RoofUnder Construction23p · 4 filings · 20 docs
ArchitectureElectricalMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing
INSTALLATION OF 300 PSF SIDEWALK SHED, PIPE SCAFFOLD AND ROOF PROTECTION AS PER PLANS. ALL EQUIPMENT SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
4 documents · 1 drawing sheet
Mechanical modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
8 documents
Plumbing modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 2 drawing sheets
Latest 3 of 4 filings on this floor.
PenthouseUnder Construction28p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Mechanical modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
8 documents · 1 drawing sheet
Structural modifications to the Cel, 1st-5th Floors, Penthouse as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 1 drawing sheet
Plumbing modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 5Under Construction28p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Mechanical modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
8 documents · 1 drawing sheet
Structural modifications to the Cel, 1st-5th Floors, Penthouse as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 1 drawing sheet
Plumbing modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 4Under Construction24p · 3 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Mechanical modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
8 documents
Plumbing modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents
Sprinkler modifications to the existing CEL, 1st -3rd Floors. New sprinkler to addition 4th - 5th floors, penthouse as plans filed herewith.
On file for this project
4 documents
Floor 3Under Construction28p · 4 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Mechanical modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
8 documents · 1 drawing sheet
Structural modifications to the Cel, 1st-5th Floors, Penthouse as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 1 drawing sheet
Plumbing modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 1 drawing sheet
Latest 3 of 4 filings on this floor.
Floor 2Under Construction24p · 3 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Mechanical modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
8 documents
Plumbing modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents
Sprinkler modifications to the existing CEL, 1st -3rd Floors. New sprinkler to addition 4th - 5th floors, penthouse as plans filed herewith.
On file for this project
4 documents
Floor 1Under Construction26p · 3 filings · 20 docs
Fire ProtectionMechanicalPlumbing
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Mechanical modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
8 documents
Plumbing modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 1 drawing sheet
Sprinkler modifications to the existing CEL, 1st -3rd Floors. New sprinkler to addition 4th - 5th floors, penthouse as plans filed herewith.
On file for this project
4 documents · 1 drawing sheet
CellarUnder Construction28p · 5 filings · 20 docs
Fire ProtectionMechanicalPlumbingStructural
Issued Permit Scope
Mechanical Systems · Plumbing · Sprinklers
Mechanical modifications to the Cel, 1st-5th Floors, Penthouse and Roof as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
8 documents · 1 drawing sheet
Structural modifications to the Cel, 1st-5th Floors, Penthouse as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
14 documents · 1 drawing sheet
Foundation modifications to the Cellar as plans filed herewith. No change in use, egress, or occupancy.
On file for this project
5 documents · 1 drawing sheet
Latest 3 of 5 filings on this floor.