← Back
Elevator apt, semi-fireproof with stores
Vital Brookdale
527 EAST 98TH STREET · Brownsville · BIN 3428749
💬 Discuss this project
2020Year Built
7Stories
D7Building Class
R6Zoning
199,383 sfGross Floor Area
161Units
LL97 CoveredRent Stabilized58 Open Violations ▸FDNY Report ↗
Elevator apt, semi-fireproof with stores · Owner of record: VITAL BROOKDALE HOUSING DEVELOPMENT FUND CORP · 42,787 sf lot · 4.66 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentCivilGeneral
Roof130p · 6 filings · 20 docs
Floor 7136p · 6 filings · 20 docs
Floor 6135p · 5 filings · 20 docs
Floor 5135p · 6 filings · 20 docs
Floor 4140p · 5 filings · 20 docs
Floor 3130p · 5 filings · 20 docs
Floor 2137p · 5 filings · 20 docs
Floor 1164p · 8 filings · 20 docs
Cellar152p · 5 filings · 20 docs
Site & exterior23p · 4 filings · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MDG DESIGN + CONSTRUCTION2003/22/2026
BROOKDALE HOSPITAL MEDICAL CENTER1107/08/2026
4MATIC CONSTRUCTION1103/22/2026
VITAL BROOKDALE HOUSING DEVELOPMENT FUND CORP703/22/2026
CORE SCAFFOLD SYSTEMS203/21/2026
BROOKDALE HOSPITAL MEDICAL C203/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EUROCELT EXPEDITING, INC803/21/2026
SPRING SCAFFOLDING LLC403/21/2026
AE DESIGN SOLUTION403/21/2026
JM ZONING, LLC.603/21/2026
WILLIAM VITACCO ASSOCIATES403/21/2026
SAFE RISE403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SPRING SCAFFOLDING LLCGeneral Contractor1207/08/2026
MONADNOCK CONSTRUCTION INGeneral Contractor1107/08/2026
SIGNATURE CONSTRUCTION GROUPGeneral Contractor703/21/2026
J.E.S. PLBG & HTG CORPPlumbing407/08/2026
MONADNOCK GEN'L CONT INCGeneral Contractor303/21/2026
PRECISION HOIST & SCAFFO*General Contractor303/21/2026
ASHLAR MECHANICALPlumbing303/22/2026
ASHLAR MECHANICAL CORPFire Protection207/08/2026
4MATIC CONSTRUCTION CORPGeneral Contractor207/08/2026
SHAMROCK MECHANICAL INCFire Protection207/08/2026
MILLER PLUMBING & HTG INCFire Protection207/08/2026
AMERICAN STANDARD P&H CORORP.Plumbing207/08/2026
GLO ELECTRIC LLCElectrical103/22/2026
AMBER LITE ELECTRIC CORP.Electrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SITE SAFETY LLC8555304/01/2024
SKYLINE ENGINEERING, PLLC267204/01/2024
PSI AGENCY INC.254403/01/2024
LT INSPECTIONS INC9795102/07/2024
Building Lifecycle
All (163)Filed (23)Permit Issued (32)Signed Off (14)Violation (60)Inspection (5)Special Inspection (29)
08/21/2026
Violation issued (HPD, open)
C
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/18/2026
Violation issued (HPD, open)
B
08/16/2026
Violation issued (HPD, open)
C
07/27/2026
Violation issued (HPD, open)
C
07/13/2026
Violation issued (HPD, open)
A
07/13/2026
Violation issued (HPD, open)
B
07/13/2026
Violation issued (HPD, open)
B
07/13/2026
Violation issued (HPD, open)
B
07/13/2026
Violation issued (HPD, open)
C
07/13/2026
Violation issued (HPD, open)
C
07/08/2026
Violation issued (HPD, open)
C
07/08/2026
Violation issued (HPD, open)
B
07/08/2026
Violation issued (HPD, open)
C
07/08/2026
Violation issued (HPD, open)
A
07/08/2026
Violation issued (HPD, open)
A
06/27/2026
Violation issued (HPD, open)
C
06/27/2026
Violation issued (HPD, open)
B
06/27/2026
Violation issued (HPD, open)
B
06/20/2026
Violation issued (HPD, open)
B
06/20/2026
Violation issued (HPD, open)
B
06/20/2026
Violation issued (HPD, open)
B
06/20/2026
Violation issued (HPD, open)
B
06/20/2026
Violation issued (HPD, open)
C
06/06/2026
Violation issued (HPD, closed)
B
06/06/2026
Violation issued (HPD, open)
C
06/06/2026
Violation issued (HPD, closed)
B
06/06/2026
Violation issued (HPD, closed)
A
06/04/2026
Signed off — Alteration
GENERAL INTERIOR CONSTRUCTION AND STOREFRONT IMPROVEMENT AS PER PLANS WITHOUT CHANGE TO USE, EGRESS, OCCUPANCY OR BULK.
