| Owner | Filings | Most Recent |
|---|---|---|
| NYC SCHOOL CONSTRUCTION AUTH | 21 | 03/21/2026 |
| SCHOOL CONSTRUCTION AUTHORITY | 2 | 03/21/2026 |
| NYC DEPARTMENT OF EDUCATION | 1 | 03/22/2026 |
| NYC SCHOOL CONSTRUCTION AUTHORITY | 1 | 03/22/2026 |
| NEW YORK CITY SCHOOL CONSTRUCTIO | 1 | 03/21/2026 |
| NYCSCAC | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| AECOM | 2 | 05/29/2026 |
| EME CONSULTING ENGINEERING GROUP | 1 | 01/18/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MDS CONSTRUCTION MANAGE | General Contractor | 8 | 04/09/2026 |
| DIA GENERAL CONTRUCTION I | General Contractor | 3 | 03/21/2026 |
| DEREK MOHAN | Electrical | 1 | 03/21/2026 |
| EVS ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| ANTHONY COMO | Electrical | 1 | 03/21/2026 |
| URBAN ELECTRICAL CORP | Electrical | 1 | 03/22/2026 |
| FRANCIS RICHARDS | Electrical | 1 | 03/21/2026 |
| A & S ELECTRIC INC. | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| KS ENGINEERS, P.C. | 7715 | 2 | 05/29/2026 |
| JPC LOGISTICS DBA JPCL EN | 351 | 1 | 01/18/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | MDS CONSTR MGMT LLC | 03/10/2026 |
| DOB NOW | General Construction | Permit Issued | MDS CONSTR MGMT LLC | 03/02/2026 |
| DOB NOW | General Construction | Permit Issued | MDS CONSTR MGMT LLC | 08/14/2024 |
| DOB NOW | Structural | Permit Issued | DIA GENERAL CONTRUCTION I | 07/20/2023 |
| DOB NOW | General Construction | Permit Issued | MDS CONSTR MGMT LLC | 06/29/2023 |
| BIS | — | ISSUED | TURNER CONSTRUCTION COMPANY | 02/03/2017 |
| BIS | PL | ISSUED | S & L PLUMBING & HEATING | 10/26/2016 |
| BIS | PL | ISSUED | S & L PLUMBING & HEATING | 10/26/2016 |
| BIS | — | ISSUED | TURNER CONSTRUCTION COMPANY | 01/07/2016 |
| BIS | PL | ISSUED | S & L PLUMBING & HEATING | 07/22/2015 |
| BIS | PL | ISSUED | S & L PLUMBING & HEATING | 07/22/2015 |
| BIS | — | ISSUED | TURNER CONSTRUCTION COMPANY | 03/25/2015 |
| BIS | SD | ISSUED | WDF, INC.DBA WDF FEDERATE | 09/18/2014 |
| BIS | PL | ISSUED | S & L PLUMBING & HEATING | 08/11/2014 |
| BIS | PL | ISSUED | S & L PLUMBING & HEATING | 08/11/2014 |
| BIS | PL | ISSUED | W D F INC | 06/27/2014 |
| BIS | PL | ISSUED | W D F INC | 05/23/2014 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 02/18/2014 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 02/18/2014 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 02/18/2014 |
| BIS | SD | ISSUED | FEDERATED FIRE PROT SYSTS | 02/18/2014 |
| BIS | — | ISSUED | TURNER CONSTRUCTION COMPANY | 01/10/2014 |
| BIS | PL | ISSUED | W D F INC | 12/17/2013 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 11/04/2013 |
| BIS | OT | ISSUED | NYCSCA | 08/06/2013 |
| BIS | PL | ISSUED | W D F INC | 07/26/2013 |
| BIS | OT | RE-ISSUED | TURNER CONSTRUCTION COMPANY | 07/22/2013 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 07/22/2013 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 07/22/2013 |
| BIS | PL | ISSUED | W D F INC | 06/14/2013 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 06/05/2013 |
| BIS | OT | ISSUED | TURNER CONSTRUCTION COMPANY | 03/09/2013 |
| BIS | PL | ISSUED | FCV SEWER & WATER INC | 01/18/2013 |
| BIS | PL | ISSUED | W D F INC | 01/14/2013 |
| BIS | FP | ISSUED | CHIEF FIRE PREV.& MECH CO | 11/30/2012 |
| BIS | — | ISSUED | TURNER CONSTRUCTION COMPANY | 11/01/2012 |
| BIS | EQ | ISSUED | TURNER CONSTRUCTION COMPANY | 11/01/2012 |
| BIS | PL | ISSUED | W D F INC | 08/24/2012 |
| BIS | EQ | ISSUED | ATLANTIC HOISTING & SCAFF | 07/27/2012 |
| BIS | SD | ISSUED | FEDERATED CONTRACTING COR | 07/26/2012 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/13/2026 | Complete | GEMINI ELECTRIC CO., INC. | — |
| 01/05/2024 | Permit Issued | A & S ELECTRIC INC. | General Wiring |
| 08/01/2023 | Permit Issued | EVS ELECTRIC CORP | General Wiring |
| 07/13/2023 | Complete | URBAN ELECTRICAL CORP | General Wiring |
| 06/08/2021 | Complete | ANCO ELECTL CONTCTNG INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/18/2023 | Permit Issued | DIA GENERAL CONTRUCTION I | Steel |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/12/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/05/2026 | Masonry | Mohamed Shahid | special |
| 06/05/2026 | Fire-Resistant Penetrations and Joints | Mohamed Shahid | special |
| 05/22/2026 | Fire-Resistant Penetrations and Joints | Mohamed Shahid | special |
| 05/22/2026 | Masonry | Mohamed Shahid | special |
| 01/13/2023 | Post-installed Anchors | Asma Hashmi | special |
| 01/13/2023 | Fire-Resistant Penetrations and Joints | Asma Hashmi | special |
| 01/13/2023 | Structural Steel - Welding | Asma Hashmi | special |
| 01/13/2023 | Structural Steel - Details | Asma Hashmi | special |
| 01/12/2023 | Final | Asma Hashmi | progress |