| Owner | Filings | Most Recent |
|---|---|---|
| OWNER OF 513 81 ST | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/07/2022 | $1.7M | — | — → — | $481/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| A PLUS DESIGN INC | 4 | 11/04/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| A PLUS DESIGN INC. | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KLE CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| CATMAN PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A PLUS DESIGN INC | 6615 | 4 | 11/04/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | CATMAN PLUMBING INC | 09/16/2024 |
| DOB NOW | General Construction | Signed-off | KLE CONSTRUCTION INC | 09/13/2024 |
| BIS | OT | ISSUED | VAST CONTRACTING CORP | 07/27/2001 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2024 | Complete | J Y ELECTRIC INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/13/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/10/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/10/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/10/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/14/2024 | Interior lighting power | HONGTENG CHEN | energy_progress |
| 11/14/2024 | Fire-Resistant Penetrations and Joints | HONGTENG CHEN | special |
| 11/14/2024 | Tenant Protection Plan Compliance | HONGTENG CHEN | special |
| 11/14/2024 | Final | HONGTENG CHEN | progress |
| 11/14/2024 | Energy Code Compliance Inspections | HONGTENG CHEN | progress |
| 11/14/2024 | Fire-Resistance Rated Construction | HONGTENG CHEN | progress |
| 11/14/2024 | Air barrier - visual inspection | HONGTENG CHEN | energy_progress |
| 11/04/2024 | Tenant Protection Plan Compliance | HONGTENG CHEN | special |
| 10/24/2024 | HVAC-R and service water piping design and insulation | HONGTENG CHEN | energy_progress |
| 10/24/2024 | Fire-Resistant Penetrations and Joints | HONGTENG CHEN | special |
| 10/24/2024 | HVAC-R and service water heating equipment | HONGTENG CHEN | energy_progress |
| 10/24/2024 | HVAC-R and service water heating system controls | HONGTENG CHEN | energy_progress |
| 10/24/2024 | Maintenance information | HONGTENG CHEN | energy_progress |
| 10/24/2024 | Energy Code Compliance Inspections | HONGTENG CHEN | progress |
| 10/24/2024 | Final | HONGTENG CHEN | progress |
| 10/24/2024 | Fire-Resistance Rated Construction | HONGTENG CHEN | progress |
| 10/24/2024 | Interior lighting power | HONGTENG CHEN | energy_progress |
| 10/24/2024 | Air barrier - visual inspection | HONGTENG CHEN | energy_progress |
| 10/24/2024 | Fire-Resistant Penetrations and Joints | HONGTENG CHEN | special |
| 10/24/2024 | Energy Code Compliance Inspections | HONGTENG CHEN | progress |