| Owner | Filings | Most Recent |
|---|---|---|
| 5421 ROOSEVELT | 54 | 08/29/2026 |
| CITISCAPE CONSULTING LTD | 14 | 08/26/2026 |
| 5421ROOSEVELTAVELLC | 4 | 07/08/2026 |
| MNK ENTERPRISES | 10 | 07/08/2026 |
| MOD CONSULTANTS | 3 | 03/22/2026 |
| L&L CONSTRUCTION DEVELOP | 1 | 03/22/2026 |
| DYNASTY CONTRACTING | 1 | 03/22/2026 |
| 54-21 ROOSEVELT AVE | 10 | 03/21/2026 |
| 39-54 56TH ST | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/23/2019 | $1.4M | — | 54-21 ROOSEVELT AVENUE, LLC → 5421 ROOSEVELT, LLC | — not available |
| 12/18/2015 | $780K | — | Private party → 54-21 ROOSEVELT AVE LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| DEFONSECA ARCHITECTS | 7 | 03/18/2026 |
| BITOPI CONSULTANTS LLC | 2 | 01/14/2026 |
| ASHRAF CORP | 1 | 12/24/2025 |
| AA BLDG & INSP SVC LLC | 10 | 09/04/2025 |
| BICALURO ASSOCIATES PC | 6 | 10/31/2024 |
| KZ ENGINEERING, P.C | 1 | 11/09/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| RP DEVELOPMENT GROUP | 32 | 03/21/2026 |
| CITISCAPE CONSULTING LTD | 8 | 03/21/2026 |
| SYNERGY BUILDING CONSULTANTS | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MOD CONSULTANTS LLC | General Contractor | 10 | 07/08/2026 |
| VIK MANAGEMENT CONSTRUCTI | General Contractor | 4 | 08/26/2026 |
| CS BRIDGE CORP | General Contractor | 3 | 07/08/2026 |
| MNK ENTERPRISES LLC | General Contractor | 3 | 07/08/2026 |
| TRI CITY MECHANICAL GROUP CORP | Plumbing | 1 | 07/02/2026 |
| M&D FIRE SPRINKLER INC | Fire Protection | 1 | 08/04/2026 |
| GREGG NY PLUMBING, INC | Plumbing | 1 | 08/05/2026 |
| JEM FIRE PREVENTION INC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| IP CONCRETE TESTING AND I | 6252 | 21 | 03/18/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | GREGG NY PLUMBING, INC | 08/04/2026 |
| DOB NOW | Sprinklers | Permit Issued | M&D FIRE SPRINKLER INC | 08/03/2026 |
| DOB NOW | General Construction | Permit Issued | VIK MANAGEMENT CONSTRUCTI | 07/13/2026 |
| DOB NOW | Structural | Permit Issued | VIK MANAGEMENT CONSTRUCTI | 07/09/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | VIK MANAGEMENT CONSTRUCTI | 06/29/2026 |
| DOB NOW | Construction Fence | Permit Issued | VIK MANAGEMENT CONSTRUCTI | 06/24/2026 |
| DOB NOW | Sprinklers | Permit Issued | JEM FIRE PREVENTION INC | 03/12/2026 |
| DOB NOW | Structural | Permit Issued | MOD CONSULTANTS LLC | 03/04/2026 |
| DOB NOW | Construction Fence | Permit Issued | MOD CONSULTANTS LLC | 03/04/2026 |
| DOB NOW | General Construction | Permit Issued | MOD CONSULTANTS LLC | 03/04/2026 |
| DOB NOW | Supported Scaffold | Signed-off | MNK ENTERPRISES LLC | 01/15/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | MNK ENTERPRISES LLC | 01/15/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | MNK ENTERPRISES LLC | 12/26/2025 |
| DOB NOW | Plumbing | Permit Issued | FLAVIO MECHANICAL CORP | 07/31/2025 |
| DOB NOW | General Construction | Permit Issued | MOD CONSULTANTS LLC | 06/04/2025 |
| DOB NOW | Foundation | Permit Issued | MOD CONSULTANTS LLC | 06/04/2025 |
| DOB NOW | Support of Excavation | Permit Issued | MOD CONSULTANTS LLC | 05/16/2025 |
| DOB NOW | Earth Work | Permit Issued | MOD CONSULTANTS LLC | 05/16/2025 |
| DOB NOW | Construction Fence | Permit Issued | MOD CONSULTANTS LLC | 11/19/2024 |
| DOB NOW | Supported Scaffold | Signed-off | CS BRIDGE CORP | 11/20/2017 |
| DOB NOW | Sidewalk Shed | Signed-off | CS BRIDGE CORP | 11/16/2017 |
| BIS | EQ | ISSUED | DYNASTY CONTRACTING LLC | 11/15/2018 |
| BIS | — | ISSUED | DYNASTY CONTRACTING LLC | 06/15/2018 |
| BIS | — | ISSUED | L&L CONSTRUCTION DEVELOP | 02/15/2018 |
| BIS | — | ISSUED | L&L CONSTRUCTION DEVELOP | 11/15/2017 |
| BIS | — | ISSUED | L&L CONSTRUCTION DEVELOP | 11/15/2017 |
| BIS | EQ | ISSUED | L&L CONSTRUCTION DEVELOP | 11/15/2017 |
| BIS | — | ISSUED | NY DRILLING INC | 01/23/2017 |
| BIS | EQ | ISSUED | NY DRILLING INC | 01/23/2017 |
| BIS | — | ISSUED | NY DRILLING INC | 01/23/2017 |
| BIS | — | ISSUED | VALUE PLUMBING INC | 07/10/2003 |
