← Back
Two family frame
51 STOCKHOLM STREET
BROOKLYN · Bushwick (West) · BIN 3344153
💬 Discuss this project
1998Year Built
2Stories
B2Building Class
R6Zoning
2,100 sfGross Floor Area
2Units
8 Open Violations 1 unresolved · 7 paperwork only ▸FDNY Report ↗
Two family frame · 2,811 sf lot · 0.75 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalMechanicalPlumbingFire ProtectionGeneral
Permit Issued — active, not yet Signed-off
PenthouseUnder Construction20p · 1 filing · 20 docs
Floor 4Under Construction19p · 1 filing · 20 docs
Floor 3Under Construction14p · 1 filing · 20 docs
Floor 2Under Construction19p · 1 filing · 20 docs
Floor 1Under Construction18p · 1 filing · 20 docs
CellarUnder Construction27p · 3 filings · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Z & T ENGINEERING, P.C.108/10/2026
JRS CONSULTING304/29/2025
R & O ENGINEERING403/26/2025
D&E BUILD EVERGREEN INC.103/18/2025
PETER CHO ARCHITECTS, PLLC103/18/2025
NY BUILDING ASSOCIATES INC109/27/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AM EXPEDITING DRAFTING DESIGN203/21/2026
METRO DESIGN CONSULTANTS INC403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYC BUILDING SOLUTIONS COGeneral Contractor207/31/2026
RITE WAY HEATING CORPPlumbing109/10/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Z & T ENGINEERING, P.C.591808/10/2026
Building Lifecycle
All (136)Filed (11)Permit Issued (3)Violation (12)Objection (80)Special Inspection (30)
09/09/2026
Permit issued — Plumbing
B01155671-S8-PL
08/10/2026
Filed — Alteration
FILED HEREWITH TO CLARIFY MEANS, METHODS AND SEQUENCE OF PARTIAL DEMOLITION AND REQUIRED TEMPORARY BRACING FILED UNDER B01155671-I1.
B01442904-I1
08/07/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Fei Zeng
08/07/2026
Special inspection requirement — Final
Fei Zeng
08/07/2026
Special inspection requirement — Demolition
Fei Zeng
07/30/2026
Permit issued — General Construction
B01155671-I1-GC
07/23/2026
Permit issued — Construction Fence
B01155671-S6-FN
04/28/2026
Objection resolved — Resolved
04/16/2026
Objection resolved — Addressed
04/15/2026
Objection raised — Admin
03/30/2026
Objection resolved — Addressed
03/30/2026
Objection resolved — Addressed
03/30/2026
Objection resolved — Addressed
03/30/2026
Objection resolved — Resolved
01/30/2026
Objection resolved — Addressed
10/17/2025
Objection resolved — Addressed
10/17/2025
Objection resolved — Addressed
08/07/2025
Objection resolved — Addressed
07/24/2025
Objection raised — Scope
07/24/2025
Objection raised — Fire_Protection
07/24/2025
Objection raised — Zoning
07/09/2025
Objection raised — Cost
06/26/2025
Objection resolved — Addressed
06/26/2025
Objection resolved — Addressed
06/26/2025
Objection resolved — Addressed
06/26/2025
Objection resolved — Addressed
05/07/2025
Objection raised — Scope
05/05/2025
Objection raised — Other
05/05/2025
Objection raised — Plumbing
05/05/2025
Objection raised — Admin
05/05/2025
Objection raised — Plumbing
05/05/2025
Objection raised — Other
05/05/2025
Objection raised — Cost
04/30/2025
Objection resolved — Resolved
04/30/2025
Objection resolved — Resolved
04/30/2025
Objection resolved — Resolved
04/30/2025
Objection resolved — Resolved
04/30/2025
Objection resolved — Resolved
04/30/2025
Objection resolved — Resolved
04/29/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH DOB NOW APPLICATION #B01155671-I1. FENCE SHALL COMPLY WITH CHAPTER 33 OF THE NYC BUILDING CODE.
