| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/13/2023 | $3.8M | — | — → — | $1,257/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| WILLIAM F. RYAN, JR. P.E. PC | 2 | 06/09/2023 |
| LAURA CARTER RA | 1 | 06/09/2023 |
| STRATFORD ENGINEERING | 1 | 06/09/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| CODE | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| THINK CONSTRUCTION LLC | General Contractor | 7 | 07/08/2026 |
| ARCON PLBG SOLUTIONS | Plumbing | 1 | 07/08/2026 |
| DONATO PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| RYAN SPECIAL ENGINEERING | 2018 | 1 | 06/09/2023 |
| STRATFORD ENGINEERING | 997 | 2 | 06/09/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | THINK CONSTRUCTION LLC | 10/22/2024 |
| DOB NOW | Plumbing | Signed-off | DONATO PLUMBING, INC | 03/25/2024 |
| DOB NOW | General Construction | Signed-off | THINK CONSTRUCTION LLC | 09/21/2023 |
| DOB NOW | Mechanical Systems | Signed-off | THINK CONSTRUCTION LLC | 09/21/2023 |
| DOB NOW | General Construction | Signed-off | THINK CONSTRUCTION LLC | 09/21/2023 |
| DOB NOW | Plumbing | Signed-off | ARCON PLBG SOLUTIONS | 08/24/2023 |
| BIS | PL | ISSUED | P.S.I. MECHANICAL | 05/03/2017 |
| BIS | OT | ISSUED | KEVIN GREER FINE CARPENTR | 06/05/2015 |
| BIS | PL | ISSUED | 24 SEVEN PLUMBING INC | 11/14/2014 |
| BIS | OT | ISSUED | KEVIN GREER FINE CARPENTR | 10/02/2014 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/21/2025 | Complete | FRACCAVENTO ELEC. CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/05/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/05/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/05/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/11/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/23/2023 | Fire-Resistance Rated Construction | LAURA CARTER | progress |
| 06/06/2023 | Chimneys and vents | William Ryan | special |
| 06/06/2023 | Fire-Resistant Penetrations and Joints | William Ryan | special |
| 06/06/2023 | Masonry | Xianzhang Chen | special |
| 06/06/2023 | Structural Cold-Formed Steel | Xianzhang Chen | special |
| 06/06/2023 | Structural Steel - Details | Xianzhang Chen | special |
| 06/06/2023 | Structural Stability – Alterations of existing buildings | Xianzhang Chen | special |
| 06/06/2023 | Concrete - Cast-In-Place | Xianzhang Chen | special |
| 06/06/2023 | Structural Steel - High Strength Bolting | Xianzhang Chen | special |
| 06/06/2023 | Post-installed Anchors | Xianzhang Chen | special |
| 06/06/2023 | Lowest Floor Elevation | Xianzhang Chen | progress |
| 06/06/2023 | Final | Xianzhang Chen | progress |
| 06/06/2023 | Footing and Foundation | Xianzhang Chen | progress |
| 06/06/2023 | Structural Steel - Welding | Xianzhang Chen | special |
| 05/26/2023 | Mechanical Systems | William Ryan | special |
| 05/26/2023 | Final | William Ryan | progress |
| 05/25/2023 | Final | LAURA CARTER | progress |
| 05/25/2023 | Structural Stability – Alterations of existing buildings | Xianzhang Chen | special |