| Owner | Filings | Most Recent |
|---|---|---|
| OWNERS REP | 11 | 09/15/2026 |
| B CONTRACTORS GROUP | 1 | 03/22/2026 |
| 5408-14 MYRTLE AVENUE | 5 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KAO HWA LEE ARCHITECTS PC | 8 | 08/24/2026 |
| SOUTH BAY ENGINEERING PLLC | 2 | 02/11/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| BUILDINGS REPRISENTATIVE LLC | 2 | 03/21/2026 |
| ADVANCED BUILDERS SERVICES | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| N TECH DESIGN OF AMERICA | General Contractor | 2 | 07/31/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SOUTH BAY ENGINEERING PLL | 6682 | 1 | 12/26/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Full Demolition | Permit Issued | N TECH DESIGN OF AMERICA | 07/30/2026 |
| DOB NOW | Construction Fence | Permit Issued | N TECH DESIGN OF AMERICA | 02/12/2026 |
| BIS | OT | ISSUED | YOUN DESIGN CORP | 01/14/2019 |
| BIS | EQ | ISSUED | S&E BRIDGE & SCAFFOLD LLC. | 05/19/2015 |
| BIS | EQ | ISSUED | S&E BRIDGE & SCAFFOLD LLC. | 07/05/2013 |
| BIS | EQ | ISSUED | S&E BRIDGE & SCAFFOLD LLC. | 03/26/2013 |
| BIS | EQ | ISSUED | S&E BRIDGE & SCAFFOLD LLC. | 03/19/2012 |
| BIS | EQ | ISSUED | S&E BRIDGE & SCAFFOLD LLC. | 02/24/2012 |
| BIS | EQ | ISSUED | PERIMETER BRIDGE & SCAFFO | 03/17/2011 |
| BIS | EQ | ISSUED | PERIMETER BRIDGE & SCAFFO | 07/26/2010 |
| BIS | EQ | RE-ISSUED | AMBROSINO CONSTRUCTION | 06/03/1993 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/24/2026 | — | — | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/15/2025 | Permit Issued | HIVOLTS ELECTRICAL INC | General Wiring |
| 12/15/2025 | Permit Issued | HIVOLTS ELECTRICAL INC | General Wiring |
| 12/15/2025 | Permit Issued | HIVOLTS ELECTRICAL INC | General Wiring |
| 11/21/2019 | Complete | WILLDAN ELECTRICAL OF NY | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/12/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/20/2026 | Post-installed Anchors | — | special |
| 08/20/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 08/20/2026 | Subgrade Inspections | — | special |
| 08/20/2026 | Structural Steel - Welding | — | special |
| 08/20/2026 | Concrete - Cast-In-Place | — | special |
| 08/20/2026 | Subgrade Inspections | — | special |
| 08/20/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 08/20/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 08/20/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 08/20/2026 | Structural Steel - Details | — | special |
| 08/06/2026 | Post-installed Anchors | — | special |
| 08/06/2026 | Sprinkler Systems | — | special |
| 08/06/2026 | Standpipe Systems | — | special |
| 08/06/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 04/22/2026 | Final | — | progress |
| 04/22/2026 | Footing and Foundation | — | progress |
| 03/29/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/29/2026 | Mechanical Systems | — | special |
| 03/29/2026 | Final | — | progress |
| 03/29/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 03/29/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 03/29/2026 | Shutoff dampers | — | energy_progress |
| 12/24/2025 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 12/24/2025 | Fire-Resistance Rated Construction | — | progress |
| 12/24/2025 | Energy Code Compliance Inspections | — | progress |