| Owner | Filings | Most Recent |
|---|---|---|
| J G CONSTRUCTION SRVCS | 6 | 03/22/2026 |
| OWNERS REP | 5 | 03/22/2026 |
| NEW YORK CITY HOUSING AUTHORITY | 6 | 03/22/2026 |
| NYC HOUSING AUTHORITY | 1 | 03/21/2026 |
| NYCHA | 14 | 03/21/2026 |
| WHR (GROUPS 1 & 2) | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| DAGHER ENGINEERING PLLC | 8 | 10/28/2024 |
| PAUL PERDEK, PROF. ENG. PLLC | 2 | 08/24/2021 |
| SYED ENGINEERING, P.C. | 1 | 04/01/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| JM ZONING, LLC. | 16 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 6 | 03/21/2026 |
| A & E PLUMBING CORP | Plumbing | 5 | 07/08/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 3 | 03/21/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| STAR ELEC'L CONTRACTORS C | Electrical | 1 | 03/22/2026 |
| DRAZIC, IVAN | Electrical | 1 | 03/21/2026 |
| PYRAMID ETC COMPANIES, LL | General Contractor | 1 | 07/08/2026 |
| BYN CUSTOM DESIGN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| M. HAMDI GUNAL, PE, P.C. | 3000 | 4 | 07/30/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | A & E PLUMBING CORP | 10/18/2024 |
| DOB NOW | Plumbing | Signed-off | A & E PLUMBING CORP | 11/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | PYRAMID ETC COMPANIES, LL | 10/30/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | CORE SCAFFOLD SYSTEMS INC | 07/28/2022 |
| DOB NOW | Sidewalk Shed | Permit Issued | CORE SCAFFOLD SYSTEMS INC | 07/30/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 04/02/2019 |
| BIS | OT | ISSUED | MONADNOCK CONSTRUCTION IN | 11/07/2023 |
| BIS | OT | ISSUED | MONADNOCK CONSTRUCTION IN | 11/17/2022 |
| BIS | OT | ISSUED | PYRAMID ETC COMPANIES, LL | 04/01/2022 |
| BIS | OT | ISSUED | MONADNOCK CONSTRUCTION IN | 10/04/2021 |
| BIS | OT | ISSUED | MONADNOCK CONSTRUCTION IN | 07/15/2021 |
| BIS | PL | ISSUED | CITY GAS HTG SVC CO INC | 04/16/2019 |
| BIS | BL | ISSUED | CITY GAS HTG SVC CO INC | 04/16/2019 |
| BIS | OT | ISSUED | LAKHI GENERAL CONTRACTOR | 06/19/2015 |
| BIS | EQ | ISSUED | LAKHI GENERAL CONTRACTOR | 02/26/2015 |
| BIS | EQ | ISSUED | LAKHI GENERAL CONTRACTOR | 11/12/2014 |
| BIS | EQ | ISSUED | LAKHI GENERAL CONTRACTOR | 08/14/2014 |
| BIS | OT | ISSUED | LAKHI GENERAL CONTRACTOR | 08/12/2014 |
| BIS | OT | ISSUED | BRI-DEN CONSTRUCTION CO | 04/06/2009 |
| BIS | OT | ISSUED | BRI-DEN CONSTRUCTION CO | 01/06/2009 |
| BIS | EQ | RE-ISSUED | POWERS BRIDGING & SCAFFOLDING | 04/03/2008 |
| BIS | OT | ISSUED | BRI-DEN CONSTRUCTION | 03/19/2008 |
| BIS | EQ | ISSUED | POWERS BRIDGING & SCAFFOLDING | 02/06/2008 |
| BIS | EQ | ISSUED | BRI-DEN CONSTRUCTION CORP. | 10/22/2007 |
| BIS | OT | ISSUED | BRI-DEN CONSTRUCTION | 04/09/2007 |
| BIS | OT | ISSUED | BRI-DEN CONSTRUCTION | 11/15/2006 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/30/2021 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/16/2022 | Permit Issued | STAR ELEC'L CONTRACTORS C | — |
| 07/30/2021 | Complete | V. VASS ELECTRIC CORP | — |
| 03/25/2019 | Permit Issued | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2021 | Permit Issued | CORE SCAFFOLD SYSTEMS INC | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/11/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/23/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/04/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/28/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/31/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/22/2023 | No Access-Final PL - Up to 9 Requested Floors | No Access | View ↗ |
| 12/08/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/09/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/28/2024 | Energy Code Compliance Inspections | Mehmet Gunal | progress |
| 10/28/2024 | HVAC-R and service water piping design and insulation | Mehmet Gunal | energy_progress |
| 09/19/2024 | HVAC-R and service water piping design and insulation | Mehmet Gunal | energy_progress |
| 09/19/2024 | Energy Code Compliance Inspections | Mehmet Gunal | progress |
| 01/23/2024 | Energy Code Compliance Inspections | Mehmet Gunal | progress |
| 01/23/2024 | HVAC-R and service water piping design and insulation | Mehmet Gunal | energy_progress |
| 08/03/2021 | HVAC insulation and sealing | Mehmet Gunal | energy_progress |
| 08/03/2021 | Maintenance information | Mehmet Gunal | energy_progress |
| 08/03/2021 | Energy Code Compliance Inspections | Mehmet Gunal | progress |
| 08/03/2021 | Fire-Resistant Penetrations and Joints | Mehmet Gunal | special |
| 07/12/2021 | Maintenance information | Mehmet Gunal | energy_progress |
| 07/12/2021 | Fire-Resistant Penetrations and Joints | Mehmet Gunal | special |
| 07/12/2021 | Energy Code Compliance Inspections | Mehmet Gunal | progress |
| 07/12/2021 | HVAC insulation and sealing | Mehmet Gunal | energy_progress |
| 08/05/2020 | Final | Mehmet Gunal | progress |
| 08/05/2020 | Fire-Resistant Penetrations and Joints | Mehmet Gunal | special |
| 08/05/2020 | Mechanical Systems | Mehmet Gunal | special |
| 08/05/2020 | Energy Code Compliance Inspections | Mehmet Gunal | progress |
| 08/05/2020 | HVAC insulation and sealing | Mehmet Gunal | energy_progress |
| 08/05/2020 | Maintenance information | Mehmet Gunal | energy_progress |