs
Mezzanine22p · 1 filing · 20 docs
Site & exterior1p · 1 filing · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MESTOUSIS ENTERPRISES1807/08/2026
POINT H REALTY803/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/04/2020$750K—Private party → CHIOS MANAGEMENT CORP.$140/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GINO O. LONGO, ARCHITECT505/29/2025
ADNAN ENGINEERING, P.C.603/08/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
POINT H. REALTY CORPGeneral Contractor607/08/2026
BYPASS MECHANICAL CORPPlumbing607/08/2026
ZATOS PLBG AND HTG INCPlumbing207/08/2026
EMPIRE ELECTRIC NYC LLCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616512/09/2024
Building Lifecycle
All (41)Filed (11)Permit Issued (6)Violation (5)Inspection (5)Objection (14)
05/29/2025
Filed — Alteration
APPLICATION HEREWITH FILED FOR PROPOSED EXHAUST VENT AT RESTROOM WITH NO WINDOW. NO CHANGE IN OCCUPANCY, USE OR EGRESS.
X00436396-S1
05/27/2025
Permit issued — Plumbing
X00436396-I1-PL
05/16/2025
Inspection — Certified Storm Drainage-ST-Piping-Roughing
Certified
View inspection ↗
05/13/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/09/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/13/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/06/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/09/2024
Filed — Alteration
APPLICATION HEREWITH FILED FOR PROPOSED EXHAUST VENT AT RESTROOM WITH NO WINDOW. NO CHANGE IN OCCUPANCY, USE OR EGRESS.
X00436396-P1
09/12/2024
Permit issued — Plumbing
X00436396-I1-PL
03/25/2023
Objection resolved — Addressed
03/14/2023
Objection raised — Inspections
03/14/2023
Objection resolved — Addressed
03/14/2023
Objection raised — Other
03/14/2023
Objection resolved — Addressed
03/14/2023
Objection raised — Fire_Protection
03/14/2023
Objection resolved — Addressed
03/14/2023
Objection raised — Other
03/14/2023
Objection resolved — Addressed
03/14/2023
Objection raised — Scope
03/14/2023
Objection resolved — Addressed
03/13/2023
Objection raised — Admin
03/10/2023
Filed — Alteration
APPLICATION HEREWITH FILED FOR PROPOSED EXHAUST VENT AT RESTROOM WITH NO WINDOW. NO CHANGE IN OCCUPANCY, USE OR EGRESS.
X00436396-I1
03/08/2023
Filed — Alteration
APPLICATION FILED FOR INCREASED BUILDING HEIGHT, HORIZONTAL ENLARGEMENT OF EXISTING MASONRY BUILDING. STRUCTURAL WORK IN CONJUNCTION WITH JOB #240282591
X00415996-P4
03/08/2023
Filed — Alteration
APPLICATION FILED FOR INCREASED BUILDING HEIGHT, HORIZONTAL ENLARGEMENT OF EXISTING MASONRY BUILDING. STRUCTURAL WORK IN CONJUNCTION WITH JOB #240282591
X00415996-P3
07/29/2022
Permit issued — Foundation
X00415996-S1-FO
06/21/2022
Permit issued — Structural
X00415996-I1-ST
06/14/2022
Permit issued — Construction Fence
X00349026-I1-FN
05/27/2022
Objection resolved — Addressed
05/24/2022
Objection raised — Admin
05/09/2022
Filed — Alteration
APPLICATION FILED FOR INCREASED BUILDING HEIGHT, HORIZONTAL ENLARGEMENT OF EXISTING MASONRY BUILDING. STRUCTURAL WORK IN CONJUNCTION WITH JOB #240282591
X00415996-P2
05/09/2022
Filed — Alteration
APPLICATION FILED FOR INCREASED BUILDING HEIGHT, HORIZONTAL ENLARGEMENT OF EXISTING MASONRY BUILDING. STRUCTURAL WORK IN CONJUNCTION WITH JOB #240282591
X00415996-P1
04/12/2022
Filed — Alteration
APPLICATION FILED FOR TEMPORARY CONSTRUCTION FENCE. NO CHANGE IN OCCUPANCY, USE OR EGRESS.
X00349026-P1
03/09/2021
Filed — Alteration
APPLICATION FILED FOR INCREASED BUILDING HEIGHT, HORIZONTAL ENLARGEMENT OF EXISTING MASONRY BUILDING. STRUCTURAL WORK IN CONJUNCTION WITH JOB #240282591
X00415996-S1
10/26/2020
Filed — Alteration
APPLICATION FILED FOR INCREASED BUILDING HEIGHT, HORIZONTAL ENLARGEMENT OF EXISTING MASONRY BUILDING. STRUCTURAL WORK IN CONJUNCTION WITH JOB #240282591
X00415996-I1
07/28/2020
Permit issued — Construction Fence
X00349026-I1-FN
06/17/2020
Filed — Alteration
APPLICATION FILED FOR TEMPORARY CONSTRUCTION FENCE. NO CHANGE IN OCCUPANCY, USE OR EGRESS.