| BIS | PL | ISSUED | CATMAN PLUMBING INC | 07/10/2003 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/31/2024 | Permit Issued | VIK MANAGEMENT CONSTRUCTI | Air Conditioning Systems, Heating and Air Conditioning Systems | Cooling Mitsubishi Electric PKA-A12LA.TH 12,000 BTU · Vrf Indoor ×4 PUY-A12NKA7 12,000 BTU · Condensing Unit ×4 Heat / Cool Mitsubishi Electric MSZ-FS09NA-U1 8,000 BTU · Fan Coil Indoor ×4 MSZ-FS12NA-U1 12,000 BTU · Split System ×4 MSZ-GS06NA-U1 24,000 BTU · Split System ×4 MSZ-GS12NA-U1 10,700 BTU · Fan Coil Indoor ×4 MUZ-FS12NA-U1 12,000 BTU · Condensing Unit ×4 MXZ-3C24NAHZ4-U1 22,000 BTU · Condensing Unit ×4 PEAD-A-42AA9 42,000 BTU · Vrf Indoor ×2 PEAD-A24AA9 24,000 BTU · Vrf Indoor ×2 PLA-A12EA7R1.TH 12,000 BTU · Vrf Indoor ×2 PURY-P72NU-A 72,000 BTU · Vrf Outdoor ×2 PUZ-A12NKA7 12,000 BTU · Condensing Unit ×2 PUZ-HA24NHA1 24,000 BTU · Vrf Outdoor ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/31/2024 | Permit Issued | M&D FIRE SPRINKLER INC | 200 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/31/2024 | Permit Issued | GREGG NY PLUMBING, INC | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Permit Issued | LENS ELECTRIC, INC | General Wiring |
| 12/26/2025 | Permit Issued | RICHARD NEU | — |
| 06/18/2025 | Permit Issued | K.A.B. ELECTRIC CORP | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/04/2025 | Permit Issued | MOD CONSULTANTS LLC | 5 scope_items |
| 09/04/2025 | Permit Issued | MOD CONSULTANTS LLC | 2 scope_items |
| 07/16/2024 | Permit Issued | VIK MANAGEMENT CONSTRUCTI | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/14/2026 | Signed-off | MNK ENTERPRISES LLC | Scaffold |
| 05/03/2024 | Permit Issued | VIK MANAGEMENT CONSTRUCTI | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/04/2025 | Permit Issued | MOD CONSULTANTS LLC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/10/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/29/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/09/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/13/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 01/13/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/08/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/22/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/27/2025 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 04/04/2025 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 01/24/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/04/2026 | Lighting in dwelling units | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Air barrier - visual inspection | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Lighting controls | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Maintenance information | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | HVAC-R and service water heating equipment | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Fenestration areas | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Interior lighting power | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Seismic Isolation Systems | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Subgrade Inspections | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Masonry | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Concrete - Cast-In-Place | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Fire-Resistant Penetrations and Joints | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Exterior Insulation and Finish Systems (EIFS) | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Concrete - Precast | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Fenestration and door U-factor and product ratings | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | HVAC-R and service water piping design and insulation | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Exterior lighting power | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Excavations - Sheeting, Shoring, and Bracing | INDARDEO PARBHUNATH | special |
| 05/04/2026 | Energy Code Compliance Inspections | INDARDEO PARBHUNATH | progress |
| 05/04/2026 | Fire-Resistance Rated Construction | INDARDEO PARBHUNATH | progress |
| 05/04/2026 | Electrical motors and elevators | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | HVAC-R and service water heating system controls | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Metering | INDARDEO PARBHUNATH | energy_progress |
| 05/04/2026 | Fenestration air leakage | INDARDEO PARBHUNATH | energy_progress |