Roof3p · 1 filing · 4 docs
Architecture
Issued Permit Scope
General Construction
Facade and roof repairs as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Floor 3671p · 9 filings · 20 docs
ArchitectureDMFire ProtectionPlumbing
Issued Permit Scope
General Construction
Removal of existing sprinkler heads with installation of a temporary loop on the 35th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Partial demolition of interior shear wall for enlargement of existing openings (CPPIB) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Minor demolition with installation of new partitions, doors, suspended ceilings and finishes on the 35th and 36th floors (CPPIB) as per plans. No change to use, egress or occupancy.
On file for this project
6 documents · 6 drawing sheets
Latest 3 of 8 filings on this floor.
Floor 3584p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction
Removal of existing sprinkler heads with installation of a temporary loop on the 35th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Partial demolition of interior shear wall for enlargement of existing openings (CPPIB) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Minor demolition with installation of new partitions, doors, suspended ceilings and finishes on the 35th and 36th floors (CPPIB) as per plans. No change to use, egress or occupancy.
On file for this project
6 documents · 22 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 341p · 1 filing · 3 docs
Fire Protection
No filed description on record for this project.
On file for this project
3 documents · 1 drawing sheet
Floor 33
Floor 32
Floor 31
Floor 30
Floor 292p · 2 filings · 19 docs
ArchitecturePlumbing
Installation of new partitions, doors, suspended ceilings and finishes on the 29th floor (Wachtell Lipton Rosen & Katz) as per plans. No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Modifications to the existing plumbing system on the 29th floor as per plans. No change to use, egress or occupancy.
On file for this project
14 documents · 1 drawing sheet
Floor 28
Floor 273p · 1 filing · 5 docs
ArchitectureDM
Removal and installation of interior partitions and related finishes on the 27th floor (Wachtell) as per plans. No change to use, egress or occupancy.
On file for this project
5 documents · 3 drawing sheets
Floor 26
Floor 25
Floor 2431p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
Plumbing
Modifications to the existing sprinkler system on the 20,21,22,24 Floors- (Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
8 documents · 2 drawing sheets
Plumbing: Modifications to the existing plumbing system on the (,20,21,22,24 Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
10 documents · 2 drawing sheets
Minor demolition with installation of new partitions, doors, suspended ceilings and finishes on the (,20,21,22,24 Floors- Orrick-Buildout as per plans. No change to use, egress or occupancy.
On file for this project
12 documents · 3 drawing sheets
Latest 3 of 7 filings on this floor.
Floor 23Under Construction39p · 5 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Plumbing · Sprinklers
Filing for partition work related to a new place of assembly on the 22nd floor and to remove an existing place of assembly on the 23rd floor.
On file for this project
10 documents · 1 drawing sheet
Plumbing: Modifications to the existing plumbing system on the (23rd Floor- Orrick) as per plans. No change to use, egress or occupancy.
On file for this project
5 documents · 3 drawing sheets
Mechanical: Modifications to the existing HVAC system on the (23rd Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 22Under Construction33p · 6 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Plumbing
Modifications to the existing sprinkler system on the 20,21,22,24 Floors- (Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
8 documents · 4 drawing sheets
Filing for partition work related to a new place of assembly on the 22nd floor and to remove an existing place of assembly on the 23rd floor.
On file for this project
10 documents · 1 drawing sheet
Plumbing: Modifications to the existing plumbing system on the (,20,21,22,24 Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
10 documents · 3 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 2126p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Plumbing
Modifications to the existing sprinkler system on the 20,21,22,24 Floors- (Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
8 documents · 3 drawing sheets
Plumbing: Modifications to the existing plumbing system on the (,20,21,22,24 Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
10 documents · 2 drawing sheets
Mechanical: Modifications to the existing HVAC system on the (,20,21,22,24 Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
20 documents · 3 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 2028p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Plumbing
Modifications to the existing sprinkler system on the 20,21,22,24 Floors- (Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
8 documents · 1 drawing sheet
Plumbing: Modifications to the existing plumbing system on the (,20,21,22,24 Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
10 documents · 3 drawing sheets
Mechanical: Modifications to the existing HVAC system on the (,20,21,22,24 Floors- Orrick Buildout) as per plans. No change to use, egress or occupancy.
On file for this project
20 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Floor 193p · 3 filings · 13 docs
Fire ProtectionMechanicalPlumbing
Modifications to the existing sprinkler system on the 19th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Modifications to the existing plumbing system on the 19th floor as per plans. No change to use, egress or occupancy.
