| Owner | Filings | Most Recent |
|---|---|---|
| EAGLE POINT PROPERTIES | 134 | 09/13/2026 |
| ROY-AL COMPANY | 7 | 03/22/2026 |
| CONSOLIDATED SCAFFOLDING INC. | 5 | 03/22/2026 |
| EKA 529 WEST 20TH STREET LLC | 2 | 03/22/2026 |
| 529 WEST 20TH STREET | 54 | 03/22/2026 |
| RKS 529 WEST 20TH LLC | 1 | 03/22/2026 |
| KALIMAM WEST 20TH LLC | 1 | 03/22/2026 |
| KIALIMIAN WEST 20TH ST | 1 | 03/22/2026 |
| KALIMIAN WEST 20TH | 16 | 03/21/2026 |
| KALIMIAN WEST 20 | 8 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| LIZARDOS ENGINEERING | 13 | 03/25/2026 |
| LOFFREDO BROOKS ARCHITECTS P.C. | 4 | 03/25/2026 |
| DAVID BUCOVY ARCHITECT | 2 | 02/05/2026 |
| BOGUE TRONDOWSKI ARCHITECT PLLC | 9 | 07/17/2025 |
| TANG STUDIO ARCHITECT, LLC | 4 | 07/14/2025 |
| AG ENGINEERING PLLC | 2 | 11/13/2024 |
| ABS ENGINEERING, PLLC | 13 | 11/12/2024 |
| PAUL G. JONES, P.E. | 1 | 08/02/2024 |
| KEVIN H. SWEENEY, P.E. | 3 | 03/27/2024 |
| SCALAR ARCHITECTURE PC | 1 | 08/04/2023 |
| SOCOTEC, INC. | 1 | 10/28/2021 |
| GROUP PROJECTS ARCHITECTURE | 1 | 09/21/2021 |
| LUKE LICALZI, P.E., P.C. | 1 | 05/10/2021 |
| GREEN DESIGN | 1 | 10/29/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| TANG STUDIO LLC | 4 | 03/21/2026 |
| BOYD CONSULTING | 58 | 03/21/2026 |
| KAZAM CONSULTANTS | 4 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| I L CONSULTING | 2 | 03/21/2026 |
| CONVERSANO ASSOCIATES, INC. | 2 | 03/21/2026 |
| DAVID BUCOVY ARCHITECT | 2 | 03/21/2026 |
| CODE | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| KLARACON LLC | General Contractor | 22 | 07/08/2026 |
| FOLOR INC | General Contractor | 18 | 07/08/2026 |
| FULL CAPACITY FIRE CORP | Fire Protection | 4 | 07/08/2026 |
| A&A PLUMBING CORP | Plumbing | 4 | 07/08/2026 |
| NON LIMITE INC | General Contractor | 3 | 07/08/2026 |
| RAF GENERAL CONTRACTING C | General Contractor | 3 | 03/21/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 3 | 03/21/2026 |
| CHAOS BUILT LLC | General Contractor | 3 | 03/21/2026 |
| CONSOLIDATED SCAFFOLDING | General Contractor | 3 | 03/21/2026 |
| A M A HOLDINGS | Scaffold | 2 | 07/08/2026 |
| HI-TECH C.P.M. CORP | General Contractor | 2 | 03/21/2026 |
| PRESERV BLD RESTOR MGT IN | General Contractor | 2 | 03/21/2026 |
| IMPACT PLUMBING INC | Plumbing | 2 | 07/08/2026 |
| KHALED MUQATTASH | Electrical | 1 | 03/21/2026 |
| JR FRAMING | General Contractor | 1 | 04/08/2026 |
| JEM FIRE PREVENTION INC | Fire Protection | 1 | 07/08/2026 |
| NYC IRONWORKERS LOCAL 40 | Electrical | 1 | 03/21/2026 |
| EMPIRE STATE ELEC MAINT & | Electrical | 1 | 03/22/2026 |
| MOLLER, GEORGE | Electrical | 1 | 03/21/2026 |
| EVEREST SCAFFOLDING INC | General Contractor | 1 | 07/08/2026 |
| DENKO MECHANICAL | General Contractor | 1 | 04/09/2026 |
| HARD SAFARI CORP | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| AMARACON TESTING & INSPEC | 5842 | 23 | 03/25/2026 |
| DAVID BUCOVY ARCHITECT | 915 | 2 | 02/05/2026 |
| TANG STUDIO LLC | 6949 | 3 | 07/14/2025 |
| ABS ENGINEERING, PLLC | 4835 | 9 | 11/12/2024 |
| WORLD DESIGN ARCHITECTURE | 9323 | 3 | 11/12/2024 |
| VALERIO ASSOCIATES, P.C. | 1379 | 5 | 03/27/2024 |
| SOCOTEC, INC. | 301 | 1 | 10/28/2021 |
| GROUP PROJECTS ARCHITECTU | 7768 | 1 | 09/21/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | FOLOR INC | 04/10/2026 |
| DOB NOW | General Construction | Permit Issued | FOLOR INC | 04/07/2026 |
| DOB NOW | General Construction | Permit Issued | FOLOR INC | 04/07/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | FOLOR INC | 04/07/2026 |
| DOB NOW | Sprinklers | Permit Issued | FULL CAPACITY FIRE CORP | 04/03/2026 |
| DOB NOW | Sprinklers | Permit Issued | FULL CAPACITY FIRE CORP | 04/01/2026 |
| DOB NOW | General Construction | Permit Issued | RAF GENERAL CONTRACTING C | 10/24/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | FOLOR INC | 10/16/2025 |
