← Back
Two stories - detached, small or mid-size
53-08 212 STREET
QUEENS · BIN 4159610
💬 Discuss this project
1940Year Built
2.5Stories
A1Building Class
R2AZoning
2,000 sfGross Floor Area
1Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Two stories - detached, small or mid-size · 4,950 sf lot · 0.4 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingCivilGeneral
Permit Issued — active, not yet Signed-off
Floor 2Under Construction18p · 1 filing · 20 docs
Floor 1Under Construction17p · 1 filing · 20 docs
CellarUnder Construction19p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
04/15/2019$1000K—Private party → Private party$500/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LI ARCHITECT ASSOCIATE, PLLC908/13/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TLS CONSTRUCTION GROUP I*General Contractor807/31/2026
L&L CONSTRUCTION DEVELOPGeneral Contractor303/21/2026
ERIC & NG ELEC'L, INC.Electrical103/22/2026
MPS PLUMBING & HEATING INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
LI ARCHITECT ASSOCIATE, P1104708/13/2026
Building Lifecycle
All (96)Filed (9)Permit Issued (8)Violation (3)Inspection (8)Objection (38)Special Inspection (30)
08/13/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
Filing plumbing work type in-conjunction with GC job number Q01215476-I1
Q01215476-P7
08/13/2026
Special inspection requirement — Exhaust and Vent Systems in Plenums and Ducts
08/06/2026
Special inspection requirement — Chimneys and vents
08/05/2026
Special inspection requirement — Duct leakage testing, insulation and design
Ling Li
08/05/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Ling Li
08/05/2026
Special inspection requirement — Metering
Ling Li
08/05/2026
Special inspection requirement — Lighting in dwelling units
Ling Li
08/05/2026
Special inspection requirement — Energy Code Compliance Inspections
Ling Li
08/05/2026
Special inspection requirement — Mechanical Systems
Ling Li
08/05/2026
Special inspection requirement — Electric vehicle service equipment requirements
Ling Li
08/05/2026
Special inspection requirement — HVAC-R and service water heating equipment
Ling Li
08/05/2026
Special inspection requirement — Fenestration air leakage
Ling Li
08/05/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Ling Li
08/05/2026
Special inspection requirement — HVAC-R and service water heating system controls
Ling Li
08/05/2026
Special inspection requirement — Insulation placement and R values
Ling Li
08/05/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Ling Li
08/05/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Ling Li
08/05/2026
Special inspection requirement — Final
Ling Li
08/05/2026
Special inspection requirement — Maintenance information
Ling Li
08/05/2026
Special inspection requirement — Fire-Resistance Rated Construction
Ling Li
08/05/2026
Special inspection requirement — Footing and Foundation
Ling Li
08/05/2026
Special inspection requirement — Permanent certificate
Ling Li
08/05/2026
Special inspection requirement — Air barrier - visual inspection
Ling Li
08/05/2026
Special inspection requirement — Concrete - Cast-In-Place
Ling Li
08/05/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Ling Li
08/05/2026
Special inspection requirement — Air barrier — testing
Ling Li
08/05/2026
Special inspection requirement — Ventilation and air distribution system
Ling Li
08/05/2026
Special inspection requirement — Demolition
Ling Li
08/05/2026
Special inspection requirement — Fenestration areas
Ling Li
07/30/2026
Permit issued — Construction Fence
Q01215930-I1-FN
07/10/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
06/30/2026
Violation issued (ECB, open)
Construction
06/19/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
Filing plumbing work type in-conjunction with GC job number Q01215476-I1
Q01215476-P6
05/21/2026
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
03/24/2026
Violation issued (ECB, closed)
Construction
02/24/2026
Permit issued — Structural
Q01215476-S4-ST
01/19/2026
Objection resolved — Addressed
01/17/2026
Objection raised — Other
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/16/2025
Objection resolved — Addressed
12/10/2025
Objection raised — Structural
12/10/2025
Objection raised — Structural
12/10/2025
Objection raised — Structural
12/10/2025
Objection raised — Structural
12/09/2025
Violation issued (ECB, closed)
Construction
12/03/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Filing plumbing work type in-conjunction with GC job number Q01215476-I1
Q01215476-P2
12/03/2025
Permit issued — Earth Work
Q01215476-I1-FO-EA
12/01/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Filing plumbing work type in-conjunction with GC job number Q01215476-I1
Q01215476-S4
11/20/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Ling Li
11/20/2025
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Ling Li
11/13/2025
Inspection — Fail-Final PL - Underground
Fail
View inspection ↗
10/16/2025
Permit issued — Mechanical Systems
Q01215476-I1-GC
10/16/2025
Permit issued — Mechanical Systems
Q01215476-I1-MS
10/16/2025
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
10/02/2025
Permit issued — Plumbing
Q01215476-S2-PL
10/02/2025
Objection resolved — Addressed
10/02/2025
Objection resolved — Addressed
10/02/2025
Objection resolved — Addressed
Latest 60 of 96 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FencePermit IssuedTLS CONSTRUCTION GROUP I*07/30/2026