On file for this project
5 documents · 2 drawing sheets
Modifications to the existing HVAC system on the 19th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 2 drawing sheets
Floor 18Under Construction13p · 5 filings · 20 docs
ArchitectureDMFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Structural
Structural modification on the 17-18 floor as per plans. No change to use egress or occupancy.
On file for this project
3 documents · 2 drawing sheets
Installation of new plumbing fixtures and associated piping on the 18th floor (Brightstar Capital Partners) as per plans. No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Installation of a new sprinkler system on the 18th floor (Brightstar Capital) as per plans. No change to use, egress or occupancy.
On file for this project
12 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.
Floor 1775p · 15 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Modifications to the existing HVAC system on the 17th floor (Core Restroom & Corridor) as per plans. No change to use, egress or occupancy.
On file for this project
7 documents · 2 drawing sheets
Removal of plumbing fixtures and associated piping on the 17th floors (Core Restroom& Corridor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 2 drawing sheets
Modifications to the existing sprinkler system on the 17th floor (Core Restroom & Corridor) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 8 filings on this floor.
Floor 16Under Construction24p · 4 filings · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing
Plumbing: Modifications to the existing plumbing system on the (16th Floors- Orrick) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 2 drawing sheets
Modifications to the existing sprinkler system on the 16th Floor- (Orrick) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 3 drawing sheets
Minor demolition with installation of new partitions, doors, suspended ceilings and finishes on the 16th Floor- (Orrick) as per plans. No change to use, egress or occupancy.
On file for this project
7 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
Floor 156p · 1 filing · 18 docs
Fire ProtectionMechanicalPlumbing
No filed description on record for this project.
On file for this project
18 documents · 6 drawing sheets
Floor 14Under Construction14p · 1 filing · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing Sprinkler system on the 13th and 14th floor as per plans submitted herewith. No Change to Use, Occupancy Group, or Egress.
On file for this project
20 documents · 7 drawing sheets
Floor 13Under Construction14p · 1 filing · 20 docs
ArchitectureFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing Sprinkler system on the 13th and 14th floor as per plans submitted herewith. No Change to Use, Occupancy Group, or Egress.
On file for this project
20 documents · 7 drawing sheets
Floor 122p · 2 filings · 12 docs
Fire ProtectionMechanical
Modifications to the existing sprinkler system on the 12th floor (Vale Insurance Partners) as per plans. No change to use, egress or occupancy.
On file for this project
7 documents · 1 drawing sheet
Modifications to the existing HVAC system on the 12th floor (Vale Insurance Partners) as per plans. No change to use, egress or occupancy.
On file for this project
5 documents · 1 drawing sheet
Floor 11
Floor 10Under Construction3p · 1 filing · 6 docs
Structural
Issued Permit Scope
Structural
Removal of existing convenience stair from the 8-10th floors as per plans submitted herewith. No Change to Use, Occupancy or Egress.
On file for this project
6 documents · 1 drawing sheet
Floor 9Under Construction2p · 1 filing · 6 docs
Structural
Issued Permit Scope
Structural
Removal of existing convenience stair from the 8-10th floors as per plans submitted herewith. No Change to Use, Occupancy or Egress.
On file for this project
6 documents
Floor 8Under Construction59p · 3 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers · Structural
Modifications to the existing Sprinkler system on the 8th floor as per plans submitted herewith. No Change to Use, Occupancy Group, or Egress.
On file for this project
20 documents · 11 drawing sheets
Removal of existing convenience stair from the 8-10th floors as per plans submitted herewith. No Change to Use, Occupancy or Egress.
On file for this project
6 documents
Removal and disposal of interior partitions, doors, suspended ceilings and finishes with patch and repair on the 18th floor as per plans. No change to use, egress or occupancy.
On file for this project
6 documents · 3 drawing sheets
Floor 718p · 7 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Sprinklers
Modifications to the existing sprinkler system on the 7th floor (Demo Phase) as per plans. No change to use, egress or occupancy.
On file for this project
3 documents
Modifications to the existing HVAC system on the 7th floor (Demo Phase) as per plans. No change to use, egress or occupancy.
On file for this project
6 documents · 1 drawing sheet
Modifications to the existing HVAC system on the 7th floor (Whitebox) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 7 filings on this floor.
Floor 6Under Construction25p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems
Architectural modifications on the 6th floor (White-box Phase) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 4 drawing sheets
Modifications to the existing HVAC system on the 6th floor (Whitebox) as per plans. No change to use, egress or occupancy.