B01155671-S8
04/29/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH DOB NOW APPLICATION #B01155671-I1. FENCE SHALL COMPLY WITH CHAPTER 33 OF THE NYC BUILDING CODE.
B01155671-S9
04/29/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
INSTALLATION OF TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH DOB NOW APPLICATION #B01155671-I1. FENCE SHALL COMPLY WITH CHAPTER 33 OF THE NYC BUILDING CODE.
B01155671-S7
04/28/2025
Special inspection requirement — Post-installed Anchors
Fei Zeng
04/28/2025
Special inspection requirement — Shutoff dampers
Fei Zeng
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Fei Zeng
04/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Fei Zeng
04/28/2025
Special inspection requirement — HVAC-R and service water heating system controls
Fei Zeng
04/28/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Fei Zeng
04/28/2025
Special inspection requirement — HVAC-R and service water heating equipment
Fei Zeng
04/28/2025
Special inspection requirement — Maintenance information
Fei Zeng
04/28/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Fei Zeng
04/28/2025
Special inspection requirement — Maintenance information
Fei Zeng
04/28/2025
Special inspection requirement — HVAC-R and service water heating system controls
Fei Zeng
04/28/2025
Special inspection requirement — HVAC-R and service water heating equipment
Fei Zeng
04/28/2025
Special inspection requirement — Energy Code Compliance Inspections
Fei Zeng
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Fei Zeng
04/28/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Fei Zeng
04/23/2025
Objection resolved — Addressed
04/23/2025
Objection resolved — Addressed
04/23/2025
Objection resolved — Addressed
Latest 60 of 136 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedRITE WAY HEATING CORP09/09/2026
DOB NOWGeneral ConstructionPermit IssuedNYC BUILDING SOLUTIONS CO07/30/2026
DOB NOWConstruction FencePermit IssuedNYC BUILDING SOLUTIONS CO07/23/2026
BISOTISSUEDAM EXPEDITING DRAFTING &11/21/2019
BIS—ISSUEDBANTA HOMES COR04/08/1998
BISPLISSUEDBLAU MECHANICAL CORP11/12/1997
BIS—ISSUEDBANTA HOMES COR07/24/1997
1 project · most recent 04/29/2025
Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
04/29/2025Permit IssuedNYC BUILDING SOLUTIONS COHeating and Air Conditioning Systems
Heat / Cool
Cooper & Hunter CH-HPR28M-230VO 28,000 BTU · Condensing Unit ×7
CH-HPR12M-230VO 12,000 BTU · Condensing Unit ×1
CH-HPR48M-230VO 48,000 BTU · Condensing Unit ×1
1 project · most recent 04/29/2025
Sprinkler System
FiledStatusContractorScope
04/29/2025——Sprinkler System
2 projects · most recent 04/29/2025
Water/Sanitary Storm Gas
FiledStatusContractorScope
04/29/2025Permit IssuedRITE WAY HEATING CORPStorm, Water/Sanitary
09/27/2019——Gas, Water/Sanitary
1 project · most recent 09/23/2026
General Wiring
FiledStatusContractorScope
09/23/2026Permit IssuedK.A.B. ELECTRIC CORPGeneral Wiring
2 projects · most recent 08/10/2026
Concrete Masonry
FiledStatusContractorScope
08/10/2026——2 scope_items
04/29/2025Permit IssuedRITE WAY HEATING CORPConcrete, Masonry
1 project · most recent 04/29/2025
Fence
FiledStatusContractorScope
04/29/2025Permit IssuedRITE WAY HEATING CORPFence
▾Special Inspection Requirements (DOB NOW) — 58
DateRequirementInspectorRole
08/07/2026Structural Stability – Alterations of existing buildingsFei Zengspecial
08/07/2026FinalFei Zengprogress
08/07/2026DemolitionFei Zengspecial
04/28/2025Post-installed AnchorsFei Zengspecial
04/28/2025Shutoff dampersFei Zengenergy_progress
04/28/2025Fire-Resistant Penetrations and JointsFei Zengspecial
04/28/2025Energy Code Compliance InspectionsFei Zengprogress
04/28/2025HVAC-R and service water heating system controlsFei Zengenergy_progress
04/28/2025HVAC-R and service water piping design and insulationFei Zengenergy_progress
04/28/2025HVAC-R and service water heating equipmentFei Zengenergy_progress
