← Back
Elevator apt, semi-fireproof without stores
54-09 100 STREET
QUEENS · Corona · BIN 4449601
💬 Discuss this project
1989Year Built
8Stories
D1Building Class
R6Zoning
266,316 sfGross Floor Area
296Units
LL97 CoveredRent Stabilized45 Open Violations 44 unresolved · 1 paperwork only ▸FISP: SWARMPFDNY Report ↗
Elevator apt, semi-fireproof without stores · Owner of record: QUEENSWOOD HOUSING DEVELOPMENT FUND CORP ORATION · 127,000 sf lot · 2.1 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingLandscape
Roof5p · 7 filings · 20 docs
Floor 141p · 1 filing · 10 docs
Floor 131p · 1 filing · 10 docs
Floor 12
Floor 11
Floor 10
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 21p · 1 filing · 7 docs
Floor 11p · 1 filing · 7 docs
Cellar1p · 1 filing · 10 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
MGT PROPERTY MANAGEMENT507/08/2026
QUEENSWOOD OWNER LLC603/22/2026
DISH303/22/2026
FOREST CITY MASTER ASSOC103/22/2026
QUEENSWOOD APARTMENTS403/22/2026
QUEENSWOOD ASSOCIATES1303/21/2026
FOREST CITY RESIDENTIAL MGMT403/21/2026
SD BUILDERS AND CONSTRUCTION LLC203/21/2026
T-MOBILE103/21/2026
FOREST CITY RESIDENTIAL GROUP203/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/29/2023$39.0M—— → —$146/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AUFGANG ARCHITECTS109/03/2025
SQUARE ARCH, LLC102/07/2025
ASHRAF CORP209/25/2024
KMB DESIGN GROUP, LLC401/26/2023
GT WIRELESS ENGINEERING, PLLC107/21/2022
ARCNET ARCHITECTS INC.108/23/2019
NB&C101/30/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KAMTECH RESTORATION CORP203/21/2026
KD DESIGNS203/21/2026
CCM CONSULTING GROUP, INC.603/21/2026
CONSTRUCTION PERMIT SERVICES203/21/2026
JM ZONING, LLC.103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
E.T. VANDERBECK INCGeneral Contractor407/08/2026
OVERLAND CONTRACTING INCGeneral Contractor303/21/2026
ALLIED TELECOM CORPGeneral Contractor303/21/2026
ARSENAL SCAFFOLD INCGeneral Contractor307/08/2026
PRIORE CONSTRUCTION SVCSGeneral Contractor203/21/2026
KAMTECH RESTORATION CORPGeneral Contractor203/21/2026
HUDSON PLMBING & MCH, LLCPlumbing107/08/2026
LLESHAJ, MARIOElectrical103/21/2026
ANTHONY COSTANZOElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SQ. ARCH, LLC4802102/07/2025
KMB DESIGN GROUP, LLC513301/26/2023
R MARSAC CONSULTING LLC329107/21/2022
BURTNER ENGINEERING SERVI5910101/30/2018
Building Lifecycle
All (144)Filed (11)Permit Issued (9)Signed Off (9)Facade (FISP) (12)Violation (60)Inspection (3)Objection (19)Special Inspection (21)
01/26/2026
Violation issued (HPD, closed)
C
01/26/2026
Violation issued (HPD, closed)
C
01/26/2026
Violation issued (HPD, closed)
B
01/26/2026
Violation issued (HPD, closed)
B
12/09/2025
Violation issued (HPD, closed)
B
09/29/2025
Objection raised — Other
09/03/2025
Filed — New Building
Application filed to erect new fourteen (14) story residential new building as per plans filed.
Q01228195-I1
09/03/2025
Violation issued (HPD, open)
B
09/03/2025
Violation issued (HPD, open)
C
08/30/2025
Violation issued (HPD, closed)
B
08/30/2025
Violation issued (HPD, closed)
C
08/30/2025
Violation issued (HPD, closed)
B
08/30/2025
Violation issued (HPD, closed)
A
08/12/2025
Violation issued (HPD, closed)
A
08/12/2025
Violation issued (HPD, closed)
B
08/07/2025
Violation issued (HPD, closed)
C
08/07/2025
Violation issued (HPD, closed)
A
07/29/2025
Special inspection requirement — Fenestration air leakage
07/29/2025
Special inspection requirement — Air barrier continuity plan testing
07/29/2025
Special inspection requirement — Fenestration areas
07/29/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
07/29/2025
Special inspection requirement — Vestibules
07/29/2025
Special inspection requirement — Insulation placement and R values
07/29/2025
Special inspection requirement — Protection of exposed foundation insulation
07/29/2025
Special inspection requirement — Air barrier - visual inspection
07/15/2025
Signed off — Alteration
ROOFTOP SOLAR INSTALLATION. NO CHANGE TO USE, OCCUPANCY OR EGRESS.
