| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/17/2026 | — | — | Air Conditioning Systems | Cooling Daikin ACU-2-1: RXRA48AAVJU / ACCU-2-1: FXMA48AAVJU 48,000 BTU · Split System ×1 ACU-2-2: RXTA36AAVJU / ACCU-2-2: FXFA36AAVJU 36,000 BTU · Split System ×1 |
| 08/11/2026 | Permit Issued | EMPIRE GENERAL CONTRACTIN | Air Conditioning Systems, Heating and Air Conditioning Systems, Ventilation Systems | |
| 05/07/2026 | Permit Issued | SKANSKA USA BUILDING, INC | Air Conditioning Systems, Heating and Air Conditioning Systems | |
| 10/02/2025 | — | — | Heating Systems, Ventilation Systems | |
| 08/01/2025 | Permit Issued | HUNTER ROBERTS CONSTRUCTI | Associated Ducts and Piping, Heating and Air Conditioning Systems, Ventilation Systems | |
| 10/24/2024 | Signed-off | H.M. HUGHES CO. INC | Heating and Air Conditioning Systems | Heat / Cool Trane YSK090A3S0M0AP200C 93,600 BTU · Chiller ×1 |
| 04/15/2024 | Signed-off | HELLMAN CONSTRUCTION CO | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM48NAM 48,000 BTU · Heat Pump Outdoor ×1 PEFY-P18NMAU-E3 18,000 BTU · Vrf Indoor ×1 PEFY-P24NMAU-E3 24,000 BTU · Vrf Indoor ×1 |
| 10/20/2023 | Permit Issued | HUNTER ROBERTS CONSTRUCTI | Air Conditioning Systems, Associated Ducts and Piping, Heating Systems, Ventilation Systems | |
| 03/18/2022 | — | — | Generators | Generators Caterpillar D-3516 1,500 kW · Generator ×1 |
| 10/29/2020 | — | — | Air Conditioning Systems, Associated Ducts and Piping | |
| 10/29/2020 | — | — | Air Conditioning Systems, Associated Ducts and Piping | |
| 05/06/2020 | — | — | Air Conditioning Systems, Associated Ducts and Piping | |
| 01/10/2020 | — | — | Air Conditioning Systems, Associated Ducts and Piping |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/17/2026 | — | — | Sprinkler System |
| 08/11/2026 | Permit Issued | ENCORE FIRE PROT SVS INC | 63 heads |
| 06/16/2026 | — | — | Sprinkler System |
| 05/07/2026 | Permit Issued | SIRINA FIRE PROT CORP | Sprinkler System |
| 10/02/2025 | — | — | Sprinkler System |
| 08/01/2025 | Permit Issued | PAR FIRE PROTECTION LLC | 3 heads |
| 04/15/2024 | Signed-off | SIRINA FIRE PROT CORP | 13 heads |
| 10/20/2023 | Permit Issued | SIRINA FIRE PROT CORP | Sprinkler System |
| 10/29/2020 | — | — | — |
| 10/29/2020 | — | — | 79 heads |
| 05/06/2020 | — | — | 30 heads |
| 04/22/2020 | — | — | — |
| 01/10/2020 | — | — | 84 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/17/2026 | — | — | Water/Sanitary |
| 08/11/2026 | Permit Issued | CARDOZA PLUMBING CORP | Medical Gas, Water/Sanitary |
| 06/16/2026 | — | — | Water/Sanitary |
| 05/07/2026 | Permit Issued | RIEHM PLUMBING CORP | Medical Gas, Water/Sanitary |
| 11/04/2025 | Permit Issued | TRISTATE PLBG SVCS CORP | Storm, Water/Sanitary |
| 10/02/2025 | — | — | Medical Gas, Water/Sanitary |
| 08/01/2025 | Permit Issued | PAR PLUMBING CO., INC | Storm |
| 10/24/2024 | Permit Issued | RIEHM PLUMBING CORP | Gas |
| 04/15/2024 | Signed-off | ALLIANCE PLUMBING CORP | Water/Sanitary |
| 10/20/2023 | Signed-off | ALLIANCE PLUMBING CORP | Water/Sanitary |
| 10/29/2020 | — | — | Water/Sanitary |
| 10/29/2020 | — | — | Medical Gas, Water/Sanitary |
| 05/06/2020 | — | — | Water/Sanitary |
| 04/22/2020 | — | — | Water/Sanitary |
| 01/10/2020 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/04/2026 | Permit Issued | ALLAN BRITEWAY ELECTRICAL | General Wiring |
| 04/15/2026 | Permit Issued | NEAD ELECTRIC INC. | General Wiring |
| 03/25/2026 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 03/25/2026 | Permit Issued | E-J ELEC. INSTALLATION CO | — |
| 03/18/2026 | Permit Issued | E-J ELEC. INSTALLATION CO | General Wiring |
| 03/18/2026 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 03/18/2026 | Permit Issued | E-J ELEC. INSTALLATION CO | General Wiring |