04/28/2025Maintenance informationFei Zengenergy_progress
04/28/2025HVAC-R and service water piping design and insulationFei Zengenergy_progress
04/28/2025Maintenance informationFei Zengenergy_progress
04/28/2025HVAC-R and service water heating system controlsFei Zengenergy_progress
04/28/2025HVAC-R and service water heating equipmentFei Zengenergy_progress
04/28/2025Energy Code Compliance InspectionsFei Zengprogress
04/28/2025Fire-Resistant Penetrations and JointsFei Zengspecial
04/28/2025Fire-Resistant Penetrations and JointsFei Zengspecial
04/17/2025Structural Stability – Alterations of existing buildingsFei Zengspecial
04/04/2025Sprinkler SystemsFei Zengspecial
04/04/2025FinalFei Zengprogress
04/04/2025Mechanical SystemsFei Zengspecial
03/18/2025Structural Stability – Alterations of existing buildingsFei Zengspecial
03/18/2025Structural Stability – Alterations of existing buildingsFei Zengspecial
03/14/2025Interior lighting powerFei Zengenergy_progress
Latest 25 of 58.
▾Documents — 59 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch1
08/16/2026B01442904-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing Legalization1
09/02/2026B00225359-I1Request digital key ↗
▸Applications & Permits9
▸BISPLAN / WORK APPROVAL APPLICATION3
01/27/2026340916682Open ↗
04/07/2025340916682Open ↗
09/20/2019321976153Open ↗
▸BISWORK PERMIT APPLICATION3
02/18/2021321976153Open ↗
12/01/2020321976153Open ↗
11/22/2019321976153Open ↗
▸BISBPP-5 - Authorization to the Department of Transportation2
05/14/2025340916682Open ↗
04/09/2025340916682Open ↗
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION1
05/14/2025340916682Open ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01155671-I1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01155671-I1Open ↗
▸Seals & Professional Certifications23
▸DOB NOWProgress Inspector Seal & Signature9
09/02/2026B01155671-S8Open ↗
09/02/2026B01155671-S8Open ↗
08/30/2026B01155671-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
09/02/2026B01155671-S8Open ↗
09/01/2026B01155671-S9Open ↗
08/30/2026B01155671-I1Open ↗
Showing 3 of 8 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
11/22/2019321976153Open ↗
09/20/2019321976153Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/16/2026B01442904-I1Open ↗
08/13/2026B00225359-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
04/07/2025340916682Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
04/07/2025340916682Open ↗
▸Safety & Tenant Protection4
▸BISBPP: STREET TREES SITE PLAN1
04/07/2025340916682Open ↗
▸BISSTREET TREE CHECKLIST1
04/07/2025340916682Open ↗
▸DOB NOWTenant Protection Plan1
08/13/2026B00225359-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B01155671-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/16/2026B01442904-I1Open ↗
08/13/2026B00225359-I1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
11/22/2019321976153Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
11/22/2019321976153Open ↗
09/20/2019321976153Open ↗
▸Inspections & Test Reports2
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026B01155671-I1Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026B01155671-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISLETTERS - SUPPORTING DOCUMENTATION1
05/14/2025340916682Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
09/20/2019321976153Open ↗
▸Filing & Intake Forms5
▸BISADDITIONAL INFORMATION2
02/05/2026340916682Open ↗
05/14/2025340916682Open ↗
▸BISEFILING COVER SHEET1
09/20/2019321976153Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
04/07/2025340916682Open ↗
▸BISBOROUGH INTAKE FORM1
12/01/2020321976153Open ↗
▸Other Documents5
▸BISBPP - SUPPORTING DOCUMENTATION2
02/05/2026340916682Open ↗
04/07/2025340916682Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
04/07/2025340916682Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01155671-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01155671-I1Open ↗