| Owner | Filings | Most Recent |
|---|---|---|
| DIMOLA CONSTRUCTION | 22 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| JOSEPH M. MORACE, A.I.A., ARCHITECT | 8 | 08/25/2025 |
| C&P DESIGN CONSULTANTS | 1 | 10/18/2024 |
| SANNA & LOCCISANO ARCHITECTS, P.C. | 2 | 04/27/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| PATRICIA L GASS | 16 | 03/21/2026 |
| SANNA LOCCISANO ARCHITECTS P C | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DIMOLA CONSTRUCTION CORP | General Contractor | 7 | 07/08/2026 |
| DUO PLUMBING & HTG CORP. | Plumbing | 2 | 07/08/2026 |
| DUO PLBG. & HTG. CORP | Fire Protection | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 5 | 08/25/2025 |
| SRA PLANNING & EXPEDITING | 5677 | 4 | 08/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | DIMOLA CONSTRUCTION | 05/16/2025 |
| DOB NOW | General Construction | Permit Issued | DIMOLA CONSTRUCTION | 02/07/2025 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 11/12/2024 |
| DOB NOW | Plumbing | Signed-off | DUO PLUMBING & HTG CORP. | 10/25/2024 |
| DOB NOW | Plumbing | Signed-off | DUO PLBG. & HTG. CORP | 10/25/2024 |
| DOB NOW | Plumbing | Signed-off | DUO PLUMBING & HTG CORP. | 08/13/2024 |
| DOB NOW | Foundation | Permit Issued | DIMOLA CONSTRUCTION | 07/31/2024 |
| DOB NOW | Construction Fence | Signed-off | DIMOLA CONSTRUCTION | 03/15/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/25/2025 | Signed-off | DIMOLA CONSTRUCTION CORP | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/25/2025 | Signed-off | DUO PLUMBING & HTG CORP. | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/28/2024 | Complete | B & R ELEC'L CONTR'G, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/25/2025 | Signed-off | DIMOLA CONSTRUCTION CORP | Concrete, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/25/2025 | Signed-off | DIMOLA CONSTRUCTION CORP | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/19/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/22/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/22/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 05/19/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/09/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 05/01/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/21/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/21/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 03/14/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/20/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 11/15/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/23/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/12/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/26/2025 | Fenestration and door U-factor and product ratings | WILLIAM MONTAGUE | energy_progress |
| 08/26/2025 | Subsurface Conditions – Fill Placement & In-Place Density | WILLIAM MONTAGUE | special |
| 08/26/2025 | Exterior Insulation and Finish Systems (EIFS) | Stanislav Pilipenko | special |
| 08/26/2025 | Subgrade Inspections | Stanislav Pilipenko | special |
| 08/26/2025 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 08/26/2025 | Heating Systems | Stanislav Pilipenko | special |
| 08/26/2025 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 08/26/2025 | Excavations - Sheeting, Shoring, and Bracing | Stanislav Pilipenko | special |
| 08/26/2025 | Structural Steel - Details | WILLIAM MONTAGUE | special |
| 08/26/2025 | Mechanical Systems | Stanislav Pilipenko | special |
| 08/26/2025 | Structural Steel - Welding | WILLIAM MONTAGUE | special |
| 08/26/2025 | Structural Steel - High Strength Bolting | WILLIAM MONTAGUE | special |
| 08/26/2025 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 08/26/2025 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 08/26/2025 | Fire-Resistance Rated Construction | Stanislav Pilipenko | progress |
| 08/26/2025 | Final | Stanislav Pilipenko | progress |
| 08/26/2025 | Footing and Foundation | Stanislav Pilipenko | progress |
| 08/26/2025 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 08/26/2025 | Fireplaces | WILLIAM MONTAGUE | energy_progress |
| 08/26/2025 | Air barrier — testing | WILLIAM MONTAGUE | energy_progress |
| 08/26/2025 | HVAC-R and service water heating equipment | WILLIAM MONTAGUE | energy_progress |
| 08/26/2025 | Interior lighting power | WILLIAM MONTAGUE | energy_progress |
| 08/26/2025 | Permanent certificate | WILLIAM MONTAGUE | energy_progress |
| 08/26/2025 | Maintenance information | WILLIAM MONTAGUE | energy_progress |
| 08/26/2025 | Fenestration air leakage | WILLIAM MONTAGUE | energy_progress |