| Owner | Filings | Most Recent |
|---|---|---|
| HOSPITAL FOR SPECIAL SURGERY | 80 | 09/12/2026 |
| TISHMAN CONSTRUCTION | 2 | 03/22/2026 |
| EAST COAST PETROLEUM | 1 | 03/22/2026 |
| HOSPITAL FOR SPECIAL S | 2 | 03/22/2026 |
| HOSPITAL OF SPECIAL SURGERY | 1 | 03/22/2026 |
| HHS | 1 | 03/22/2026 |
| SPECIALTY MGMT.CO.,INC | 2 | 03/21/2026 |
| HOSPITAL F | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PLATFORM SOLUTIONS INC | 2 | 01/07/2026 |
| PCS ENGINEERING | 7 | 07/21/2025 |
| PLAN B ENGINEERING | 28 | 06/20/2025 |
| LOMBARDO PROFESSIONAL ENGINEERING | 5 | 03/20/2025 |
| ALLEN DIALBERTO PE | 2 | 07/08/2024 |
| ASHRAF CORP | 5 | 09/08/2022 |
| MPS ENGINEERING PLLC | 1 | 06/07/2022 |
| JAROS BAUM & BOLLES | 1 | 02/04/2022 |
| EWINGCOLE | 3 | 11/23/2021 |
| AECOM USA, INC. | 1 | 10/12/2021 |
| KEMS ENGINEERING AND CONSTRUCTION | 1 | 06/25/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| EUROCELT EXPEDITING, INC | 60 | 03/21/2026 |
| LOMBARDO BUILDING CONSULTANTS | 10 | 03/21/2026 |
| RIGGING CONSULTANTS | 10 | 03/21/2026 |
| KD DESIGNS | 5 | 03/21/2026 |
| MUNICIPAL EXPEDITING | 10 | 03/21/2026 |
| LEWSAN CONSULTING | 2 | 03/21/2026 |
| MARTELL SOLUTIONS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PLATFORM SOLUTIONS, INC | General Contractor | 79 | 07/14/2026 |
| TISHMAN CONSTRUCTION CORP | General Contractor | 7 | 07/08/2026 |
| CUSTOM METALCRAFTERS INC | General Contractor | 6 | 07/08/2026 |
| PACE PLUMBING CORP | Fire Protection | 4 | 07/08/2026 |
| PEAK FIRE PROTECTION LLC | Fire Protection | 4 | 07/08/2026 |
| GREG LOGISTICS LLC | General Contractor | 3 | 07/08/2026 |
| NORTH SHORE NEON SIGN | Scaffold | 2 | 07/08/2026 |
| DEPENDABLE MECHANICAL COR | Fire Protection | 2 | 07/08/2026 |
| DHS FRACO LLC | General Contractor | 2 | 07/08/2026 |
| ALLAN BRITEWAY ELECTRICAL | Electrical | 2 | 03/22/2026 |
| DUFFY, STEVEN | Electrical | 1 | 03/21/2026 |
| CITY ELEC'L SIGN ERECTORS | Electrical | 1 | 03/22/2026 |
| STEVEN DUFFY | Electrical | 1 | 03/21/2026 |
| ANTHONY D'ANNA | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PCS ENGINEERING | 3745 | 7 | 07/21/2025 |
| FUTURE TECH CONSULTANTS O | 589 | 3 | 06/07/2022 |
| GREGORY V. PEROTTO, P.E. | 947 | 1 | 06/25/2020 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Suspended Scaffold | Permit Issued | CUSTOM METAL CRAFTERS INC | 09/10/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | PLATFORM SOLUTIONS, INC | 07/13/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 07/02/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | PLATFORM SOLUTIONS, INC | 06/17/2026 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 06/03/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | PLATFORM SOLUTIONS, INC | 04/20/2026 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATFORM SOLUTIONS, INC | 04/20/2026 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 04/20/2026 |
| DOB NOW | Construction Fence | Permit Issued | PLATFORM SOLUTIONS, INC | 03/16/2026 |
| DOB NOW | Standpipe | Permit Issued | DEPENDABLE MECHANICAL COR | 01/27/2026 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 01/07/2026 |
| DOB NOW | Standpipe | Permit Issued | DEPENDABLE MECHANICAL COR | 11/17/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 09/03/2025 |
| DOB NOW | Boiler Equipment | Signed-off | EAST COAST PETROLEUM INC | 07/23/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 07/17/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | PLATFORM SOLUTIONS, INC | 06/23/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 06/04/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | CUSTOM METALCRAFTERS INC | 06/03/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | CUSTOM METAL CRAFTERS INC | 05/22/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | PLATFORM SOLUTIONS, INC | 04/28/2025 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 04/25/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | PLATFORM SOLUTIONS, INC | 04/21/2025 |
| DOB NOW | Construction Fence | Permit Issued | PLATFORM SOLUTIONS, INC | 04/04/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 03/26/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 03/11/2025 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | CUSTOM METALCRAFTERS INC | 03/05/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 02/21/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | PLATFORM SOLUTIONS, INC | 02/19/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 02/18/2025 |
| DOB NOW | Standpipe | Permit Issued | MANENGEERING BUREAU, INC | 12/19/2024 |
| DOB NOW | Standpipe | Permit Issued | MANENGEERING BUREAU, INC | 12/19/2024 |
| DOB NOW | Construction Fence | Permit Issued | TISHMAN CONSTRUCTION CORP | 10/09/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 10/03/2024 |