B00942865-I1
06/02/2026
Violation issued (HPD, open)
C
06/02/2026
Violation issued (HPD, closed)
B
06/02/2026
Violation issued (HPD, open)
C
05/18/2026
Violation issued (HPD, open)
C
05/18/2026
Violation issued (HPD, open)
B
05/11/2026
Violation issued (HPD, closed)
A
04/09/2026
Violation issued (HPD, open)
C
04/05/2026
Violation issued (HPD, closed)
B
03/14/2026
Violation issued (HPD, closed)
C
03/04/2026
Signed off — Alteration
Filing of alt-2 for existing equipment use permits. All equipment filed/installed under application B00214563-I1. No work will be performed under this application.
B00944502-I1
03/03/2026
Violation issued (HPD, closed)
B
03/03/2026
Violation issued (HPD, closed)
B
02/22/2026
Violation issued (HPD, closed)
B
02/22/2026
Violation issued (HPD, open)
B
02/22/2026
Violation issued (HPD, closed)
B
02/22/2026
Violation issued (HPD, closed)
B
02/18/2026
Permit issued — Mechanical Systems
B00944502-I1-MS
02/16/2026
Violation issued (HPD, open)
B
02/16/2026
Violation issued (HPD, open)
B
02/07/2026
Violation issued (HPD, closed)
B
02/07/2026
Violation issued (HPD, closed)
C
02/07/2026
Violation issued (HPD, closed)
C
02/07/2026
Violation issued (HPD, closed)
C
02/07/2026
Violation issued (HPD, closed)
C
02/07/2026
Violation issued (HPD, open)
B
02/07/2026
Violation issued (HPD, closed)
C
02/07/2026
Violation issued (HPD, closed)
C
02/07/2026
Violation issued (HPD, closed)
C
12/18/2025
Violation issued (HPD, closed)
C
Latest 60 of 163 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offSIGNATURE CONSTRUCTION GR02/18/2026
DOB NOWGeneral ConstructionSigned-offSIGNATURE CONSTRUCTION GR09/17/2024
DOB NOWMechanical SystemsSigned-offSIGNATURE CONSTRUCTION GR09/17/2024
DOB NOWSprinklersSigned-offASHLAR MECHANICAL CORP07/12/2024
DOB NOWPlumbingSigned-offASHLAR MECHANICAL CORP05/28/2024
DOB NOWMechanical SystemsSigned-offSIGNATURE CONSTRUCTION GR05/01/2024
DOB NOWCurb CutSigned-offSIGNATURE CONSTRUCTION GR04/16/2024
DOB NOWPlumbingSigned-offAMERICAN STANDARD P&H CORORP.04/09/2024
DOB NOWGeneral ConstructionSigned-offSIGNATURE CONSTRUCTION GR03/14/2024
DOB NOWStructuralPermit IssuedMONADNOCK GEN'L CONT INC03/11/2024
DOB NOWPlumbingSigned-offJ.E.S. PLBG & HTG CORP10/25/2022
DOB NOWMechanical SystemsSigned-offMONADNOCK CONSTRUCTION IN03/30/2022
DOB NOWStandpipeSigned-offSHAMROCK MECHANICAL INC03/02/2022
DOB NOWSprinklersSigned-offSHAMROCK MECHANICAL INC03/02/2022
DOB NOWConstruction FenceSigned-offSPRING SCAFFOLDING LLC02/24/2022
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC02/24/2022
DOB NOWPlumbingSigned-offJ.E.S. PLBG & HTG CORP10/22/2021
DOB NOWConstruction FenceSigned-offMONADNOCK CONSTRUCTION IN10/04/2021
DOB NOWSprinklersSigned-offMILLER PLUMBING & HTG INC08/30/2021
DOB NOWStandpipeSigned-offMILLER PLUMBING & HTG INC08/30/2021
DOB NOWPlumbingSigned-offJ.E.S. PLBG & HTG CORP04/29/2021
DOB NOWSupported ScaffoldSigned-offPRECISION HOIST & SCAFFO*04/20/2021
DOB NOWSupported ScaffoldSigned-off4MATIC CONSTRUCTION CORP04/07/2021
DOB NOWConstruction FenceSigned-offSPRING SCAFFOLDING LLC03/03/2021
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC03/03/2021