| DOB NOW | General Construction | Permit Issued | JR FRAMING | 10/03/2025 |
| DOB NOW | Plumbing | Signed-off | A&A PLUMBING CORP | 06/23/2025 |
| DOB NOW | Plumbing | Signed-off | A&A PLUMBING CORP | 05/09/2025 |
| DOB NOW | General Construction | Signed-off | FOLOR INC | 04/22/2025 |
| DOB NOW | Plumbing | Permit Issued | A&A PLUMBING CORP | 04/21/2025 |
| DOB NOW | General Construction | Signed-off | FOLOR INC | 02/26/2025 |
| DOB NOW | Sprinklers | Signed-off | JEM FIRE PREVENTION INC | 01/24/2025 |
| DOB NOW | General Construction | Permit Issued | KLARACON | 12/31/2024 |
| DOB NOW | General Construction | Signed-off | NON LIMITE INC | 11/25/2024 |
| DOB NOW | Mechanical Systems | Signed-off | NON LIMITE INC | 11/25/2024 |
| DOB NOW | Sign | Signed-off | A.M.A HOLDINGS INC | 11/14/2024 |
| DOB NOW | Sign | Signed-off | A.M.A HOLDINGS INC | 11/14/2024 |
| DOB NOW | General Construction | Permit Issued | FOLOR INC | 11/07/2024 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | CONSOLIDATED SCAFFOLDING | 08/02/2024 |
| DOB NOW | Mechanical Systems | Signed-off | KLARACON | 07/05/2024 |
| DOB NOW | General Construction | Permit Issued | FOLOR INC | 05/24/2024 |
| DOB NOW | Structural | Permit Issued | FOLOR INC | 05/07/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | FOLOR INC | 05/07/2024 |
| DOB NOW | Sprinklers | Permit Issued | FULL CAPACITY FIRE CORP | 04/29/2024 |
| DOB NOW | Sprinklers | Permit Issued | FULL CAPACITY FIRE CORP | 03/25/2024 |
| DOB NOW | General Construction | Permit Issued | KLARACON | 02/20/2024 |
| DOB NOW | Mechanical Systems | Signed-off | KLARACON | 02/20/2024 |
| DOB NOW | Plumbing | Signed-off | A&A PLUMBING CORP | 02/09/2024 |
| DOB NOW | General Construction | Permit Issued | FOLOR INC | 02/02/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | FOLOR INC | 01/31/2024 |
| DOB NOW | General Construction | Permit Issued | KLARACON | 12/18/2023 |
| DOB NOW | Mechanical Systems | Signed-off | KLARACON | 12/18/2023 |
| DOB NOW | Mechanical Systems | Signed-off | KLARACON | 11/28/2023 |
| DOB NOW | Plumbing | Signed-off | IMPACT PLUMBING INC | 09/26/2023 |
| DOB NOW | General Construction | Permit Issued | KLARACON | 09/11/2023 |
| DOB NOW | General Construction | Permit Issued | HARD SAFARI CORP | 08/08/2023 |
| DOB NOW | General Construction | Signed-off | KLARACON | 03/13/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 03/25/2026 | Permit Issued | FOLOR INC | Heating and Air Conditioning Systems | Heat / Cool Daikin RXTQ60TBVJUB 60,000 BTU · Vrf Outdoor ×1 |
| 03/25/2026 | Permit Issued | FOLOR INC | Heating and Air Conditioning Systems | Heat / Cool Daikin Daikin RXYA120AATJA 91,000 BTU · Condensing Unit ×1 Daikin RXYA72AATJA 65,500 BTU · Vrf Outdoor ×1 |
| 03/03/2026 | Permit Issued | FOLOR INC | Others | Other Neptronic DF CF00H 7 kW · Ductwork ×3 |
| 11/12/2024 | Permit Issued | FOLOR INC | Heating and Air Conditioning Systems | Heat / Cool Daikin REYQ120AATJA 114,000 BTU · Vrf Outdoor ×2 |
| 01/11/2024 | Permit Issued | FOLOR INC | Heating and Air Conditioning Systems | Heat / Cool Daikin RXTQ60TBVJUA 57,500 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/25/2026 | Permit Issued | FULL CAPACITY FIRE CORP | Sprinkler System |
| 03/25/2026 | Permit Issued | FULL CAPACITY FIRE CORP | — |
| 03/03/2026 | — | — | 26 heads |
| 01/10/2024 | Permit Issued | FULL CAPACITY FIRE CORP | 18 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/03/2026 | Permit Issued | A&A PLUMBING CORP | Water/Sanitary |
| 07/14/2025 | — | — | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/20/2026 | Permit Issued | EMPIRE STATE ELEC MAINT & | General Wiring |
| 07/20/2026 | Permit Issued | EMPIRE STATE ELEC MAINT & | General Wiring |
| 01/22/2026 | Permit Issued | MACINTOSH ELECTRIC CORP | General Wiring |