| DOB NOW | Suspended Scaffold | Signed-off | GREG LOGISTICS LLC | 09/27/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | PLATFORM SOLUTIONS, INC | 09/23/2024 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 09/06/2024 |
| DOB NOW | Supported Scaffold | Signed-off | PLATFORM SOLUTIONS, INC | 07/29/2024 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | CUSTOM METALCRAFTERS INC | 05/29/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | CUSTOM METAL CRAFTERS INC | 05/28/2024 |
| DOB NOW | Sign | Permit Issued | NORTH SHORE NEON SIGN CO | 05/16/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/04/2022 | Permit Issued | A&H EXPRESS PLBG&HTG CORP | 4 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/16/2026 | Permit Issued | ALLAN BRITEWAY ELECTRICAL | General Wiring |
| 04/30/2025 | Complete | CITY ELEC'L SIGN ERECTORS | — |
| 01/29/2025 | Complete | ALLAN BRITEWAY ELECTRICAL | — |
| 01/29/2025 | Complete | ALLAN BRITEWAY ELECTRICAL | — |
| 01/29/2025 | Pending Payment | ALLAN BRITEWAY ELECTRICAL | — |
| 01/28/2025 | Permit Issued | ALLAN BRITEWAY ELECTRICAL | General Wiring |
| 02/16/2024 | Complete | PM ELEC'L MAINTENANCE INC | — |
| 02/16/2024 | Complete | PM ELEC'L MAINTENANCE INC | General Wiring |
| 02/13/2024 | Complete | PM ELEC'L MAINTENANCE INC | General Wiring |
| 01/31/2024 | Permit Issued | ALLAN/BRITE-WAY ELEC'L CO | — |
| 04/18/2023 | Permit Issued | ALLAN/BRITE-WAY ELEC'L CO | — |
| 04/18/2023 | Permit Issued | ALLAN/BRITE-WAY ELEC'L CO | — |
| 04/05/2023 | Permit Issued | ALLAN/BRITE-WAY ELEC'L CO | General Wiring |
| 06/29/2022 | Permit Issued | RIGID ELECTRIC, INC. | General Wiring |
| 06/29/2022 | Complete | RIGID ELECTRIC, INC. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/07/2026 | Signed-off | PLATFORM SOLUTIONS, INC | Scaffold |
| 06/04/2025 | Signed-off | PLATFORM SOLUTIONS, INC | Scaffold |
| 05/10/2024 | Signed-off | PLATFORM SOLUTIONS, INC | Scaffold |
| 05/09/2024 | Signed-off | PLATFORM SOLUTIONS, INC | Sidewalk Shed |
| 11/17/2023 | Signed-off | PLATFORM SOLUTIONS, INC | Scaffold |
| 11/17/2023 | Permit Issued | PLATFORM SOLUTIONS, INC | Sidewalk Shed |
| 11/23/2021 | Permit Issued | NORTH SHORE NEON SIGN LLC | Sign |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/11/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/11/2026 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 04/27/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/13/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 03/24/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 03/19/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/05/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/02/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/23/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (100 Foot Increments) | Certified | View ↗ |
| 01/23/2026 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| 01/23/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/01/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 11/11/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/11/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/25/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 07/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 07/17/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 03/12/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/28/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/22/2023 | Certified StandPipe - SD - Alarm Sys 64/09 - Finish | Certified | View ↗ |
| 12/22/2023 | Certified StandPipe - SD - Hydrostatic 63/09 Test (Initial 75 Feet) | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/21/2025 | Post-installed Anchors | Michael Walsh | special |
| 07/08/2025 | Post-installed Anchors | Michael Walsh | special |
| 06/03/2025 | Post-installed Anchors | Michael Walsh | special |
| 09/24/2024 | Post-installed Anchors | Michael Walsh | special |
| 07/17/2024 | Post-installed Anchors | Michael Walsh | special |
| 03/15/2022 | Standpipe Systems | MARISA HARTE | special |
| 10/12/2021 | Final | MARISA HARTE | progress |
| 10/12/2021 | Final | MARISA HARTE | progress |
| 09/28/2021 | Post-installed Anchors | MARISA HARTE | special |
| 09/28/2021 | Concrete - Cast-In-Place | MARISA HARTE | special |
| 09/28/2021 | Structural Cold-Formed Steel | MARISA HARTE | special |
| 09/08/2021 | Final | MOSTAFA ELMORSI | progress |
| 09/08/2021 | Structural Stability – Alterations of existing buildings | MARISA HARTE | special |
| 09/08/2021 | Structural Steel - Details | MARISA HARTE | special |
| 09/08/2021 | Structural Steel - High Strength Bolting | MARISA HARTE | special |
| 09/08/2021 | Structural Steel - Welding | MARISA HARTE | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Hospital for Special Surgery | Medical / Healthcare | Floor 2 | Project M01050067 Project M00699296 Project M00589906 |