X00349026-I1
06/10/1996
Violation issued (ECB, closed)
Construction
02/07/1995
Violation issued (ECB, closed)
Construction
02/07/1995
Violation issued (ECB, closed)
Construction
09/07/1993
Violation issued (ECB, closed)
Construction
03/08/1993
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offZATOS PLBG AND HTG INC05/27/2025
DOB NOWPlumbingSigned-offBYPASS MECHANICAL CORP09/12/2024
DOB NOWFoundationPermit IssuedPOINT H. REALTY CORP07/29/2022
DOB NOWStructuralPermit IssuedPOINT H. REALTY CORP06/21/2022
DOB NOWConstruction FencePermit IssuedPOINT H. REALTY CORP06/14/2022
DOB NOWConstruction FencePermit IssuedPOINT H. REALTY CORP07/28/2020
BIS—ISSUEDPOINT H. REALTY CORP06/07/2023
BIS—ISSUEDPOINT H. REALTY CORP05/19/2023
BISOTISSUEDPOINT H. REALTY CORP07/31/2020
1 project · most recent 05/29/2025
Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
05/29/2025——Ventilation Systems
Ventilation
Broan # 696N 50 CFM ×2
1 project · most recent 05/29/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
05/29/2025Signed-offZATOS PLBG AND HTG INCGas, Storm, Water/Sanitary
1 project · most recent 07/22/2018
FiledStatusContractorScope
07/22/2018CompleteEMPIRE ELECTRIC NYC LLC2 meters, 2 new_meters
1 project · most recent 03/08/2023
Steel Masonry
FiledStatusContractorScope
03/08/2023Permit IssuedPOINT H. REALTY CORPSteel, Masonry
1 project · most recent 04/12/2022
Fence
FiledStatusContractorScope
04/12/2022Permit IssuedPOINT H. REALTY CORPFence
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
05/16/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
05/13/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/09/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
03/13/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/06/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 40
DateRequirementInspectorRole
12/12/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
12/12/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
12/12/2024HVAC and service water heating system controls FAHAD FATEHenergy_progress
12/12/2024HVAC and service water heating equipment FAHAD FATEHenergy_progress
12/12/2024HVAC insulation and sealing FAHAD FATEHenergy_progress
11/14/2024Energy Code Compliance InspectionsFAHAD FATEHprogress
11/14/2024HVAC and service water heating system controls FAHAD FATEHenergy_progress
11/14/2024HVAC insulation and sealing FAHAD FATEHenergy_progress
11/14/2024HVAC and service water heating equipment FAHAD FATEHenergy_progress
11/14/2024Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
07/15/2024Mechanical Systems—special
07/15/2024Final—progress
03/08/2023MasonryFAHAD FATEHspecial
03/08/2023Structural Cold-Formed SteelFAHAD FATEHspecial
03/08/2023Post-installed AnchorsFAHAD FATEHspecial
03/08/2023Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
03/08/2023Structural Steel - DetailsFAHAD FATEHspecial
03/08/2023Structural Steel - High Strength BoltingFAHAD FATEHspecial
03/08/2023Structural Steel - WeldingFAHAD FATEHspecial
03/08/2023FinalFAHAD FATEHprogress
03/08/2023Footing and FoundationFAHAD FATEHprogress
03/08/2023Concrete - Cast-In-PlaceFAHAD FATEHspecial
03/08/2023Helical Piles Foundation (BB # 2014-020)FAHAD FATEHspecial
03/08/2023Subgrade InspectionsFAHAD FATEHspecial
03/08/2023Subsurface Investigations (Borings/Test Pits)Soorjbally Harilallspecial
Latest 25 of 40.