DOB NOWStructuralPermit IssuedTLS CONSTRUCTION GROUP I*02/24/2026
DOB NOWEarth WorkPermit IssuedTLS CONSTRUCTION GROUP I*12/03/2025
DOB NOWMechanical SystemsPermit IssuedTLS CONSTRUCTION GROUP I*10/16/2025
DOB NOWMechanical SystemsPermit IssuedTLS CONSTRUCTION GROUP I*10/16/2025
DOB NOWPlumbingPermit IssuedMPS PLUMBING & HEATING IN10/02/2025
DOB NOWEarth WorkPermit IssuedL&L CONSTRUCTION DEVELOP09/08/2025
DOB NOWConstruction FencePermit IssuedTLS CONSTRUCTION GROUP I*05/16/2025
1 project · most recent 08/13/2026
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScope
08/13/2026Permit IssuedTLS CONSTRUCTION GROUP I*Heating and Air Conditioning Systems, Ventilation Systems
1 project · most recent 08/13/2026
Gas Water/Sanitary
FiledStatusContractorScope
08/13/2026Permit IssuedMPS PLUMBING & HEATING INGas, Water/Sanitary
2 projects · most recent 08/30/2026
General Wiring
FiledStatusContractorScope
08/30/2026Permit IssuedERIC & NG ELEC'L, INC.General Wiring
10/06/2025Permit IssuedERIC & NG ELEC'L, INC.—
1 project · most recent 08/13/2026
Steel
FiledStatusContractorScope
08/13/2026Permit IssuedTLS CONSTRUCTION GROUP I*Steel
1 project · most recent 08/13/2026
Earthwork
FiledStatusContractorScope
08/13/2026Permit IssuedTLS CONSTRUCTION GROUP I*Earthwork
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
07/10/2026Fail-Final General Construction Non-Directive 14FailView ↗
05/21/2026Fail-Final General Construction Non-Directive 14FailView ↗
11/13/2025Fail-Final PL - UndergroundFailView ↗
10/16/2025Pass-Final PL - UndergroundPassView ↗
07/13/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/28/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
06/23/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
02/08/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 63
DateRequirementInspectorRole
08/13/2026Exhaust and Vent Systems in Plenums and Ducts—special
08/06/2026Chimneys and vents—special
08/05/2026MeteringLing Lienergy_progress
08/05/2026Air barrier — testing Ling Lienergy_progress
08/05/2026HVAC-R and service water piping design and insulationLing Lienergy_progress
08/05/2026Ventilation and air distribution systemLing Lienergy_progress
08/05/2026Lighting in dwelling unitsLing Lienergy_progress
08/05/2026Concrete - Cast-In-PlaceLing Lispecial
08/05/2026DemolitionLing Lispecial
08/05/2026Excavations - Sheeting, Shoring, and BracingLing Lispecial
08/05/2026Fire-Resistant Penetrations and JointsLing Lispecial
08/05/2026Mechanical SystemsLing Lispecial
08/05/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationLing Lispecial
08/05/2026Energy Code Compliance InspectionsLing Liprogress
08/05/2026FinalLing Liprogress
08/05/2026Fire-Resistance Rated ConstructionLing Liprogress
08/05/2026Footing and FoundationLing Liprogress
08/05/2026Electric vehicle service equipment requirementsLing Lienergy_progress
08/05/2026Permanent certificateLing Lienergy_progress
08/05/2026Air barrier - visual inspectionLing Lienergy_progress
08/05/2026HVAC-R and service water heating equipmentLing Lienergy_progress
08/05/2026Fenestration and door U-factor and product ratingsLing Lienergy_progress
08/05/2026Maintenance informationLing Lienergy_progress
08/05/2026Fenestration air leakageLing Lienergy_progress
08/05/2026Insulation placement and R valuesLing Lienergy_progress
Latest 25 of 63.
▾Documents — 66 on file (BIS + DOB NOW)
▸Plans & Drawings10
▸DOB NOWPlans/Sketch10
08/20/2026Q01215930-I1Request digital key ↗
08/19/2026Q01215476-P5Request digital key ↗
08/19/2026Q01215476-P2Request digital key ↗
Showing 3 of 10 on file for this type
▸Zoning, Tax Lot & Property Records6
▸DOB NOWZD1: DOB Zoning Diagram4
08/19/2026Q01215476-P7Open ↗
08/19/2026Q01215476-P6Open ↗
08/13/2026Q01215476-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/13/2026Q01215476-P2Open ↗
08/13/2026Q01215476-I1Open ↗
▸Seals & Professional Certifications23
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/20/2026Q01215930-I1Open ↗
08/19/2026Q01215476-P5Open ↗
08/19/2026Q01215476-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
08/28/2026Q01215476-P5Open ↗
08/28/2026Q01215476-P5Open ↗
08/27/2026Q01215476-P7Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
08/28/2026Q01215476-P5Open ↗
08/27/2026Q01215476-P7Open ↗
08/25/2026Q01215476-S2Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment4
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)4
08/19/2026Q01215476-P7Open ↗
08/19/2026Q01215476-P6Open ↗
08/13/2026Q01215476-I1Open ↗
Showing 3 of 4 on file for this type
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/19/2026Q01215476-P7Open ↗
▸Environmental & Asbestos9
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/19/2026Q01215476-P5Open ↗
08/19/2026Q01215476-P7Open ↗
08/19/2026Q01215476-P6Open ↗
Showing 3 of 9 on file for this type
▸Other Documents13
▸DOB NOWProperty Ownership Certification4
08/19/2026Q01215476-P7Open ↗
08/19/2026Q01215476-P6Open ↗
08/13/2026Q01215476-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSite Survey: Initial4
08/19/2026Q01215476-P7Open ↗
08/19/2026Q01215476-P6Open ↗
08/13/2026Q01215476-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone4
08/19/2026Q01215476-P7Open ↗
08/19/2026Q01215476-P6Open ↗
08/13/2026Q01215476-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWAdjoining Owners Notification1
08/13/2026Q01215476-I1Open ↗