← Back
Elevator apt, miscellaneous
535 WEST 112 STREET
MANHATTAN · Morningside Heights · BIN 1056991
💬 Discuss this project
1906Year Built
6Stories
D9Building Class
R8Zoning
11,433 sfGross Floor Area
12Units
Rent Stabilized21 Open Violations ▸FISP: SWARMP
Elevator apt, miscellaneous · Owner of record: TRUSTEES OF COLUMBIA UNIVERSITY · 2,523 sf lot · 4.53 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TRIERA CONTRACTING607/08/2026
CEPRINE CONSTRUCTION1003/22/2026
COLUMBIA UNIVERSITY303/21/2026
ROCK GROUP NY CORP103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
KZ ENGINEERING, P.C211/24/2021
ENTHINK ENGINEERS LLC210/13/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
SYNERGY BUILDING CONSULTANTS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CEPRINE CONSTRUCTION INCGeneral Contractor603/21/2026
DIFUSCO, ALFONSOElectrical203/21/2026
DUNN, JEREMYElectrical203/21/2026
CRUGNALE, MICHAELElectrical203/21/2026
BOROWIDE ELECT'L CONTR'SElectrical103/22/2026
TRIERA CONTRACTING INCGeneral Contractor107/08/2026
GREGORY PAPANTONIOUElectrical103/21/2026
NEW AGE ELEC'L CONTRG INCElectrical103/22/2026
NIKOLL DUSHIElectrical103/21/2026
Building Lifecycle
All (72)Filed (4)Permit Issued (4)Signed Off (4)Facade (FISP) (12)Violation (44)Special Inspection (4)
04/01/2024
Violation issued (HPD, closed)
A
11/15/2023
Violation issued (HPD, closed)
I
11/15/2022
Cycle 9 facade report signed — SWARMP
11/02/2022
Violation issued (HPD, closed)
I
09/28/2022
Signed off — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M00611236-I1
09/28/2022
Signed off — Alteration
M00611277-I1
08/16/2022
Cycle 9 facade report submitted
06/21/2022
Signed off — Alteration
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00633891-I1
06/21/2022
Signed off — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00633898-I1
06/18/2022
Cycle 9 facade inspection completed
02/22/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/16/2022
Violation issued (HPD, closed)
A
11/26/2021
Permit issued — Sidewalk Shed
M00633891-I1-SH
11/26/2021
Permit issued — Supported Scaffold
M00633898-I1-SF
11/24/2021
Filed — Alteration
Installation of temporary sidewalk shed per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00633891-I1
11/24/2021
Filed — Alteration
Installation of temporary supported scaffold per plan submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M00633898-I1
11/18/2021
Special inspection requirement — Final
Karol Zdancewicz
11/18/2021
Special inspection requirement — Final
Karol Zdancewicz
10/14/2021
Permit issued — Sidewalk Shed
M00611236-I1-SH
10/14/2021
Permit issued — Supported Scaffold
M00611277-I1-SF
10/13/2021
Filed — Alteration
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. LIVE LOAD 300PSF.
M00611236-I1
10/13/2021
Filed — Alteration
M00611277-I1
10/13/2021
Special inspection requirement — Final
Sunil Saigal
10/13/2021
Special inspection requirement — Final
Sunil Saigal
04/02/2021
Violation issued (HPD, closed)
A
10/17/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
05/09/2016
Cycle 8 facade report submitted
04/29/2016
Cycle 8 facade report signed — SWARMP
04/21/2016
Cycle 8 facade inspection completed
02/03/2015
Violation issued (HPD, closed)
I
03/31/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/14/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
08/30/2011
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
05/25/2011
Cycle 7 facade report submitted
05/20/2011
Cycle 7 facade report signed — SWARMP
05/04/2011
Cycle 7 facade inspection completed
04/13/2010
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
02/27/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/26/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
02/06/2007
Cycle 6 facade report submitted
01/08/2007
Cycle 6 facade report signed — SAFE
12/08/2005
Cycle 6 facade inspection completed
11/05/2004
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
03/19/2003
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/10/1997
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/29/1995
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/18/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/23/1992
Violation issued (ECB, closed)
Elevators
11/23/1992
Violation issued (DOB, closed)
VPW*-VIOLATION UNSERVED ECB-WORK WITHOUT PERMIT-DISMISSED
11/27/1989
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/27/1989
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
12/08/1987
Violation issued (HPD, open)
B
12/08/1987
Violation issued (HPD, open)
B
12/08/1987
Violation issued (HPD, open)
B
12/08/1987
Violation issued (HPD, open)
B
12/08/1987
Violation issued (HPD, open)
B
12/08/1987
Violation issued (HPD, open)
B
12/08/1987
Violation issued (HPD, open)
B
12/08/1987
Violation issued (HPD, open)
B
12/08/1987
Violation issued (HPD, open)
B
Latest 60 of 72 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedSigned-offCEPRINE CONSTRUCTION INC11/26/2021
DOB NOWSupported ScaffoldSigned-offCEPRINE CONSTRUCTION INC11/26/2021
DOB NOWSidewalk ShedSigned-offTRIERA CONTRACTING INC10/14/2021
DOB NOWSupported ScaffoldSigned-offTRIERA CONTRACTING INC10/14/2021
BISOTISSUEDHENRY RESTORATION LTD12/03/2021
BISOTISSUEDHENRY RESTORATION LTD10/13/2021
BISOTISSUEDHENRY RESTORATION LTD11/24/2020
BISOTISSUEDKAY WATERPROOFING CORP08/06/2015
