ECB05/05/2025WWP: INSPECTOR OBSERVED AT BASEMENT LEVEL EXCAVATION DONE WITH HAND TOOLS AND CONCRETE REMOVED TO EXP. #3 & #4'. ALSO NEW STEEL AND OPEN ELECTRICAL PANELS, OUTLETS, SWITCHES, AND LIGHTS, PLUMBING DRAINS MADE OF$3K due
DOB05/14/2024DEPT FOUND UNPERMITTED WORK: UNDOCUMENTED/UNINSPECTEDFOUNDATION WORK & STEEL INSTALLATION, CELLAR PARTIALLY EXCAVATED,POSING HAZARD; PROPERTY FULLY VACATED. REMEDY: RETAIN NYS PE & CONTRACTOR 2 STABILIZE, SECURE & PROTECT THE SITE.PROVID DAILY INSPECTN RPTS.FILE/PERMIT WITHIN 48 HR
DOB05/13/2024BASEMENT LEVEL EXCAVATION BEING DONE BY HAND TOOLS AND CHIPPING GUN, ALL CONCRETE REMOVED & SOIL 5-8IN ON EXP 3&4 OVER 1FT EXP2, BEING PUT IN BAGS, AND REMOVED. ALSO NEW STEEL & OPEN ELECTRICAL PANELS, OUTLETS, SWITCHES, AND LIGHTS. ALONG WITH OPEN AND PLUMBING DRAINS MADE OF PVC AND WATER LINES
DOB05/13/2024BASEMENT LEVEL EXCAVATION BEING DONE BY HAND TOOLS AND CHIPPING GUN, ALL CONCRETE REMOVED & SOIL 5-8IN ON EXP 3&4 OVER 1FT EXP2, BEING REMOVED INTO CONTAINER IN FRONT OF BUILDING UNDERMINING WALLS, ALSO NEW STEEL INSTALLED.
ECB03/05/2007FAILURE TO MAINTAIN EXTERIOR BLDG WALL. NOTED: AT FRONT OF PREMISES REPLACE BRICK PORCH 6 STEPS W/O HANDRAILS. REMEDY: INSTALL HANDRAILS.Nothing owed — awaiting certificate of correction
One family attached or semi-detached · 1,900 sf lot · 0.61 FAR built · Flood zone X