Roof90p · 3 filings · 20 docs
ArchitectureElectricalFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Protection and Mechanical Methods · Sprinklers · Structural · Supported Scaffold
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY ROOF PROTECTION AT ADJACENT PROPERTIES AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. TEMPORARY ROOF PROTECTION SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE.
On file for this project
2 documents · 1 drawing sheet
INSTALLATION OF MEDIUM DUTY PIPE SCAFFOLDING AND NEEDLE BEAM PLATFORM AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. PIPE SCAFFOLD AND NEEDLE BEAM PLATFORM SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE.
On file for this project
2 documents
Floor 679p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 2 drawing sheets
Floor 581p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 4 drawing sheets
Floor 481p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 4 drawing sheets
Floor 381p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 4 drawing sheets
Floor 278p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 1 drawing sheet
Floor 180p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 3 drawing sheets
Mezzanine83p · 1 filing · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 6 drawing sheets
Cellar84p · 1 filing · 20 docs
ArchitectureCivilFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Earth Work · General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural · Support of Excavation
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 7 drawing sheets
Site & exterior99p · 3 filings · 20 docs
ArchitectureDMElectricalEquipmentFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
Construction Fence · Sidewalk Shed · Supported Scaffold
SUPPORT OF EXCAVATION WORK FOR NEW 6-STORY CONCRETE RESIDENTIAL WITH CELLAR.
On file for this project
130 documents · 12 drawing sheets
INSTALLATION OF MEDIUM DUTY PIPE SCAFFOLDING AND NEEDLE BEAM PLATFORM AS PER PLANS. NO CHANGE IN USE OCCUPANCY OR EGRESS UNDER THIS APPLICATION. PIPE SCAFFOLD AND NEEDLE BEAM PLATFORM SHALL COMPLY WITH CHAPTER 33 OF THE 2014 NYC BUILDING CODE.
On file for this project
2 documents · 6 drawing sheets
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLANS. SIDEWALK SHED SHALL COMPLY WITH CHAPTER 33 OF THE 2022 NYC BUILDING CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 12 drawing sheets