| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2026 | Signed-off | AMERICAN STANDARD P&H COR | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/18/2025 | Complete | A.C. MORGAN ELECTRIC | General Wiring |
| 10/22/2024 | Complete | GOODALL ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2026 | Signed-off | AMERICAN STANDARD P&H COR | Steel |
| Owner | Filings | Most Recent |
|---|---|---|
| LT PRO CONSTRUCTION | 40 | 07/08/2026 |
| 532 CLINTON ST LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/23/2026 | $5.0M | — | — → — | $1,982/sf building |
| 07/09/2024 | $2.5M | — | FM 532 CLINTON CORP → 532 CLINTON ST LLC | $992/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NA | 7 | 01/27/2026 |
| BANGASH ASSOCIATES INC. | 7 | 11/04/2025 |
| NY BUILDING ASSOCIATES INC | 1 | 09/20/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| BUILD TEAM | 6 | 03/21/2026 |
| NYC BUILDING CONSULTANTS | 9 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| LT PRO CONSTRUCTION INC | General Contractor | 6 | 07/08/2026 |
| AMERICAN STANDARD P&H CORORP. | Plumbing | 3 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BANGASH ASSOCIATES INC | 8488 | 6 | 11/04/2025 |
| JUST CONSULTING ENGINEERI | 5865 | 2 | 03/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | AMERICAN STANDARD P&H CORORP. | 12/17/2025 |
| DOB NOW | Plumbing | Signed-off | AMERICAN STANDARD P&H CORORP. | 05/12/2025 |
| DOB NOW | General Construction | Permit Issued | LT PRO CONSTRUCTION INC | 03/20/2025 |
| DOB NOW | Structural | Signed-off | LT PRO CONSTRUCTION INC | 03/04/2025 |
| DOB NOW | General Construction | Signed-off | LT PRO CONSTRUCTION INC | 02/03/2025 |
| DOB NOW | Plumbing | Signed-off | AMERICAN STANDARD P&H CORORP. | 10/30/2024 |
| DOB NOW | General Construction | Signed-off | LT PRO CONSTRUCTION INC | 08/13/2024 |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/16/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/09/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/15/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 10/15/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 10/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 10/15/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 10/02/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/07/2025 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 03/31/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/20/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/20/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 01/02/2025 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 10/25/2024 | Certified StandPipe-SD-Fixtures-Finish-SD | Certified | View ↗ |
| 06/21/2024 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/17/2026 | Fenestration and door U-factor and product ratings | XIAOJUN WANG | energy_progress |
| 03/17/2026 | Fenestration areas | XIAOJUN WANG | energy_progress |
| 03/17/2026 | Fire-Resistance Rated Construction | XIAOJUN WANG | progress |
| 03/17/2026 | Air barrier - visual inspection | XIAOJUN WANG | energy_progress |
| 03/17/2026 | Insulation placement and R values | XIAOJUN WANG | energy_progress |
| 03/17/2026 | Interior lighting power | XIAOJUN WANG | energy_progress |
| 03/17/2026 | Fenestration air leakage | XIAOJUN WANG | energy_progress |
| 01/26/2026 | Fenestration air leakage | XIAOJUN WANG | energy_progress |
| 01/26/2026 | Interior lighting power | XIAOJUN WANG | energy_progress |
| 01/26/2026 | Fenestration and door U-factor and product ratings | XIAOJUN WANG | energy_progress |
| 01/26/2026 | Air barrier - visual inspection | XIAOJUN WANG | energy_progress |
| 01/26/2026 | Fire-Resistance Rated Construction | XIAOJUN WANG | progress |
| 01/26/2026 | Insulation placement and R values | XIAOJUN WANG | energy_progress |
| 01/26/2026 | Fenestration areas | XIAOJUN WANG | energy_progress |
| 11/10/2025 | Energy Code Compliance Inspections | FAZAL BANGASH | progress |
| 11/10/2025 | HVAC-R and service water heating equipment | FAZAL BANGASH | energy_progress |
| 11/10/2025 | Permanent certificate | FAZAL BANGASH | energy_progress |
| 11/10/2025 | HVAC-R and service water heating system controls | FAZAL BANGASH | energy_progress |
| 11/10/2025 | HVAC-R and service water piping design and insulation | FAZAL BANGASH | energy_progress |
| 11/10/2025 | Fire-Resistant Penetrations and Joints | FAZAL BANGASH | special |
| 11/05/2025 | Fire-Resistant Penetrations and Joints | FAZAL BANGASH | special |
| 11/05/2025 | Energy Code Compliance Inspections | FAZAL BANGASH | progress |
| 11/05/2025 | HVAC-R and service water piping design and insulation | FAZAL BANGASH | energy_progress |
| 11/03/2025 | HVAC-R and service water piping design and insulation | FAZAL BANGASH | energy_progress |
| 11/03/2025 | HVAC-R and service water heating equipment | FAZAL BANGASH | energy_progress |