BISEQISSUEDROCK GROUP NY CORP06/12/2015
BISOTISSUEDC C CONTROLLED COMBUSTION09/25/2014
BISOTISSUEDHENRY RESTORATION LTD10/10/2013
BISEQISSUEDEVEREST SCAFFOLDING INC07/30/2013
BISFBISSUEDPAT SEMENTA PLBG&HTG CO.I11/02/2007
2 projects · most recent 09/17/2024
FiledStatusContractorScope
09/17/2024Permit IssuedNEW AGE ELEC'L CONTRG INC1 meters
12/07/2021CompleteBOROWIDE ELECT'L CONTR'S—
▾Special Inspection Requirements (DOB NOW) — 4
DateRequirementInspectorRole
11/18/2021FinalKarol Zdancewiczprogress
11/18/2021FinalKarol Zdancewiczprogress
10/13/2021FinalSunil Saigalprogress
10/13/2021FinalSunil Saigalprogress
▾Documents — 125 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/03/2026M00611236-I1Request digital key ↗
09/03/2026M00611277-I1Request digital key ↗
09/03/2026M00633891-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits17
▸BISPLAN / WORK APPROVAL APPLICATION10
04/27/2023140927308Open ↗
03/17/2023140927308Open ↗
02/24/2023140927308Open ↗
Showing 3 of 10 on file for this type
▸BISWORK PERMIT APPLICATION7
11/24/2020140927308Open ↗
08/27/2015122413968Open ↗
07/07/2015122440698Open ↗
Showing 3 of 7 on file for this type
▸Seals & Professional Certifications33
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION11
03/22/2016122413968Open ↗
03/22/2016122413968Open ↗
03/02/2016122440698Open ↗
Showing 3 of 11 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT4
10/08/2020140927308Open ↗
06/23/2015122440698Open ↗
09/12/2014122127180Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST4
06/23/2015122440698Open ↗
06/05/2015122413968Open ↗
09/12/2014122127180Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/03/2026M00611277-I1Open ↗
09/03/2026M00633898-I1Open ↗
08/13/2026M00633891-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/02/2026M00611236-I1Open ↗
08/28/2026M00611277-I1Open ↗
08/25/2026M00633891-I1Open ↗
Showing 3 of 4 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
10/08/2020140927308Open ↗
07/30/2013140101084Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
10/08/2020140927308Open ↗
07/30/2013140101084Open ↗
▸BISProfessional and Owner Certification (POC3)1
06/05/2015122413968Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
05/23/2013121627212Open ↗
▸Safety & Tenant Protection11
▸BISSRO MD ANTI-HARASSMENT CHECKLIST5
10/08/2020140927308Open ↗
06/29/2015122440698Open ↗
07/30/2013140101084Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHPD-3: Single Room Occupancy Multiple Dwelling (SRO MD) Anti-Harassment Checklist4
09/03/2026M00611277-I1Open ↗
09/03/2026M00633898-I1Open ↗
08/13/2026M00611236-I1Open ↗
Showing 3 of 4 on file for this type
▸BISHPD: SRO MD CERTIFICATE OF NO HARASSMENT1
06/10/2015122413968Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
10/08/2020140927308Open ↗
▸Environmental & Asbestos5
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
10/08/2020140927308Open ↗
09/12/2014122127180Open ↗
05/23/2013121627212Open ↗
Showing 3 of 4 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
08/27/2015122413968Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
03/22/2016122413968Open ↗
03/22/2016122413968Open ↗
07/07/2015122127180Open ↗
Showing 3 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
03/22/2016122413968Open ↗
07/07/2015122127180Open ↗
01/08/2014121627212Open ↗
▸BISTR8: Energy Code Progress Inspections2
09/12/2014122127180Open ↗
01/08/2014121627212Open ↗
▸BISNYCECC ANALYSIS1
10/08/2020140927308Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
07/30/2013140101084Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
10/08/2020140927308Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
04/28/2023140927308Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: RESPONSIBILITY3
04/28/2023140927308Open ↗
04/18/2023140927308Open ↗
07/30/2013140101084Open ↗
▸BISDIR-14 ID OF RESPONSIBILITY (TR1)1
11/24/2020140927308Open ↗
▸Approvals, Objections & Sign-offs11
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST6
05/03/2023140927308Open ↗
04/01/2016122413968Open ↗
03/02/2016122440698Open ↗
Showing 3 of 6 on file for this type
▸BISADMINISTRATIVE OBJECTIONS2
05/23/2013121627212Open ↗
06/01/2012121089543Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
09/03/2026M00611277-I1Open ↗
08/13/2026M00611236-I1Open ↗
▸BISFINAL1
04/28/2023140927308Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT8
10/08/2020140927308Open ↗
04/01/2016122413968Open ↗
07/07/2015122127180Open ↗
Showing 3 of 8 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
04/28/2023140927308Open ↗
▸Filing & Intake Forms11
▸BISEFILING COVER SHEET5
06/23/2015122440698Open ↗
06/05/2015122413968Open ↗
09/12/2014122127180Open ↗
Showing 3 of 5 on file for this type
▸BISADDITIONAL INFORMATION3
04/27/2023140927308Open ↗
07/24/2015122413968Open ↗
12/02/2014122127180Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET2
10/08/2020140927308Open ↗
07/30/2013140101084Open ↗
▸BISHPD-3 - SRO MD ANTI-HARASSEMENT CHECKLIST1
09/29/2014122127180Open ↗
▸Other Documents5
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION2
07/30/2013140101084Open ↗
07/30/2013140101084Open ↗
▸BISFEE EXEMPTION DOCUMENTATION1
07/30/2013140101084Open ↗
▸BISSupporting Document: Fee Exempt1
09/11/2014122127180Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
06/11/2015122413968Open ↗