← Back
BuildNYC
One story - permanent living quarter
53 DALE AVENUE
STATEN ISLAND · BIN 5058881
💬 Discuss this project
1950Year Built
1Stories
A2Building Class
R3XZoning
912 sfGross Floor Area
1Units
One story - permanent living quarter · 5,000 sf lot · 0.18 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Filed — no permit issued34p · 1 filing · 5 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Kindo210/21/2026
Building Lifecycle
10/21/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
ALT-CO OF TWO STORY WITH ATTIC & CELLAR, SEMI-DETACHED TWO FAMILY BUILDING FILED UNDER NYC 2022 BUILDING CODE.
S01366746-S1
05/06/2026
Objection raised — Fire_Protection
05/06/2026
Objection raised — Scope
03/23/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
ALT-CO OF TWO STORY WITH ATTIC & CELLAR, SEMI-DETACHED TWO FAMILY BUILDING FILED UNDER NYC 2022 BUILDING CODE.
S01366746-I1
03/19/2026
Special inspection requirement — Insulation placement and R values
29 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Nothing on file for this building.
1 project · most recent 10/21/2026
Steel Concrete Wood
FiledStatusContractorScope
10/21/2026——Steel, Concrete, Wood
1 project · most recent 10/21/2026
Fence
FiledStatusContractorScope
10/21/2026——Fence
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
03/19/2026Insulation placement and R values—energy_progress
03/19/2026Concrete - Cast-In-Place—special
03/19/2026Demolition—special
03/19/2026Exterior Insulation and Finish Systems (EIFS)—special
03/19/2026Fire-Resistant Penetrations and Joints—special
03/19/2026Post-installed Anchors—special
03/19/2026Structural Stability – Alterations of existing buildings—special
03/19/2026Structural Cold-Formed Steel—special
03/19/2026Structural Steel - Details—special
03/19/2026Energy Code Compliance Inspections—progress
03/19/2026Fenestration air leakage—energy_progress
03/19/2026Chimneys and vents—special
03/19/2026Fire-Resistance Rated Construction—progress
03/19/2026Interior lighting power—energy_progress
03/19/2026Lighting controls—energy_progress
03/19/2026Permanent certificate—energy_progress
03/19/2026Air barrier — testing —energy_progress
03/19/2026Protection of exposed foundation insulation—energy_progress
03/19/2026Electric vehicle service equipment requirements—energy_progress
03/19/2026Air barrier - visual inspection—energy_progress
03/19/2026Fenestration and door U-factor and product ratings—energy_progress
03/19/2026Fireplaces—energy_progress
03/19/2026Fenestration areas—energy_progress
03/03/2026Final—progress
03/03/2026Footing and Foundation—progress
6 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account