| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/21/2021 | $850K | — | Private party → Private party | $824/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| EDWARD LUI ARCHITECT PLLC | 6 | 11/05/2024 |
| PARKER AND WEST ENGINEERING, PLLC | 1 | 03/01/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| AMTECK CORP | General Contractor | 7 | 07/08/2026 |
| HI-TECH PLUMBING & HEATING | Plumbing | 2 | 07/08/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| G ENGINEERING PC | 7778 | 7 | 11/05/2024 |
| PARKER AND WEST ENGINEERI | 5272 | 1 | 03/01/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 03/08/2024 |
| DOB NOW | Plumbing | Signed-off | HI-TECH PLUMBING & HEATIN | 12/11/2023 |
| DOB NOW | Construction Fence | Signed-off | AMTECK CORP | 12/05/2023 |
| DOB NOW | Earth Work | Permit Issued | AMTECK CORP | 12/05/2023 |
| DOB NOW | Plumbing | Signed-off | HI-TECH PLUMBING & HEATIN | 09/04/2023 |
| DOB NOW | Foundation | Signed-off | AMTECK CORP | 08/24/2023 |
| DOB NOW | Structural | Permit Issued | AMTECK CORP | 08/24/2023 |
| DOB NOW | Foundation | Signed-off | AMTECK CORP | 08/23/2023 |
| DOB NOW | Foundation | Signed-off | AMTECK CORP | 08/23/2023 |
| DOB NOW | Construction Fence | Signed-off | AMTECK CORP | 08/15/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/05/2024 | Signed-off | HI-TECH PLUMBING & HEATIN | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/05/2024 | Complete | R & T ELECTRICAL CORP | General Wiring |
| 03/01/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/04/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/06/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/04/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/22/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/31/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/31/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/14/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/11/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/13/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/13/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/04/2024 | Concrete - Cast-In-Place | XIONGCAI GU | special |
| 12/04/2024 | Maintenance information | XIONGCAI GU | energy_progress |
| 12/04/2024 | Interior lighting power | XIONGCAI GU | energy_progress |
| 12/04/2024 | Air barrier — testing | XIONGCAI GU | energy_progress |
| 12/04/2024 | Fenestration air leakage | XIONGCAI GU | energy_progress |
| 12/04/2024 | Fenestration and door U-factor and product ratings | XIONGCAI GU | energy_progress |
| 12/04/2024 | Insulation placement and R values | XIONGCAI GU | energy_progress |
| 12/04/2024 | Electric vehicle service equipment requirements | XIONGCAI GU | energy_progress |
| 12/04/2024 | Metering | XIONGCAI GU | energy_progress |
| 12/04/2024 | Protection of exposed foundation insulation | XIONGCAI GU | energy_progress |
| 12/04/2024 | Fenestration areas | XIONGCAI GU | energy_progress |
| 12/04/2024 | Air barrier - visual inspection | XIONGCAI GU | energy_progress |
| 12/04/2024 | Permanent certificate | XIONGCAI GU | energy_progress |
| 12/04/2024 | Energy Code Compliance Inspections | XIONGCAI GU | progress |
| 12/04/2024 | Footing and Foundation | XIONGCAI GU | progress |
| 12/04/2024 | Fire-Resistance Rated Construction | XIONGCAI GU | progress |
| 12/04/2024 | Final | YIPENG LUAN | progress |
| 12/04/2024 | Structural Wood Frame | XIONGCAI GU | progress |
| 12/04/2024 | Masonry | XIONGCAI GU | special |
| 12/04/2024 | Fire-Resistant Penetrations and Joints | XIONGCAI GU | special |
| 12/04/2024 | Structural Stability – Alterations of existing buildings | XIONGCAI GU | special |
| 11/03/2024 | Interior lighting power | XIONGCAI GU | energy_progress |
| 11/03/2024 | Concrete - Cast-In-Place | XIONGCAI GU | special |
| 11/03/2024 | Fire-Resistant Penetrations and Joints | XIONGCAI GU | special |
| 11/03/2024 | Masonry | XIONGCAI GU | special |