| Owner | Filings | Most Recent |
|---|---|---|
| PARK SLOPE RENTALS 1 LLC | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/09/2026 | $3.1M | — | — → — | $648/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| JOHN H HATHEWAY JR., ARCHITECT | 1 | 08/05/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/31/2026 | Complete | ANTONIO CERIELLO ELEC INC | 3 meters, 3 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2026 | — | — | Steel, Masonry, Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/30/2026 | Structural Steel - Details | — | special |
| 07/27/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 07/27/2026 | Concrete - Cast-In-Place | — | special |
| 07/27/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/27/2026 | Post-installed Anchors | — | special |
| 07/27/2026 | Final | — | progress |
| 07/27/2026 | Fire-Resistance Rated Construction | — | progress |
| 07/27/2026 | Structural Wood Frame | — | progress |
| 07/27/2026 | Fenestration and door U-factor and product ratings | John Hatheway | energy_progress |
| 07/27/2026 | Fenestration air leakage | John Hatheway | energy_progress |
| 07/27/2026 | Air barrier - visual inspection | John Hatheway | energy_progress |
| 07/27/2026 | Interior lighting power | John Hatheway | energy_progress |
| 07/27/2026 | Insulation placement and R values | John Hatheway | energy_progress |
| 07/27/2026 | Masonry | — | special |
| 07/27/2026 | Fenestration areas | John Hatheway | energy_progress |