| Firm | Filings | Most Recent |
|---|---|---|
| FAIRFIELD TESTING LABORATORY | 1 | 07/25/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN POWER SOLUTIONS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FINALE CONCRETE CORP | General Contractor | 3 | 03/21/2026 |
| ALEXANDER BERNARDI | Electrical | 1 | 03/21/2026 |
| HIMELFARB, LEONARD | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FAIRFIELD TESTING LABORAT | 3404 | 1 | 07/25/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | FINALE CONCRETE CORP | 09/19/2025 |
| BIS | OT | ISSUED | GT DEVELOPMENT ENTERPRISE | 10/02/2014 |
| BIS | FS | ISSUED | JACK PICCINI, INC | 07/06/2007 |
| BIS | — | ISSUED | TWIN CONTRACTORS INC | 09/27/2006 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/12/2025 | Complete | BERNARDI ELECTRIC INC. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/25/2025 | Permit Issued | FINALE CONCRETE CORP | 254 panels, 123.19 kw, 12,177 roof_area_sqft |