Q01178254-I1
07/09/2025
Violation issued (HPD, open)
B
06/12/2025
Violation issued (HPD, closed)
A
06/10/2025
Violation issued (HPD, closed)
C
06/09/2025
Violation issued (HPD, open)
C
05/23/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
05/23/2025
Special inspection requirement — Concrete - Cast-In-Place
05/23/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
05/23/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
05/23/2025
Special inspection requirement — Post-installed Anchors
05/23/2025
Special inspection requirement — Energy Code Compliance Inspections
05/23/2025
Special inspection requirement — Fire-Resistance Rated Construction
05/13/2025
Permit issued — Solar
Q01178254-I1-SL
05/11/2025
Violation issued (HPD, closed)
C
05/11/2025
Violation issued (HPD, closed)
B
05/11/2025
Violation issued (HPD, closed)
C
04/28/2025
Objection resolved — Addressed
04/24/2025
Violation issued (HPD, closed)
C
04/24/2025
Violation issued (HPD, closed)
B
04/24/2025
Violation issued (HPD, closed)
A
04/24/2025
Violation issued (HPD, closed)
C
04/24/2025
Violation issued (HPD, closed)
C
04/24/2025
Violation issued (HPD, closed)
A
04/24/2025
Violation issued (HPD, closed)
C
04/24/2025
Violation issued (HPD, closed)
C
04/24/2025
Violation issued (HPD, closed)
A
04/24/2025
Violation issued (HPD, closed)
A
04/16/2025
Violation issued (HPD, closed)
C
04/16/2025
Violation issued (HPD, closed)
A
04/16/2025
Violation issued (HPD, closed)
C
03/21/2025
Objection resolved — Addressed
03/20/2025
Signed off — Alteration
INSTALLATION OF PIPE SCAFFOLDING REQUIRED FOR THE SUPPORT OF DEBRIS CHUTE AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE 2022 CODE. NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
Q01114082-I1
03/20/2025
Signed off — Alteration
Q01114191-I1
03/05/2025
Objection resolved — Addressed
02/27/2025
Objection resolved — Addressed
Latest 60 of 144 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offKAMTECH RESTORATION CORP05/13/2025
DOB NOWSupported ScaffoldSigned-offARSENAL SCAFFOLD INC09/26/2024
DOB NOWProtection and Mechanical MethodsSigned-offARSENAL SCAFFOLD INC09/26/2024
DOB NOWAntennaSigned-offPRIORE CONSTRUCTION SVCS09/16/2022
DOB NOWMechanical SystemsSigned-offE.T. VANDERBECK INC05/18/2022
DOB NOWAntennaSigned-offE.T. VANDERBECK INC05/16/2022
DOB NOWPlumbingSigned-offHUDSON PLMBING & MCH, LLC04/13/2022
DOB NOWAntennaSigned-offOVERLAND CONTRACTING INC12/13/2019
DOB NOWAntennaSigned-offALLIED TELECOM CORP02/06/2018
BISPLISSUEDCLOVERDALE MASTER P&H INC02/27/2017
BISOTISSUEDCHARLES M DWYER INC10/06/2015
BISOTISSUEDBECHTEL INFRASTRUCTURE AN08/03/2015
BISOTISSUEDMARREN MECHANICAL INC09/10/2014
BISPLISSUEDCLOVERDALE MASTER P&H INC09/10/2014
BISOTISSUEDWESTOWER COMMUNICATIONS I02/13/2013
BISOTISSUEDPREFERRED BUILDERS INC05/27/2011
BISOTISSUEDSQUAN CONSTRUCTION SERVIC03/07/2011
BISOTISSUEDODYSSIA GLOBAL COMM. CORP01/06/2009
BISOTISSUEDVANTAGE ASSOC09/19/2006
BISOTISSUEDCOSTA CONSTRUCTION CONSULTING &06/23/2005
BISOTISSUEDCOSTA CONSTRUCTION & CONSULTING03/29/2005
BISOTISSUEDCOSTA CONSTRUCTION & CONSULTING02/28/2005
BISOTISSUEDODYSSIA GLOBAL COMM. CORP02/28/2003
2 projects · most recent 02/04/2025
General Wiring
FiledStatusContractorScope
02/04/2025CompleteBERGER QUALITY ELEC'L CON—
02/06/2023Permit IssuedASSOCIATED ELEC CONT OF NGeneral Wiring
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
03/20/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
10/27/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
10/20/2022Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
07/29/2025Fenestration air leakage—energy_progress
07/29/2025Air barrier continuity plan testing—energy_progress
07/29/2025Fenestration areas—energy_progress
07/29/2025Fenestration and door U-factor and product ratings—energy_progress
07/29/2025Vestibules—energy_progress
07/29/2025Insulation placement and R values—energy_progress
07/29/2025Protection of exposed foundation insulation—energy_progress
07/29/2025Air barrier - visual inspection—energy_progress
05/23/2025Subsurface Investigations (Borings/Test Pits)—special
05/23/2025Concrete - Cast-In-Place—special
05/23/2025Exterior Insulation and Finish Systems (EIFS)—special
05/23/2025Fire-Resistant Penetrations and Joints—special
05/23/2025Post-installed Anchors—special
05/23/2025Energy Code Compliance Inspections—progress
05/23/2025Fire-Resistance Rated Construction—progress
02/07/2025Fire-Resistant Penetrations and JointsKaijin Liangspecial
02/07/2025Structural Stability – Alterations of existing buildingsKaijin Liangspecial
