| Owner | Filings | Most Recent |
|---|---|---|
| KINGS CAPITAL | 4 | 09/29/2026 |
| 515E12 LLC | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CONCORD CONSULTING ENGINEERING PC | 2 | 07/03/2026 |
| OPERA STUDIO ARCHITECTURE, LLC | 2 | 06/22/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HARROW NY INC | General Contractor | 2 | 09/29/2026 |
| PETER MICELI PLUMBING | Plumbing | 1 | 09/26/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 4 | 07/03/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | HARROW NY INC | 09/28/2026 |
| DOB NOW | Plumbing | Permit Issued | PETER MICELI PLUMBING | 09/25/2026 |
| DOB NOW | General Construction | Permit Issued | HARROW NY INC | 07/20/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/03/2026 | Permit Issued | HARROW NY INC | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-2D20NLHZ 20,000 BTU · Condensing Unit ×5 MUZ-GX09NLHZ 9,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/03/2026 | Permit Issued | FLOWRITE SYSTEMS CORP | Gas, Water/Sanitary |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/30/2026 | Insulation placement and R values | SHAHRIAR QUAYYUM | energy_progress |
| 06/30/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 06/30/2026 | Tenant Protection Plan Compliance | SHAHRIAR QUAYYUM | special |
| 06/30/2026 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |
| 06/30/2026 | Final | Thomas Barry | progress |
| 06/30/2026 | Exterior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 06/30/2026 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 06/30/2026 | Interior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 06/30/2026 | Lighting in dwelling units | SHAHRIAR QUAYYUM | energy_progress |
| 06/30/2026 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 06/30/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 06/15/2026 | Fenestration and door U-factor and product ratings | SHAHRIAR QUAYYUM | energy_progress |
| 06/15/2026 | Fenestration areas | SHAHRIAR QUAYYUM | energy_progress |
| 06/15/2026 | Insulation placement and R values | SHAHRIAR QUAYYUM | energy_progress |
| 06/15/2026 | Interior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 06/15/2026 | Fenestration air leakage | SHAHRIAR QUAYYUM | energy_progress |
| 06/15/2026 | Lighting in dwelling units | SHAHRIAR QUAYYUM | energy_progress |
| 06/15/2026 | Exterior lighting power | SHAHRIAR QUAYYUM | energy_progress |
| 06/15/2026 | Fire-Resistant Penetrations and Joints | SHAHRIAR QUAYYUM | special |
| 06/15/2026 | Tenant Protection Plan Compliance | — | special |
| 06/15/2026 | Final | Thomas Barry | progress |
| 06/15/2026 | Fire-Resistance Rated Construction | SHAHRIAR QUAYYUM | progress |