← Back
Two family frame
53-18 HASPEL STREET
QUEENS · Elmhurst · BIN 4065640
💬 Discuss this project
1920Year Built
2Stories
B2Building Class
R5Zoning
2,116 sfGross Floor Area
2Units
Two family frame · 2,500 sf lot · 0.85 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectrical
Roof3p · 1 filing · 13 docs
Sub-Basement1 filing · 13 docs
Site & exterior1 filing · 13 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NY BUILDING ASSOCIATES INC202/24/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BROOKLYN SOLARWORKS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ARC ELECTRICAL & MECH CONElectrical103/21/2026
BROOKYLN SOLARWORKS, LLCElectrical103/22/2026
STEVEN BURKEElectrical103/21/2026
BROOKLYN SOLARWORKS LLCGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NKM ENGINEERING PLLC6244202/24/2026
Building Lifecycle
All (12)Filed (2)Permit Issued (1)Signed Off (1)Special Inspection (8)
03/02/2026
Signed off — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
Q01277567-I1
03/02/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
03/02/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
03/02/2026
Special inspection requirement — Final
NARESH MAHANGU
03/02/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
02/24/2026
Filed — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
Q01277567-P1
02/24/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
NARESH MAHANGU
02/24/2026
Special inspection requirement — Energy Code Compliance Inspections
NARESH MAHANGU
02/24/2026
Special inspection requirement — Final
NARESH MAHANGU
02/24/2026
Special inspection requirement — Air barrier - visual inspection
NARESH MAHANGU
09/04/2025
Permit issued — Solar
Q01277567-I1-SL
08/28/2025
Filed — Alteration
INSTALLATION OF SOLAR PV SYSTEM. NO CHANGE TO USE, EGRESS, OR OCCUPANCY.
Q01277567-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offBROOKLYN SOLARWORKS LLC09/04/2025
BIS—ISSUEDPETER HOME IMPROVEMENT08/13/2004
BISPLISSUEDWAGNER ZIV PLUMBING & HEATING08/02/2004
BISPLISSUEDWADE PLG & HTG05/25/2004
1 project · most recent 10/20/2025
FiledStatusContractorScope
10/20/2025CompleteBROOKYLN SOLARWORKS, LLC—
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
03/02/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
03/02/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
03/02/2026FinalNARESH MAHANGUprogress
03/02/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
02/24/2026Fire-Resistant Penetrations and JointsNARESH MAHANGUspecial
02/24/2026Energy Code Compliance InspectionsNARESH MAHANGUprogress
02/24/2026FinalNARESH MAHANGUprogress
02/24/2026Air barrier - visual inspectionNARESH MAHANGUenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/17/2026Q01277567-P1Request digital key ↗
08/17/2026Q01277567-I1Request digital key ↗
▸Seals & Professional Certifications8
▸DOB NOWProgress Inspector Seal & Signature4
08/26/2026Q01277567-I1Open ↗
08/26/2026Q01277567-I1Open ↗
08/25/2026Q01277567-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/17/2026Q01277567-I1Open ↗
08/13/2026Q01277567-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026Q01277567-I1Open ↗
08/25/2026Q01277567-P1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/17/2026Q01277567-I1Open ↗
08/13/2026Q01277567-P1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01277567-I1Open ↗