| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/10/2025 | Permit Issued | BUILDWISE CONSTRUCTION GR | Heating and Air Conditioning Systems | Heat / Cool Mitsubishi Electric MXZ-SM36NAMHZ 36,000 BTU · Heat Pump Outdoor ×6 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/10/2025 | Permit Issued | W.R. PLBG AND HTG CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/19/2026 | Complete | P.L. ELEC'L CONTR'G CORP | General Wiring |
| 05/01/2023 | Complete | P.L. ELEC'L CONTR'G CORP | — |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/18/2016 | $3.3M | — | Private party → Private party | $1,093/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| FLUSHING ENGINEERING SERVICE PC | 4 | 02/10/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| K A INTERIOR DESIGN | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| 148 HUA HONG INC | General Contractor | 11 | 07/08/2026 |
| CORE MECHANICAL CONTRACTING | General Contractor | 3 | 03/21/2026 |
| PIPESTYLISTS, INC | Plumbing | 3 | 07/08/2026 |
| BUILDWISE CONSTRUCTION GR | General Contractor | 1 | 07/08/2026 |
| CUBE BUILDERS GROUP NY | General Contractor | 1 | 04/09/2026 |
| W.R. PLBG AND HTG CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FLUSHING ENGINEERING SERV | 4373 | 4 | 02/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | BUILDWISE CONSTRUCTION GR | 04/23/2026 |
| DOB NOW | Plumbing | Permit Issued | W.R. PLBG AND HTG CORP | 02/18/2026 |
| DOB NOW | Plumbing | Permit Issued | T & T PLUMBING INC | 06/03/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | CUBE BUILDERS GROUP NY | 05/12/2025 |
| DOB NOW | General Construction | Permit Issued | 148 HUA HONG | 04/30/2025 |
| DOB NOW | General Construction | Permit Issued | CORE MECHANICAL CONTRACTI | 08/08/2024 |
| DOB NOW | Plumbing | Permit Issued | T & T PLUMBING INC | 05/17/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | 148 HUA HONG | 03/29/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | 148 HUA HONG | 05/12/2023 |
| DOB NOW | General Construction | Permit Issued | 148 HUA HONG | 05/10/2023 |
| DOB NOW | Plumbing | Permit Issued | T & T PLUMBING INC | 04/20/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | 148 HUA HONG | 04/11/2023 |
| DOB NOW | Mechanical Systems | Permit Issued | 148 HUA HONG | 04/10/2023 |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/01/2025 | Pass-Final PL - More than 10 Requested Floors | Pass | View ↗ |
| 04/17/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/17/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 04/15/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/19/2025 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 03/19/2025 | Energy Code Compliance Inspections | KY FU | progress |
| 03/19/2025 | HVAC-R and service water heating equipment | KY FU | energy_progress |
| 03/19/2025 | Maintenance information | KY FU | energy_progress |
| 03/19/2025 | HVAC-R and service water heating system controls | KY FU | energy_progress |
| 03/19/2025 | HVAC-R and service water piping design and insulation | KY FU | energy_progress |
| 02/25/2025 | HVAC-R and service water heating equipment | KY FU | energy_progress |
| 02/25/2025 | Fenestration air leakage | KY FU | energy_progress |
| 02/25/2025 | Insulation placement and R values | KY FU | energy_progress |
| 02/25/2025 | Fire-Resistant Penetrations and Joints | KY FU | special |
| 02/25/2025 | Mechanical Systems | KY FU | special |
| 02/25/2025 | Energy Code Compliance Inspections | KY FU | progress |
| 02/25/2025 | Final | KY FU | progress |
| 02/25/2025 | Fire-Resistance Rated Construction | KY FU | progress |
| 02/25/2025 | Interior lighting power | KY FU | energy_progress |
| 02/25/2025 | Air barrier - visual inspection | KY FU | energy_progress |
| 02/25/2025 | Maintenance information | KY FU | energy_progress |
| 02/25/2025 | HVAC-R and service water heating system controls | KY FU | energy_progress |
| 02/25/2025 | Fenestration areas | KY FU | energy_progress |
| 02/25/2025 | HVAC-R and service water piping design and insulation | KY FU | energy_progress |
| 02/25/2025 | Fenestration and door U-factor and product ratings | KY FU | energy_progress |
| 01/22/2025 | HVAC-R and service water piping design and insulation | KY FU | energy_progress |
| 01/22/2025 | Mechanical Systems | KY FU | special |
| 01/22/2025 | Energy Code Compliance Inspections | KY FU | progress |
| 01/22/2025 | Final | KY FU | progress |