02/07/2025Energy Code Compliance InspectionsKaijin Liangprogress
02/07/2025FinalKaijin Liangprogress
02/07/2025Air barrier - visual inspectionKaijin Liangenergy_progress
12/14/2022Fire-Resistant Penetrations and JointsEkata Shahspecial
▾Documents — 145 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch10
08/29/2026Q00012471-I1Request digital key ↗
08/26/2026Q00587545-I1Request digital key ↗
08/26/2026Q00587555-I1Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Antenna1
08/28/2026Q00184612-I1Request digital key ↗
▸Applications & Permits23
▸BISPLAN / WORK APPROVAL APPLICATION12
04/12/2019440166106Open ↗
08/11/2015421196057Open ↗
06/25/2015421168382Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION11
03/06/2017440166106Open ↗
10/15/2015421196057Open ↗
08/11/2015421168382Open ↗
Showing 3 of 11 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01228195-I1Open ↗
▸Seals & Professional Certifications35
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION15
06/24/2019440166106Open ↗
12/04/2015421196057Open ↗
11/05/2015421168382Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/28/2026Q00184612-I1Open ↗
08/26/2026Q00587545-I1Open ↗
08/26/2026Q00587555-I1Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/31/2026Q01178254-I1Open ↗
08/31/2026Q01178254-I1Open ↗
08/31/2026Q01178254-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/31/2026Q01178254-I1Open ↗
08/31/2026Q01178254-I1Open ↗
08/25/2026Q00587555-P1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
09/03/2014440166106Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
09/03/2014440166106Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/03/2014440166106Open ↗
▸Trade Schedules & Equipment3
▸BISFA - FDNY APPROVAL : FD-FAA1
06/25/2015421168382Open ↗
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
09/03/2014440166106Open ↗
▸BISSCHEDULE B - PLUMBING1
09/03/2014440166106Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026Q01228195-I1Open ↗
▸Environmental & Asbestos16
▸DOB NOWDEP ACP-5: Asbestos Assessment Report7
08/28/2026Q00184612-I1Open ↗
08/26/2026Q00587545-I1Open ↗
08/26/2026Q00587555-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'5
02/28/2011420323368Open ↗
01/12/2011420314341Open ↗
12/24/2008410204381Open ↗
Showing 3 of 5 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)4
10/01/2015421196057Open ↗
06/25/2015421168382Open ↗
09/03/2014440166106Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance12
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS6
06/24/2019440166106Open ↗
12/04/2015421196057Open ↗
11/05/2015421168382Open ↗
Showing 3 of 6 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS3
02/11/2019440166106Open ↗
12/04/2015421196057Open ↗
11/05/2015421168382Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
09/03/2014440166106Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
09/03/2014440166106Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026Q00621554-I1Open ↗
▸Inspections & Test Reports1
▸BISTECHNICAL REPORT: RESPONSIBILITY1
09/03/2014440166106Open ↗
▸Approvals, Objections & Sign-offs19
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST7
07/18/2019440166106Open ↗
02/11/2019440166106Open ↗
12/04/2015421196057Open ↗
Showing 3 of 7 on file for this type
▸BISADMINISTRATIVE OBJECTIONS6
08/11/2015421196057Open ↗
06/25/2015421168382Open ↗
07/25/2012420579387Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION4
02/11/2019440166106Open ↗
01/06/2015420314341Open ↗
03/05/2013420579387Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter1
08/13/2026Q01228195-I1Open ↗
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01178254-I1Open ↗
▸Cost, Insurance & Ownership10
▸BISCOST AFFIDAVIT10
02/11/2019440166106Open ↗
12/04/2015421196057Open ↗
08/11/2015421196057Open ↗
Showing 3 of 10 on file for this type
▸Filing & Intake Forms8
▸BISADDITIONAL INFORMATION4
10/20/2015421196057Open ↗
12/04/2014440166106Open ↗
09/03/2013420579387Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET2
08/11/2015421196057Open ↗
06/25/2015421168382Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
09/03/2014440166106Open ↗
▸BISBOROUGH INTAKE FORM1
02/20/2019440166106Open ↗
▸Other Documents5
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026Q01228195-I1Open ↗
▸DOB NOWDHCR Document1
08/13/2026Q01228195-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/14/2026Q01228195-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q01228195-I1Open ↗
▸DOB NOWFinal Survey1