▾Documents — 145 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch - Foundation3
08/23/2026X00415996-S1Request digital key ↗
08/23/2026X00415996-P1Request digital key ↗
08/15/2026X00415996-P3Request digital key ↗
▸DOB NOWPlans/Sketch - Structural3
08/23/2026X00415996-I1Request digital key ↗
08/23/2026X00415996-P4Request digital key ↗
08/15/2026X00415996-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence2
08/24/2026X00349026-P1Request digital key ↗
08/24/2026X00349026-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
08/19/2026X00436396-P1Request digital key ↗
08/15/2026X00436396-I1Request digital key ↗
▸DOB NOWPlans/Sketch1
08/19/2026X00436396-S1Request digital key ↗
▸Applications & Permits24
▸BISPLAN / WORK APPROVAL APPLICATION13
03/17/2023240282591Open ↗
01/11/2023240282591Open ↗
03/30/2022240282591Open ↗
Showing 3 of 13 on file for this type
▸BISWORK PERMIT APPLICATION4
06/07/2023240282591Open ↗
05/22/2023240282591Open ↗
05/22/2023240282591Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION3
07/21/2020220731929Open ↗
07/21/2020220731929Open ↗
07/21/2020220731929Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
01/20/2023240299495Open ↗
02/01/2021240299495Open ↗
▸BISPARTIAL DEMO PLAN & DS1 (FOR AL/EW-OT PERMITS)1
07/28/2020220731929Open ↗
▸BISPARTIAL DEMO: 10-DAY NOTICE (FOR AL/EW-OT PERMITS)1
07/29/2020220731929Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISZONING DIAGRAM3
03/01/2023240282591Open ↗
02/25/2022240282591Open ↗
03/22/2021240282591Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
03/22/2021240282591Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
03/22/2021240282591Open ↗
▸Seals & Professional Certifications28
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/24/2026X00349026-P1Open ↗
08/24/2026X00349026-I1Open ↗
08/23/2026X00415996-S1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/02/2026X00415996-P3Open ↗
09/01/2026X00436396-P1Open ↗
09/01/2026X00436396-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/02/2026X00415996-P3Open ↗
09/02/2026X00415996-P3Open ↗
09/02/2026X00415996-P3Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
03/22/2021240282591Open ↗
02/01/2021240299495Open ↗
▸BISAPPLICANT OWNER SIGNATURE2
03/22/2021240282591Open ↗
02/01/2021240299495Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION1
04/29/2020220731929Open ↗
▸Safety & Tenant Protection5
▸BISSTREET TREE CHECKLIST4
03/01/2023240282591Open ↗
01/20/2023240299495Open ↗
03/22/2021240282591Open ↗
Showing 3 of 4 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM1
04/29/2020220731929Open ↗
▸Environmental & Asbestos11
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/23/2026X00415996-S1Open ↗
08/23/2026X00415996-I1Open ↗
08/23/2026X00415996-P4Open ↗
Showing 3 of 9 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
03/22/2021240282591Open ↗
04/29/2020220731929Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
12/28/2022240282591Open ↗
03/22/2021240282591Open ↗
07/21/2020220731929Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
03/22/2021240282591Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
04/29/2020220731929Open ↗
▸Inspections & Test Reports20
▸BISTECHNICAL REPORT: RESPONSIBILITY13
03/01/2023240282591Open ↗
03/01/2023240282591Open ↗
12/28/2022240282591Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSOIL REPORT3
08/15/2026X00415996-P3Open ↗
08/13/2026X00415996-P1Open ↗
08/13/2026X00415996-S1Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION2
03/22/2021240282591Open ↗
06/17/2020220731929Open ↗
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026X00415996-S1Open ↗
▸DOB NOWTR4 Plot Diagram1
08/13/2026X00415996-S1Open ↗
▸Approvals, Objections & Sign-offs8
▸BISSCHEDULE A - OCCUPANCY / USE5
01/11/2023240282591Open ↗
03/18/2022240282591Open ↗
03/03/2022240282591Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
01/20/2023240299495Open ↗
01/20/2023240299495Open ↗
01/20/2023240299495Open ↗
▸Cost, Insurance & Ownership9
▸BISPROJECT-SPECIFIC GL INSURANCE4
05/22/2023240282591Open ↗
04/14/2023240282591Open ↗
04/11/2023240282591Open ↗
Showing 3 of 4 on file for this type
▸BISCOST AFFIDAVIT4
01/12/2022240282591Open ↗
03/22/2021240282591Open ↗
06/03/2020220731929Open ↗
Showing 3 of 4 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
07/21/2020220731929Open ↗
▸Filing & Intake Forms13
▸BISADDITIONAL INFORMATION9
05/18/2023240282591Open ↗
04/11/2023240282591Open ↗
03/01/2023240282591Open ↗
Showing 3 of 9 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET1
02/01/2021240299495Open ↗
▸BISBOROUGH INTAKE FORM1
05/22/2023240282591Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
02/01/2021240299495Open ↗
▸BISEFILING COVER SHEET1
04/29/2020220731929Open ↗
▸Other Documents6
▸BISSupporting Document: Fee Exempt3
02/25/2022240282591Open ↗
02/25/2022240282591Open ↗
03/22/2021240282591Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
02/01/2021240299495Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
01/06/2023240282591Open ↗
▸BISPLOT DIAGRAM1
02/25/2022240282591Open ↗