| 02/19/2026 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 01/30/2026 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 06/20/2025 | Permit Issued | E-J ELEC. INSTALLATION CO | General Wiring |
| 04/15/2025 | Permit Issued | E-J ELEC. INSTALLATION CO | — |
| 02/11/2025 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| 12/23/2024 | Complete | TOP SHELF ELECTRIC CORP | — |
| 12/09/2024 | Permit Issued | BIGMAN BROS., INC. | General Wiring |
| 12/03/2024 | Complete | E-J ELEC. INSTALLATION CO | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/30/2025 | Permit Issued | HUNTER ROBERTS CONSTRUCTI | Steel |
| 10/20/2023 | Permit Issued | SIRINA FIRE PROT CORP | Steel, Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/23/2026 | Permit Issued | SAFWAY ATLANTIC, LLC | Scaffold, Sidewalk Shed |
| 11/07/2025 | Signed-off | SAFWAY ATLANTIC, LLC | Sidewalk Shed |
| 12/13/2024 | Permit Issued | UNIVERSAL BUILD SUPP LLC | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2025 | Permit Issued | DNA CONTRACTING LLC | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| NEW YORK PRESBYTERIAN HOSPITAL | 262 | 09/25/2026 |
| NEW YORK PRESBYTERIAN | 43 | 07/08/2026 |
| NEW YORK DOWNTOWN HOSPITAL | 101 | 03/22/2026 |
| BR MASTER LIMITED PARTNER | 3 | 03/22/2026 |
| NYU DOWNTOWN HOSPITAL | 6 | 03/22/2026 |
| NY DOWNTOWN HOSPITAL | 39 | 03/22/2026 |
| BEEKMAN DOWNTOWN HOSPITAL | 3 | 03/22/2026 |
| DOWNTOWN MEDICAL ASSOCIAT | 1 | 03/22/2026 |
| NY PRESBYTERIAN HOSPITAL | 49 | 03/22/2026 |
| NEW YORK PRESBYTERIAN UNIV HOSPITAL | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| OVE ARUP & PARTNERS PC | 3 | 08/19/2026 |
| LILKER ASSOCIATES CONSULTING ENGINE | 9 | 08/17/2026 |
| HORACIO REPETTO | 2 | 08/05/2026 |
| BRAND ACCESS SOLUTIONS | 16 | 07/23/2026 |
| LORING CONSULTING ENGINEERS, INC. | 2 | 06/16/2026 |
| HELLMUTH OBATA & KASSABAUM PC | 5 | 05/07/2026 |
| COSENTINI ASSOCIATES | 17 | 04/21/2026 |
| O'DONNELL & NACCARATO STRUCTURAL EN | 2 | 03/26/2026 |
| FACILITY LEADERS IN ARCHITECTURAL/E | 3 | 03/18/2026 |
| AKF ENGINEERS, LLP | 25 | 11/04/2025 |
| LIZARDOS ENGINEERING | 3 | 10/02/2025 |
| EFH ARCHITECTURE | 1 | 10/01/2025 |
| ARRAY ARCHITECTS | 2 | 08/05/2025 |
| GILSANZ MURRAY STEFICEK LLP | 3 | 07/30/2025 |
| WELLWORTH CONSULTING LLC | 2 | 03/24/2025 |
| HOK | 2 | 02/20/2025 |
| LPE ENGINEERING, PC | 4 | 02/12/2025 |
| UNIVERSAL BUILDERS SUPPLY, LLC | 2 | 12/13/2024 |
| INSITE DESIGN STUDIO | 1 | 11/19/2024 |
| NADASKAY KOPELSON ARCHITECTS | 1 | 11/05/2024 |
| GOLDMAN COPELAND ASSOCIATES | 2 | 10/03/2024 |
| HDR ARCHITECTURE & ENGINEERING | 1 | 06/06/2024 |
| EWINGCOLE | 1 | 04/10/2024 |
| WSP | 7 | 02/05/2024 |
| WJL ARCHITECTURE & ENGINEERING DPC | 1 | 02/01/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL EXPEDITING | 172 | 03/21/2026 |
| A1 EXPEDITING SERVICE | 30 | 03/21/2026 |
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| EUROCELT EXPEDITING, INC | 4 | 03/21/2026 |
| BUILDING BROTHERS | 12 | 03/21/2026 |
| SPRING SCAFFOLDING LLC | 2 | 03/21/2026 |
| Enviornmental & Energy Solutions | 2 | 03/21/2026 |
| UNITED SAFETY CONSULTANTS | 2 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HELLMAN CONSTRUCTION CO | General Contractor | 26 | 07/08/2026 |
| SAFWAY ATLANTIC, LLC | General Contractor | 24 | 09/18/2026 |
| HUNTER ROBERTS CONSTRUCTION | General Contractor | 21 | 07/08/2026 |
| SIRINA FIRE PROT CORP | Fire Protection | 15 | 09/25/2026 |
| RED HOOK SIGN ELECT | Scaffold | 13 | 07/08/2026 |
| SKANSKA USA BUILDING, INC | General Contractor | 12 | 08/30/2026 |
| SPRING SCAFFOLDING LLC | General Contractor | 10 | 07/08/2026 |
| TALISEN CONSTRUCTION CORP | General Contractor | 10 | 07/08/2026 |
| ALLIANCE PLUMBING CORP | Plumbing | 9 | 07/08/2026 |
| H.M. HUGHES CO. INC | General Contractor | 8 | 07/08/2026 |
| TUTTLE ROOFING CO INC | General Contractor | 5 | 07/08/2026 |
| RIEHM PLUMBING CORP | Plumbing | 5 | 07/08/2026 |