On file for this project
6 documents
Modifications to the existing sprinkler system on the 6th floor (Harbor Group Headquarters) as per plans. No change to use, egress or occupancy.
On file for this project
6 documents · 2 drawing sheets
Latest 3 of 6 filings on this floor.
Floor 5Under Construction13p · 4 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing Sprinkler System on the 5th floor as per plans submitted herewith. No Change to Use, Occupancy, or Egress.
On file for this project
22 documents · 4 drawing sheets
Removal of existing Plumbing Fixtures and Sprinkler heads and piping on the 5th floor and installation of Temp Sprinkler Loop as per plans submitted herewith. No Change to Use, Occupancy or Egress.
On file for this project
28 documents · 6 drawing sheets
2 hour rated partition in the cellar to create amenity space and safe area in the cellar.
On file for this project
12 documents
Latest 3 of 4 filings on this floor.
Floor 4Under Construction43p · 6 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing Sprinkler system on the 4th floor as per plans submitted herewith. No Change to Use, Occupancy Group, or Egress.
On file for this project
20 documents · 3 drawing sheets
Removal and disposal of interior partitions, doors, suspended ceilings and finishes with patch and repair on the 4th floor as per plans. No change to use, egress or occupancy.
On file for this project
7 documents · 1 drawing sheet
Modifications to the existing HVAC system on the 4th floor as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 1 drawing sheet
Latest 3 of 6 filings on this floor.
Floor 3Under Construction47p · 3 filings · 20 docs
ArchitectureFire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the existing Sprinkler system on the 3rd floor as per plans submitted herewith. No Change to Use, Occupancy, or Egress.
On file for this project
21 documents · 3 drawing sheets
Interior Demo to existing 3rd floor office space as per plans submitted herewith. No Change to Use, Occupancy Group, or Egress
On file for this project
13 documents · 1 drawing sheet
2 hour rated partition in the cellar to create amenity space and safe area in the cellar.
On file for this project
12 documents
Floor 2Under Construction57p · 5 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanicalPlumbing
Issued Permit Scope
General Construction · Mechanical Systems · Plumbing · Sprinklers
Modifications to the Mechanical systems on the 2nd floor as per plans submitted herewith. No Change to Use, Occupancy or Egress.
On file for this project
18 documents · 4 drawing sheets
Plumbing and Sprinkler Demo and installation of Temp Sprinkler Loop on the 2nd floor as per plans submitted herewith. No Change to Use, Occupancy Group, or Egress.
On file for this project
13 documents · 6 drawing sheets
2 hour rated partition in the cellar to create amenity space and safe area in the cellar.
On file for this project
12 documents
Latest 3 of 5 filings on this floor.
Floor 115p · 1 filing · 12 docs
Architecture
Issued Permit Scope
General Construction
2 hour rated partition in the cellar to create amenity space and safe area in the cellar.
On file for this project
12 documents
Mezzanine15p · 1 filing · 12 docs
Architecture
Issued Permit Scope
General Construction
2 hour rated partition in the cellar to create amenity space and safe area in the cellar.
On file for this project
12 documents
CellarUnder Construction28p · 6 filings · 20 docs
ArchitectureDMElectricalFire ProtectionMechanicalPlumbing
Issued Permit Scope
General Construction
Modifications to the existing sprinkler system (Amenity Space) as per plans. No change to use, egress or occupancy.
On file for this project
6 documents · 3 drawing sheets
Filing for partition work related to a new place of assembly on the 22nd floor and to remove an existing place of assembly on the 23rd floor.
On file for this project
10 documents
2 hour rated partition in the cellar to create amenity space and safe area in the cellar.
On file for this project
12 documents
Latest 3 of 6 filings on this floor.
Basement21p · 5 filings · 20 docs
ArchitectureDMFire ProtectionGeneralMechanical
Issued Permit Scope
General Construction
Modifications to the existing sprinkler system (Lobby Renovation) as per plans. No change to use, egress or occupancy.
On file for this project
3 documents · 1 drawing sheet
2 hour rated partition in the cellar to create amenity space and safe area in the cellar.
On file for this project
12 documents
Architectural modifications (Lobby Renovation) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents · 2 drawing sheets
Latest 3 of 5 filings on this floor.
Sub-Basement4p · 1 filing · 4 docs
Architecture
Issued Permit Scope
General Construction
Architectural modifications (Lobby Renovation) as per plans. No change to use, egress or occupancy.
On file for this project
4 documents