← Back
Walk-up cooperative
529 EAST 88 STREET
MANHATTAN · Upper East Side-Yorkville · BIN 1051347
💬 Discuss this project
1920Year Built
5Stories
C6Building Class
R8BZoning
8,805 sfGross Floor Area
18Units
Rent Stabilized3 Open Violations ▸
Walk-up cooperative · 2,508 sf lot · 3.51 FAR built · Flood zone X
Locations of Work
StructuralPlumbingEquipmentGeneral
Floor 511p · 1 filing · 11 docs
Floor 410p · 1 filing · 11 docs
Floor 311p · 1 filing · 11 docs
Floor 210p · 1 filing · 11 docs
Floor 111p · 1 filing · 11 docs
Sub-Basement10p · 1 filing · 11 docs
Site & exterior6p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
529 EAST 88 OWNERS203/21/2026
529 OWNERS CORP C OMAUTNER GLICK203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PATTI & ANTHES CONSULTING ENGINEERS301/25/2024
ENTHINK ENGINEERS LLC103/01/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JAM CONSULTANTS, INC.603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
EVERGREEN MECHANICAL CORPPlumbing207/08/2026
ANDAMIO SCAFFOLDING LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
METRIC CONSULTING AND INS1803301/25/2024
Building Lifecycle
All (26)Filed (4)Permit Issued (3)Signed Off (1)Violation (9)Inspection (5)Special Inspection (4)
01/25/2024
Filed — Alteration
CONSOLIDATE COOKING AND LAUNDRY GAS METERS INTO A SINGLE CON EDISON METER. INSTALL NEW EXTERIOR, COMMON GAS RISERS TO SUPPLY COOKING GAS TO ALL APARTMENTS.
M00848675-P2
01/25/2024
Special inspection requirement — Tenant Protection Plan Compliance
SAMI HAJJAR P.E
01/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
SAMI HAJJAR P.E
01/25/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
SAMI HAJJAR P.E
01/25/2024
Special inspection requirement — Tenant Protection Plan Compliance
11/15/2023
Violation issued (HPD, closed)
I
10/06/2023
Signed off — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00829106-I1
08/24/2023
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
08/11/2023
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
08/04/2023
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
07/28/2023
Inspection — Pass-Final PL - More than 10 Requested Floors
Pass
View inspection ↗
07/18/2023
Permit issued — Plumbing
M00848675-I1-PL
07/17/2023
Filed — Alteration
CONSOLIDATE COOKING AND LAUNDRY GAS METERS INTO A SINGLE CON EDISON METER. INSTALL NEW EXTERIOR, COMMON GAS RISERS TO SUPPLY COOKING GAS TO ALL APARTMENTS.
M00848675-P1
07/07/2023
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/18/2023
Permit issued — Plumbing
M00848675-I1-PL
04/06/2023
Filed — Alteration
CONSOLIDATE COOKING AND LAUNDRY GAS METERS INTO A SINGLE CON EDISON METER. INSTALL NEW EXTERIOR, COMMON GAS RISERS TO SUPPLY COOKING GAS TO ALL APARTMENTS.
M00848675-I1
03/01/2023
Filed — Alteration
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLANS. WORK SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
M00829106-I1
03/01/2023
Permit issued — Supported Scaffold
M00829106-I1-SF
07/07/2022
Violation issued (ECB, closed)
Construction
07/07/2022
Violation issued (ECB, closed)
Plumbing
04/01/2021
Violation issued (HPD, closed)
A
08/02/2006
Violation issued (ECB, closed)
Construction
06/26/2006
Violation issued (ECB, closed)
Construction
08/29/1995
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/18/1993
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offEVERGREEN MECHANICAL CORP07/18/2023
DOB NOWPlumbingSigned-offOZERY PLBG & HTG INC04/18/2023
DOB NOWSupported ScaffoldSigned-offANDAMIO SCAFFOLDING LLC03/01/2023
BISPLISSUEDENTERPRISES P/H INC03/14/2007
BISOTISSUEDSUBURBAN CONTRACTING CORP06/29/2006
BISOTISSUEDSUBURBAN CONTRACTING CORP06/19/2006
BISPLISSUEDEDGECOMBS PLUMB HEAT. INC.05/03/2001
BISOTISSUEDAXIAK CONSTRUCTION CORP04/07/2000
BISFSISSUEDROCKWAY FUEL OIL CORP11/21/1995
1 project · most recent 01/25/2024
Gas
FiledStatusContractorScope
01/25/2024Signed-offEVERGREEN MECHANICAL CORPGas
▾Field Inspections (DOB CAP) — 5
DateTypeResultReport
08/24/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
08/11/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
08/04/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
07/28/2023Pass-Final PL - More than 10 Requested FloorsPassView ↗
07/07/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
01/25/2024Tenant Protection Plan ComplianceSAMI HAJJAR P.Especial
01/25/2024Fire-Resistant Penetrations and JointsSAMI HAJJAR P.Especial
01/25/2024Fire-Resistant Penetrations and JointsSAMI HAJJAR P.Especial
01/25/2024Tenant Protection Plan Compliance—special
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/31/2026M00829106-I1Request digital key ↗
08/31/2026M00848675-P2Request digital key ↗
08/31/2026M00848675-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications6
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/31/2026M00829106-I1Open ↗
08/31/2026M00848675-P1Open ↗
08/31/2026M00848675-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026M00848675-I1Open ↗
08/25/2026M00848675-P2Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/31/2026M00848675-P2Open ↗
08/31/2026M00848675-P1Open ↗
08/31/2026M00848675-I1Open ↗