1931Year Built
2Stories
B1Building Class
R6BZoning
2,340 sfGross Floor Area
2Units
0 Active ViolationsFDNY Report ↗
Two family brick · Owner of record: 534 Kosciuszko BK · 1,950 sf lot · 1.2 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 212p · 2 filings · 20 docs
Floor 113p · 2 filings · 20 docs
Cellar13p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Skyview GC1104/09/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/22/2025$1.0M—Flagstar Bank, N.A. → 534 KOSCIUSZKO BK INC$438/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Asr Engineering402/11/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Brothers Construction GroupGeneral Contractor104/09/2026
M & M Piping and HeatingPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Asr Engineering8404302/11/2026
Building Lifecycle
03/30/2026
Signed off — Alteration
B01329193-I1
03/30/2026
Signed off — Alteration
FILING FOR INTERIOR RENOVATION OF EXIST 2 STORY & CELLAR TWO FAMILY DWELLING. NEW PARTITION WALLS, FINISH FLOORING, NEW INTERIOR DOORS, NEW TILES AND NEW PLUMBING FIXTURES AS PER PLANS. REMOVE ILLEGAL APT IN CELLAR. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B01269044-S1
02/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
AKM RAHMAN
02/13/2026
Special inspection requirement — HVAC-R and service water heating system controls
AKM RAHMAN
02/13/2026
Special inspection requirement — Maintenance information
AKM RAHMAN
79 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offBrothers Construction Group12/26/2025
DOB NOWPlumbingSigned-offM & M Piping and Heating10/09/2025
1 project · most recent 02/11/2026
Gas Water/Sanitary
FiledStatusContractorScope
02/11/2026Signed-offM & M Piping and HeatingGas, Water/Sanitary
1 project · most recent 05/26/2026
General Wiring
FiledStatusContractorScope
05/26/2026CompleteKepler Electrical ContGeneral Wiring
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
10/17/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
10/17/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/17/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
10/15/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 26
DateRequirementInspectorRole
02/13/2026Fire-Resistant Penetrations and JointsAKM RAHMANspecial
02/13/2026HVAC-R and service water heating system controlsAKM RAHMANenergy_progress
02/13/2026Maintenance informationAKM RAHMANenergy_progress
02/13/2026HVAC-R and service water heating equipmentAKM RAHMANenergy_progress
02/13/2026HVAC-R and service water piping design and insulationAKM RAHMANenergy_progress
02/13/2026Energy Code Compliance InspectionsAKM RAHMANprogress
12/04/2025Fenestration and door U-factor and product ratingsAKM RAHMANenergy_progress
12/04/2025Fire-Resistant Penetrations and JointsAKM RAHMANspecial
12/04/2025FinalAKM RAHMANprogress
12/04/2025Energy Code Compliance InspectionsAKM RAHMANprogress
12/04/2025Fire-Resistance Rated ConstructionAKM RAHMANprogress
12/04/2025Air barrier - visual inspectionAKM RAHMANenergy_progress
12/04/2025Insulation placement and R valuesAKM RAHMANenergy_progress
12/04/2025Fenestration air leakageAKM RAHMANenergy_progress
12/04/2025Interior lighting powerAKM RAHMANenergy_progress
12/04/2025Fenestration areasAKM RAHMANenergy_progress
10/09/2025Final—progress
08/10/2025Fenestration and door U-factor and product ratings—energy_progress
08/10/2025Insulation placement and R values—energy_progress
08/10/2025Interior lighting power—energy_progress
08/10/2025Fenestration areas—energy_progress
08/10/2025Fenestration air leakage—energy_progress
08/10/2025Air barrier - visual inspection—energy_progress
08/10/2025Fire-Resistance Rated Construction—progress
08/10/2025Fire-Resistant Penetrations and Joints—special