DOB NOWConstruction FenceSigned-offSPRING SCAFFOLDING LLC01/28/2021
DOB NOWConstruction FenceSigned-offMONADNOCK CONSTRUCTION IN11/10/2020
DOB NOWConstruction FenceSigned-offMONADNOCK CONSTRUCTION IN10/09/2020
DOB NOWConstruction FenceSigned-offMONADNOCK CONSTRUCTION IN09/09/2020
DOB NOWSupported ScaffoldSigned-off4MATIC CONSTRUCTION CORP09/04/2020
DOB NOWSidewalk ShedSigned-offSPRING SCAFFOLDING LLC06/11/2020
DOB NOWPlumbingSigned-offJ.E.S. PLBG & HTG CORP05/29/2020
BIS—ISSUEDMONADNOCK CONSTRUCTION IN05/23/2022
BISEQISSUEDCORE SCAFFOLD SYSTEMS INC.08/25/2021
BISEQISSUEDSPRING SCAFFOLDING LLC08/09/2021
BISOTISSUEDSOLAR ENERGY SYSTEMS INC08/03/2021
BISEQISSUEDSPRING SCAFFOLDING LLC07/06/2021
BIS—ISSUEDMONADNOCK CONSTRUCTION IN08/11/2020
BIS—ISSUEDMONADNOCK CONSTRUCTION IN08/11/2020
BISEQISSUEDSPRING SCAFFOLDING LLC08/10/2020
+ 3 more permits on file
6 projects · most recent 03/27/2024
General Wiring Lighting HVAC Wiring Boiler Controls
FiledStatusContractorScope
03/27/2024CompleteMAUCERI ELECTRIC CORP.General Wiring
07/12/2022CompleteGLO ELECTRIC LLCGeneral Wiring, Lighting, HVAC Wiring, Boiler Controls
04/21/2022CompleteMETROPOLITAN ELEC OF NY I—
05/12/2021CompleteTUXEDO ELEC'L CONTR'G INC—
09/30/2020CompleteAMBER LITE ELECTRIC CORP.—
06/05/2020CompleteTOP SHELF ELECTRIC CORP—
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
08/21/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
09/09/2024Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
07/23/2024Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
07/17/2024Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/01/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 29
DateRequirementInspectorRole
02/08/2024Structural Steel - WeldingMAURICIO ANDRADEspecial
02/08/2024FinalMAURICIO ANDRADEprogress
02/08/2024Concrete - PrecastMAURICIO ANDRADEspecial
02/08/2024Concrete – PrestressedMAURICIO ANDRADEspecial
02/08/2024MasonryMAURICIO ANDRADEspecial
02/08/2024Post-installed AnchorsMAURICIO ANDRADEspecial
02/08/2024Structural Stability – Alterations of existing buildingsMAURICIO ANDRADEspecial
02/08/2024Structural Steel - DetailsMAURICIO ANDRADEspecial
02/08/2024Structural Steel - High Strength BoltingMAURICIO ANDRADEspecial
02/05/2024Tenant Protection Plan ComplianceKHALID ALGENDEspecial
02/05/2024Tenant Protection Plan ComplianceKHALID ALGENDEspecial
11/25/2023Sprinkler SystemsMatthew Wavrospecial
11/24/2023VestibulesChih Hsuenergy_progress
11/24/2023Exterior lighting powerChih Hsuenergy_progress
11/24/2023Air barrier - visual inspectionChih Hsuenergy_progress
11/24/2023Fenestration and door U-factor and product ratingsChih Hsuenergy_progress
11/24/2023Lighting controlsChih Hsuenergy_progress
11/24/2023Insulation placement and R valuesChih Hsuenergy_progress
11/24/2023Interior lighting powerChih Hsuenergy_progress
11/24/2023Fire-Resistant Penetrations and JointsChih Hsuspecial
11/24/2023Energy Code Compliance InspectionsChih Hsuprogress
11/24/2023Fire-Resistance Rated ConstructionChih Hsuprogress
11/24/2023PreliminaryChih Hsuprogress
10/06/2023Mechanical SystemsMAURICIO ANDRADEspecial
10/06/2023Tenant Protection Plan ComplianceMAURICIO ANDRADEspecial
Latest 25 of 29.