| 06/25/2025 | Complete | EMPIRE STATE ELEC MAINT & | General Wiring |
| 03/21/2025 | Complete | EMPIRE STATE ELEC MAINT & | — |
| 03/21/2025 | Permit Issued | EMPIRE STATE ELEC MAINT & | General Wiring |
| 08/09/2024 | Complete | MSK ELECTL INSTALLATION | General Wiring |
| 07/15/2024 | Complete | EMPIRE STATE ELEC MAINT & | General Wiring, Lighting |
| 11/04/2020 | Complete | BOROWIDE ELECT'L CONTR'S | — |
| 04/10/2019 | Complete | ASK ELECTL CONTRTNG CORP | General Wiring |
| 08/01/2018 | Permit Issued | HESO ELECTRICAL INC | General Wiring |
| 04/26/2018 | Permit Issued | AVALON ELECTRIC CORP. | General Wiring, Lighting |
| 04/26/2018 | Permit Issued | AVALON ELECTRIC CORP. | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/27/2024 | Permit Issued | FOLOR INC | Steel, Concrete, Masonry |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/24/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/29/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/29/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/15/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/22/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/20/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/01/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/07/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/07/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/02/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/18/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/01/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/17/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 11/05/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/30/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/30/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/15/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/15/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/14/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/06/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/05/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/11/2022 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/08/2022 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/09/2026 | Fire-Resistance Rated Construction | david bucovy | progress |
| 04/09/2026 | Fire-Resistant Penetrations and Joints | david bucovy | special |
| 04/09/2026 | Final | david bucovy | progress |
| 03/23/2026 | Final | CONNIE PISANI | progress |
| 03/18/2026 | Energy Code Compliance Inspections | CONNIE PISANI | progress |
| 03/18/2026 | Sprinkler Systems | CONNIE PISANI | special |
| 03/18/2026 | Fire-Resistant Penetrations and Joints | CONNIE PISANI | special |
| 03/18/2026 | Mechanical Systems | CONNIE PISANI | special |
| 03/18/2026 | Final | CONNIE PISANI | progress |
| 03/18/2026 | Heating Systems | CONNIE PISANI | special |
| 03/03/2026 | Fire-Resistant Penetrations and Joints | CONNIE PISANI | special |
| 03/03/2026 | Final | CONNIE PISANI | progress |
| 03/03/2026 | Mechanical Systems | CONNIE PISANI | special |
| 03/03/2026 | Fire-Resistant Penetrations and Joints | CONNIE PISANI | special |
| 03/03/2026 | Post-installed Anchors | CONNIE PISANI | special |
| 03/03/2026 | Final | CONNIE PISANI | progress |
| 03/03/2026 | Post-installed Anchors | CONNIE PISANI | special |
| 03/03/2026 | Mechanical Systems | CONNIE PISANI | special |
| 01/20/2026 | Final | david bucovy | progress |
| 01/20/2026 | Fire-Resistant Penetrations and Joints | david bucovy | special |
| 01/20/2026 | Fire-Resistance Rated Construction | david bucovy | progress |
| 11/10/2025 | Mechanical Systems | CONNIE PISANI | special |
| 11/10/2025 | Post-installed Anchors | CONNIE PISANI | special |
| 11/10/2025 | Sprinkler Systems | CONNIE PISANI | special |
| 11/10/2025 | Sprinkler Systems | CONNIE PISANI | special |