| Firm | Filings | Most Recent |
|---|---|---|
| ALPHA HOME DESIGN LLC | 3 | 01/14/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| ECDESIGN STUDIO | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| YILIN CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| SO PLUMBING & HEATING INC | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Signed-off | YILIN CONSTRUCTION INC | 11/21/2019 |
| DOB NOW | Plumbing | Signed-off | NICHOLAS SUIDA | 11/13/2019 |
| BIS | OT | ISSUED | YILIN CONSTRUCTION INC | 06/05/2020 |
| BIS | OT | ISSUED | YILIN CONSTRUCTION INC | 10/25/2019 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/31/2019 | Complete | KJK ELECTRIC INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/07/2019 | Final | YAN GAO | progress |