▾Documents — 256 on file (BIS + DOB NOW)
▸Plans & Drawings24
▸DOB NOWPlans/Sketch9
09/01/2026B00503534-P2Request digital key ↗
09/01/2026B00503534-I1Request digital key ↗
09/01/2026B00503534-P3Request digital key ↗
Showing 3 of 9 on file for this type
▸DOB NOWPlans/Sketch - Plumbing5
09/02/2026B00214588-I1Request digital key ↗
09/02/2026B00214588-P5Request digital key ↗
09/02/2026B00214588-P3Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Structural2
08/25/2026B00214469-I1Request digital key ↗
08/15/2026B00214469-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence2
09/02/2026B00314698-I1Request digital key ↗
09/01/2026B00461385-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/02/2026B00391975-I1Request digital key ↗
08/15/2026B00391975-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/02/2026B00356917-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Standpipe1
09/02/2026B00214743-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/02/2026B00214743-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems1
09/02/2026B00214563-I1Request digital key ↗
▸Applications & Permits37
▸BISPLAN / WORK APPROVAL APPLICATION19
02/04/2026321594832Open ↗
03/29/2024340907040Open ↗
08/25/2023321594832Open ↗
Showing 3 of 19 on file for this type
▸BISWORK PERMIT APPLICATION14
08/25/2021340820605Open ↗
08/03/2021340818431Open ↗
06/01/2021321594832Open ↗
Showing 3 of 14 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation3
03/29/2024340907040Open ↗
02/09/2022340714212Open ↗
06/04/2021340714212Open ↗
▸BISDOT PERMIT FOR CLOSING OF STREETS ORSIDEWALKS, OR TO THE OBSTRUCTION OF ANYPART THEREOF.1
05/17/2022340727324Open ↗
▸Zoning, Tax Lot & Property Records6
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
01/30/2020321594832Open ↗
▸BISVERIFY TAX LOT1
08/23/2023321594832Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
01/30/2020321594832Open ↗
▸BISZONING DIAGRAM1
02/12/2020321594832Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
01/30/2020321594832Open ↗
▸BISZONING RESOLUTION DETERMINATION1
02/12/2020321594832Open ↗
▸Seals & Professional Certifications54
▸DOB NOWDPL-1: Design Professional Seal & Signature23
09/01/2026B00461385-I1Open ↗
08/25/2026B00942865-I1Open ↗
08/25/2026B00942865-S1Open ↗
Showing 3 of 23 on file for this type
▸DOB NOWProgress Inspector Seal & Signature7
09/06/2026B00942865-I1Open ↗
09/06/2026B00942865-I1Open ↗
09/06/2026B00942865-I1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/06/2026B00942865-I1Open ↗
09/06/2026B00942865-I1Open ↗
09/02/2026B00942865-S2Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
03/24/2020321594832Open ↗
03/24/2020321594832Open ↗
03/24/2020321594832Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY4
03/29/2024340907040Open ↗
08/24/2021340820605Open ↗
07/30/2021340818431Open ↗
Showing 3 of 4 on file for this type
▸BISAPPLICANT OWNER SIGNATURE3
03/29/2024340907040Open ↗
05/07/2020340727324Open ↗
01/22/2020340714212Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
08/24/2021340820605Open ↗
07/30/2021340818431Open ↗
06/11/2020340733914Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION3
08/24/2021340820605Open ↗
07/30/2021340818431Open ↗
06/11/2020340733914Open ↗
▸Trade Schedules & Equipment1
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
02/18/2022321594832Open ↗
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST2
05/27/2021340714212Open ↗
01/30/2020321594832Open ↗
▸BISBPP: STREET TREES SITE PLAN2
03/29/2024340907040Open ↗
05/27/2021340714212Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
08/26/2020321594832Open ↗
▸BISSTREET TREE SIGNOFF1
03/07/2024321594832Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
