| Owner | Filings | Most Recent |
|---|---|---|
| AMERICAN RED CROSS | 23 | 09/13/2026 |
| REAL ESTATE INDUSTRIALS | 6 | 03/21/2026 |
| OWNERS REP | 5 | 07/08/2026 |
| REAL ESTATE INDUSTRIES | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| GENSLER | 3 | 05/05/2026 |
| GILSANZ MURRAY STEFICEK LLP | 2 | 04/24/2026 |
| KPFF CONSULTING ENGINEERS | 1 | 04/13/2026 |
| RIGID STRUCTURAL DESIGN, LLC | 2 | 06/28/2024 |
| ROBERT DERECTOR ASSOCIATES | 1 | 03/20/2024 |
| NAVI STRUCTURAL ENGINEERING, PLLC | 1 | 07/14/2021 |
| PAUL PERDEK, PROF. ENG. PLLC | 2 | 04/27/2021 |
| GREEN DESIGN | 1 | 06/11/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| A1 EXPEDITING SERVICE CORP. | 4 | 03/21/2026 |
| Rigid Structural Design, LLC | 2 | 03/21/2026 |
| ACA ASSOCIATES | 1 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WESBUILT CONSTRUCTION MAN | General Contractor | 4 | 07/08/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 4 | 07/08/2026 |
| BUILDCOX CONSTRUCTION COR | General Contractor | 3 | 03/21/2026 |
| RUSSCO ,INC | General Contractor | 2 | 07/22/2026 |
| VAN VASSELL | Electrical | 1 | 03/21/2026 |
| PHOENIX SUTTON STR INC | General Contractor | 1 | 07/08/2026 |
| JAVELIN ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| PARAGON BUILDING RESTORATION | General Contractor | 1 | 07/08/2026 |
| CHARNJIT SINGH | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| COLE TECHNOLOGIES/CONTROL | 1290 | 5 | 05/05/2026 |
| GILSANZ MURRAY STEFICEK | 240 | 2 | 04/24/2026 |
| NAVI STRUCTURAL ENGINEERI | 4624 | 1 | 07/14/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Structural | Permit Issued | RUSSCO ,INC | 07/20/2026 |
| DOB NOW | Structural | Permit Issued | RUSSCO ,INC | 05/12/2026 |
| DOB NOW | Mechanical Systems | Signed-off | WESBUILT CONSTRUCTION MAN | 09/19/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | BUILDCOX CONSTRUCTION COR | 06/12/2024 |
| DOB NOW | General Construction | Signed-off | WESBUILT CONSTRUCTION MAN | 05/13/2024 |
| DOB NOW | Structural | Signed-off | WESBUILT CONSTRUCTION MAN | 05/13/2024 |
| DOB NOW | General Construction | Permit Issued | PARAGON BUILDING RESTORATION | 07/19/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/27/2021 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 04/27/2021 |
| DOB NOW | Sidewalk Shed | Permit Issued | PHOENIX SUTTON STR INC | 06/12/2020 |
| BIS | — | ISSUED | JOHN GALLIN AND SON, INC. | 06/10/2019 |
| BIS | OT | ISSUED | JOHN GALLIN & SON, INC | 11/27/2018 |
| BIS | OT | ISSUED | JOHN GALLIN & SON, INC | 11/27/2018 |
| BIS | EQ | ISSUED | CONSOLIDATED SCAFFOLD & BRIDGE | 06/16/2015 |
| BIS | OT | ISSUED | WALTER T. GORMAN, PE., PC. | 08/13/2009 |
| BIS | EQ | ISSUED | EAGLE SCAFFOLDING SVCS INC | 09/11/2008 |
| BIS | EQ | ISSUED | EAGLE SCAFFOLDING SVCS INC | 09/09/2008 |
| BIS | OT | ISSUED | WESTERN WATERPROOFING COM | 04/21/2008 |
| BIS | OT | ISSUED | LARRY E. TREET CO | 09/19/2007 |
| BIS | FP | ISSUED | FIREGUARD OF LONG ISLAND | 09/19/2007 |
| BIS | BL | ISSUED | PETER AGLIARDO CONTRACTING INC | 10/06/2006 |
| BIS | FS | ISSUED | PETER AGLIARDO CONTRACTING INC | 08/29/2006 |