| E-J ELEC. INSTALLATION CO | Electrical | 5 | 03/22/2026 |
| SCALA, JR., ANTHONY | Electrical | 4 | 03/21/2026 |
| MOORE, KEVIN | Electrical | 4 | 03/21/2026 |
| NY PRESBYTERIAN UNIV HOSP | Electrical | 3 | 03/22/2026 |
| PAR FIRE PROTECTION LLC | Fire Protection | 3 | 07/08/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 2 | 03/21/2026 |
| DNA CONTRACTING LLC | General Contractor | 2 | 07/08/2026 |
| EMPIRE GENERAL CONTRACTIN | General Contractor | 2 | 07/08/2026 |
| SKYLINE RESTORATION INC | General Contractor | 2 | 03/21/2026 |
| UNIVERSAL BUILD SUPP LLC | General Contractor | 2 | 07/08/2026 |
| PACE PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| ENCORE FIRE PROT SVS INC | Fire Protection | 1 | 07/08/2026 |
| INTERSTATE MECH SVCS INC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FENAGH, INC | 6942 | 28 | 08/17/2026 |
| ALAN MARGOLIN & ASSOC | 423 | 39 | 08/11/2026 |
| G. BLINN CONSULTING, LLC | 2894 | 3 | 07/23/2026 |
| LEO Y LEE ASSOCIATES | 2481 | 2 | 04/22/2025 |
| TECTONIC ENGINEERING CONS | 106 | 11 | 12/13/2023 |
| LPE ENGINEERING PC | 3102 | 2 | 10/04/2022 |
| NUENERGEN | 1717 | 2 | 03/18/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | SIRINA FIRE PROT CORP | 09/24/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | SAFWAY ATLANTIC, LLC | 09/17/2026 |
| DOB NOW | General Construction | Permit Issued | SKANSKA USA BUILDING, INC | 08/27/2026 |
| DOB NOW | General Construction | Permit Issued | SKANSKA USA BUILDING, INC | 08/26/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | SKANSKA USA BUILDING, INC | 08/25/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | SKANSKA USA BUILDING, INC | 06/26/2026 |
| DOB NOW | General Construction | Permit Issued | SKANSKA USA BUILDING, INC | 06/26/2026 |
| DOB NOW | Sprinklers | Permit Issued | SIRINA FIRE PROT CORP | 06/25/2026 |
| DOB NOW | Sprinklers | Permit Issued | RIEHM PLUMBING CORP | 06/25/2026 |
| DOB NOW | Sprinklers | Permit Issued | ENCORE FIRE PROT SVS INC | 05/15/2026 |
| DOB NOW | Plumbing | Permit Issued | ALLIANCE PLUMBING CORP | 05/13/2026 |
| DOB NOW | Plumbing | Permit Issued | PAR PLUMBING CO., INC | 04/20/2026 |
| DOB NOW | Sprinklers | Permit Issued | PAR FIRE PROTECTION LLC | 04/20/2026 |
| DOB NOW | General Construction | Permit Issued | EMPIRE GENERAL CONTRACTIN | 04/10/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | EMPIRE GENERAL CONTRACTIN | 04/01/2026 |
| DOB NOW | General Construction | Signed-off | SKANSKA USA BUILDING, INC | 02/11/2026 |
| DOB NOW | Structural | Signed-off | SKANSKA USA BUILDING, INC | 02/11/2026 |
| DOB NOW | Construction Fence | Permit Issued | UNIVERSAL BUILD SUPP LLC | 02/03/2026 |
| DOB NOW | Plumbing | Permit Issued | TRISTATE PLBG SVCS CORP | 01/25/2026 |
| DOB NOW | Plumbing | Permit Issued | CARDOZA PLUMBING WMBE | 01/08/2026 |
| DOB NOW | General Construction | Signed-off | HELLMAN CONSTRUCTION CO | 01/06/2026 |
| DOB NOW | Mechanical Systems | Signed-off | HM HUGHES CO INC | 12/12/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 12/11/2025 |
| DOB NOW | General Construction | Signed-off | HM HUGHES CO INC | 12/11/2025 |
| DOB NOW | Plumbing | Permit Issued | RIEHM PLUMBING CORP | 10/08/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | SAFWAY ATLANTIC, LLC | 10/01/2025 |
| DOB NOW | Sprinklers | Permit Issued | SIRINA FIRE PROT CORP | 09/30/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | SAFWAY ATLANTIC, LLC | 09/29/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 09/26/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 09/25/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | SAFWAY ATLANTIC, LLC | 09/25/2025 |
| DOB NOW | Supported Scaffold | Signed-off | SAFWAY ATLANTIC, LLC | 09/25/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | SAFWAY ATLANTIC, LLC | 09/22/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | HM HUGHES CO INC | 08/26/2025 |