05/07/2020340727324Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY4
04/09/2022340818431Open ↗
08/03/2021340818431Open ↗
07/30/2021340818431Open ↗
Showing 3 of 4 on file for this type
▸BISFENESTRATION U-FACTOR & PRODUCT RATING1
04/13/2022321594832Open ↗
▸BISFENESTRATION AREAS1
04/13/2022321594832Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
04/13/2022321594832Open ↗
▸BISLIGHTING IN DWELLING UNITS1
04/13/2022321594832Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
04/13/2022321594832Open ↗
▸BISELECTRIC MOTORS1
04/13/2022321594832Open ↗
▸BISLIGHTING CONTROLS1
04/13/2022321594832Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
03/24/2020321594832Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
04/13/2022321594832Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
07/30/2021340818431Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026B00214563-I1Open ↗
▸Inspections & Test Reports36
▸BISTECHNICAL REPORT: RESPONSIBILITY16
05/16/2022340727324Open ↗
05/12/2022340733914Open ↗
04/09/2022340818431Open ↗
Showing 3 of 16 on file for this type
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT6
08/16/2021321594832Open ↗
10/28/2020321594832Open ↗
10/28/2020321594832Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX4
08/16/2021321594832Open ↗
08/26/2020321594832Open ↗
03/24/2020321594832Open ↗
Showing 3 of 4 on file for this type
▸BISSPRAYED FIRE-RESISTANT MATERIALS2
04/28/2022321594832Open ↗
04/28/2022321594832Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
06/01/2022321594832Open ↗
03/24/2020321594832Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
04/28/2022321594832Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
04/28/2022321594832Open ↗
▸BISPOST-INSTALLED ANCHORS1
04/28/2022321594832Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
05/02/2022321594832Open ↗
▸BISSOIL REPORT1
01/30/2020321594832Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
01/30/2020321594832Open ↗
▸Approvals, Objections & Sign-offs21
▸BISSCHEDULE A - OCCUPANCY / USE7
02/04/2026321594832Open ↗
08/25/2023321594832Open ↗
08/24/2022321594832Open ↗
Showing 3 of 7 on file for this type
▸BISSUPERSEDING LETTER6
06/01/2021321594832Open ↗
06/01/2021321594832Open ↗
06/01/2021321594832Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
03/24/2020321594832Open ↗
03/24/2020321594832Open ↗
03/24/2020321594832Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST4
05/17/2022340727324Open ↗
05/13/2022340733914Open ↗
04/11/2022340818431Open ↗
Showing 3 of 4 on file for this type
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
04/09/2022340818431Open ↗
07/30/2021340818431Open ↗
▸Filing & Intake Forms24
▸BISADDITIONAL INFORMATION8
02/02/2022340714212Open ↗
05/27/2021340714212Open ↗
05/04/2021321594832Open ↗
Showing 3 of 8 on file for this type
▸BISBOROUGH INTAKE FORM8
06/01/2021321594832Open ↗
06/01/2021321594832Open ↗
06/01/2021321594832Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET6
03/29/2024340907040Open ↗
08/24/2021340820605Open ↗
07/30/2021340818431Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET2
08/28/2019321594832Open ↗
08/28/2019321594832Open ↗
▸Other Documents9
▸BISEXTERIOR INSULATION AND FINISH SYSTEMS (EIFS)2
04/28/2022321594832Open ↗
04/28/2022321594832Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
02/12/2020321594832Open ↗
▸BISVESTIBULES1
04/13/2022321594832Open ↗
▸BISMAINTENANCE INFORMATION1
04/13/2022321594832Open ↗
▸BISON-SITE STORM WATER DRAIN. DISP. /DETENT INSTALL (DRYWELL)1
04/28/2022321594832Open ↗
▸BISPROTECTION OF EXPOSED FOUNDATION INSULATION1
04/13/2022321594832Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
06/04/2021340714212Open ↗
▸BISPLOT DIAGRAM1
09/12/2019321594832Open ↗