| BIS | MH | ISSUED | STRUCTURE TONE, LLC | 08/08/2006 |
| BIS | EQ | ISSUED | ALL SAFE HEIGHTS | 03/31/2006 |
| BIS | EQ | ISSUED | ALL SAFE HEIGHTS | 03/31/2006 |
| BIS | OT | ISSUED | STRUCTURE TONE, LLC | 03/01/2006 |
| BIS | OT | ISSUED | STRUCTURE TONE, LLC | 02/15/2006 |
| BIS | MH | ISSUED | STRUCTURE TONE, LLC | 02/14/2006 |
| BIS | OT | ISSUED | STRUCTURE TONE, LLC | 02/14/2006 |
| BIS | FP | ISSUED | FIREGUARD OF LONG ISLAND | 02/07/2006 |
| BIS | OT | ISSUED | LARRY E. TREET CO | 02/07/2006 |
| BIS | PL | ISSUED | PACE PLUMBING CORP | 01/17/2006 |
| BIS | SP | RE-ISSUED | ABCO-PEERLESS SPRKLR CORP | 01/03/2006 |
| BIS | EQ | ISSUED | COLE PARTNERS INC | 10/27/2005 |
| BIS | OT | ISSUED | STRUCTURE TONE, LLC | 10/25/2005 |
| BIS | MH | ISSUED | STRUCTURE TONE, LLC | 10/25/2005 |
| BIS | EQ | ISSUED | ALL SAFE HEIGHTS | 10/21/2005 |
| BIS | EQ | ISSUED | ALL SAFE HEIGHTS | 10/21/2005 |
| BIS | OT | ISSUED | UNIVERSAL DESIGN & CONSRUCTION | 04/08/1998 |
| BIS | BL | ISSUED | VALCO ENERGY SYSTEMS INC | 08/19/1993 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/16/2026 | Complete | E.T. ELEC'L CONTR CO INC | General Wiring |
| 07/02/2024 | Permit Issued | LIT MODE ELECL CONTG INC | — |
| 03/31/2021 | Complete | V. VASS ELECTRIC CORP | — |
| 06/08/2020 | Permit Issued | ELPO ELECTRICAL CONTG INC | — |
| 12/07/2018 | Complete | JAVELIN ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2026 | Permit Issued | RUSSCO ,INC | 1 scope_items |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/16/2026 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 05/16/2026 | Air barrier - visual inspection | GEORGE ANDERSEN | energy_progress |
| 05/16/2026 | Insulation placement and R values | GEORGE ANDERSEN | energy_progress |
| 05/16/2026 | Final | GEORGE ANDERSEN | progress |
| 02/26/2026 | Structural Steel - Details | Karl Rubenacker | special |
| 02/20/2026 | Structural Steel - Welding | Karl Rubenacker | special |
| 02/20/2026 | Final | Karl Rubenacker | progress |
| 09/19/2024 | Fire-Resistance Rated Construction | GEORGE ANDERSEN | progress |
| 09/19/2024 | Air barrier - visual inspection | GEORGE ANDERSEN | energy_progress |
| 09/19/2024 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 09/19/2024 | Final | GEORGE ANDERSEN | progress |
| 09/19/2024 | Insulation placement and R values | GEORGE ANDERSEN | energy_progress |
| 04/03/2024 | Structural Stability – Alterations of existing buildings | GEORGE ANDERSEN | special |
| 03/15/2024 | Structural Steel - Details | GEORGE ANDERSEN | special |
| 03/15/2024 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 03/15/2024 | Masonry | GEORGE ANDERSEN | special |
| 03/13/2024 | Final | GEORGE ANDERSEN | progress |
| 03/13/2024 | Mechanical Systems | GEORGE ANDERSEN | special |
| 03/13/2024 | Final | GEORGE ANDERSEN | progress |
| 07/14/2021 | Final | Humayun Ahmed | progress |
| 07/14/2021 | Masonry | Humayun Ahmed | special |
| 04/26/2021 | Final | Paul Perdek | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| American Red Cross | Parking | Cellar, Floor 1 | Project M01342597 Project M01019765 Project M01019761 Project M01019756 |