| DOB NOW | Mechanical Systems | Signed-off | SKANSKA USA BUILDING, INC | 08/20/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 07/22/2025 |
| DOB NOW | Structural | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 07/22/2025 |
| DOB NOW | General Construction | Permit Issued | HUNTER ROBERTS CONSTRUCTION | 07/22/2025 |
| DOB NOW | General Construction | Signed-off | HELLMAN CONSTRUCTION CO | 07/01/2025 |
| DOB NOW | General Construction | Signed-off | HM HUGHES CO INC | 05/23/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/15/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/15/2026 | Certified Sprinkler - SP - Roughing | Certified | View ↗ |
| 04/30/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/24/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/03/2026 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 03/31/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/25/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/25/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/20/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/27/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/23/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 09/18/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/10/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/01/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/18/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 06/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/07/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 05/07/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/05/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/24/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/19/2025 | Certified Medical Gas - MG - PL - Finish | Certified | View ↗ |
| 02/19/2025 | Certified Medical Gas - MG - PL - Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/21/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 08/21/2026 | Sprinkler Systems | Young Suh | special |
| 08/21/2026 | HVAC-R and service water piping design and insulation | Young Suh | energy_progress |
| 08/21/2026 | Post-installed Anchors | Young Suh | special |
| 08/07/2026 | HVAC-R and service water piping design and insulation | Young Suh | energy_progress |
| 08/07/2026 | Post-installed Anchors | Young Suh | special |
| 08/07/2026 | Sprinkler Systems | Young Suh | special |
| 08/07/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 08/05/2026 | Duct leakage testing, insulation and design | AILANTO DANIEL MINAWI | energy_progress |
| 08/05/2026 | HVAC-R and service water piping design and insulation | AILANTO DANIEL MINAWI | energy_progress |
| 08/05/2026 | Energy Code Compliance Inspections | AILANTO DANIEL MINAWI | progress |
| 08/05/2026 | Fire-Resistant Penetrations and Joints | AILANTO DANIEL MINAWI | special |
| 08/05/2026 | Maintenance information | AILANTO DANIEL MINAWI | energy_progress |
| 08/05/2026 | Post-installed Anchors | AILANTO DANIEL MINAWI | special |
| 08/05/2026 | Post-installed Anchors | AILANTO DANIEL MINAWI | special |
| 07/23/2026 | Post-installed Anchors | GREG BLINN | special |
| 07/22/2026 | Post-installed Anchors | GREG BLINN | special |
| 07/21/2026 | Final | AILANTO DANIEL MINAWI | progress |
| 07/21/2026 | Sprinkler Systems | AILANTO DANIEL MINAWI | special |
| 07/21/2026 | Fire-Resistant Penetrations and Joints | Young Suh | special |
| 07/21/2026 | Mechanical Systems | AILANTO DANIEL MINAWI | special |
| 07/21/2026 | HVAC-R and service water piping design and insulation | Young Suh | energy_progress |
| 07/21/2026 | Sprinkler Systems | Young Suh | special |
| 07/21/2026 | Post-installed Anchors | Young Suh | special |
| 07/20/2026 | Fire-Resistant Penetrations and Joints | AILANTO DANIEL MINAWI | special |