Primarily 2 family with 1 store or office
54 HUDSON AVENUE
BROOKLYN · BIN 3000061
💬 Discuss this project
1841Year Built
3Stories
S2Building Class
R6BZoning
2,560 sfGross Floor Area
3Units
Primarily 2 family with 1 store or office · 1,458 sf lot · 1.76 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanical
Roof1p · 1 filing · 14 docs
Floor 101p · 1 filing · 12 docs
Floor 9
Floor 8
Floor 7
Floor 6
Floor 5
Floor 4
Floor 3
Floor 22p · 1 filing · 14 docs
Floor 1
Cellar4p · 2 filings · 20 docs
Sub-Cellar1p · 1 filing · 12 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
11/24/2020$2.0M—Private party → Private party$771/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BENDIX ENGINEERING, P.C.404/22/2025
MOS ARCHITECTS PLLC302/26/2024
ROBERT SILMAN ASSOC STRUCT ENG DPC211/14/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
J CALLAHAN CONSULTING1803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LEONIDAS INTERIORS LLCGeneral Contractor2907/08/2026
WALTER J.GRANDE P & H INCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BENDIX ENGINEERING, P.C.4293204/22/2025
SHAHRISH SHUVO ENGINEERIN8524702/26/2024
Building Lifecycle
All (84)Filed (9)Permit Issued (19)Signed Off (4)Inspection (2)Objection (28)Special Inspection (22)
10/20/2025
Signed off — Alteration
Herewith filing alterations to an existing commercial space, as per plans submitted. There is no change to use, egress or occupancy.
B00773657-I1
10/14/2025
Signed off — Alteration
B00775106-I1
10/10/2025
Signed off — Alteration
Herewith filing removal, replacement and installation of plumbing fixtures, as per plans submitted
B00754634-I1
10/10/2025
Signed off — Alteration
Herewith filing for the installation of an HVAC system and related piping, as per plans submitted.
B00754616-I1
06/09/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
05/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
05/07/2025
Special inspection requirement — Final
Shahrish Shuvo
05/07/2025
Special inspection requirement — Mechanical Systems
Shahrish Shuvo
04/22/2025
Filed — Alteration
Herewith filing for the installation of an HVAC system and related piping, as per plans submitted.
B00754616-P1
04/11/2025
Permit issued — Plumbing
B00754634-I1-PL
04/09/2025
Permit issued — General Construction
B00773657-I1-GC
04/08/2025
Permit issued — Mechanical Systems
B00754616-I1-MS
03/21/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/04/2025
Filed — Alteration
Herewith filing removal, replacement and installation of plumbing fixtures, as per plans submitted
B00754634-P1
02/18/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Matthew Bendix
02/18/2025
Special inspection requirement — Mechanical Systems
Matthew Bendix
02/18/2025
Special inspection requirement — Final
Matthew Bendix
01/23/2025
Permit issued — General Construction
B00773657-I1-GC
01/22/2025
Permit issued — Structural
B00775106-I1-ST
01/22/2025
Permit issued — Mechanical Systems
B00754616-I1-MS
09/11/2024
Permit issued — General Construction
B00773657-I1-GC
09/11/2024
Permit issued — Mechanical Systems
B00754616-I1-MS
09/11/2024
Permit issued — Structural
B00775106-I1-ST
04/09/2024
Permit issued — General Construction
B00773657-I1-GC
04/03/2024
Permit issued — Structural
B00775106-I1-ST
04/03/2024
Permit issued — Mechanical Systems
B00754616-I1-MS
04/02/2024
Objection resolved — Addressed
03/29/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
Shahrish Shuvo
03/29/2024
Special inspection requirement — Structural Steel - Details
Shahrish Shuvo
03/29/2024
Special inspection requirement — Final
Shahrish Shuvo
03/29/2024
Special inspection requirement — Structural Wood Frame
Shahrish Shuvo
03/29/2024
Special inspection requirement — Post-installed Anchors
Shahrish Shuvo
03/29/2024
Special inspection requirement — Structural Steel - Welding
Shahrish Shuvo
03/04/2024
Objection raised — Other
02/26/2024
Filed — Alteration
Herewith filing alterations to an existing commercial space, as per plans submitted. There is no change to use, egress or occupancy.
B00773657-P2
02/22/2024
Special inspection requirement — Final
Shahrish Shuvo
02/22/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
02/01/2024
Permit issued — Structural
B00775106-I1-ST
01/22/2024
Permit issued — General Construction
B00773657-I1-GC
01/22/2024
Permit issued — Mechanical Systems
B00754616-I1-MS
11/22/2023
Objection resolved — Addressed
11/16/2023
Objection raised — Other
11/14/2023
Filed — Alteration
Herewith filing alterations to an existing commercial space, as per plans submitted. There is no change to use, egress or occupancy.
B00773657-P1
11/14/2023
Filed — Alteration
B00775106-P1
11/13/2023
Special inspection requirement — Structural Wood Frame
Shahrish Shuvo
11/13/2023
Special inspection requirement — Structural Steel - Welding
Shahrish Shuvo
11/13/2023
Special inspection requirement — Structural Steel - Details
Shahrish Shuvo
11/13/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Shahrish Shuvo
11/13/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Shahrish Shuvo
11/13/2023
Special inspection requirement — Final
Shahrish Shuvo
11/13/2023
Special inspection requirement — Post-installed Anchors
Shahrish Shuvo
11/13/2023
Special inspection requirement — Final
Shahrish Shuvo
08/15/2023
Permit issued — Structural
B00775106-I1-ST
08/15/2023
Permit issued — Plumbing
B00754634-I1-PL
08/14/2023
Permit issued — Mechanical Systems
B00754616-I1-MS
08/10/2023
Permit issued — General Construction
B00773657-I1-GC
07/28/2022
Objection raised — Other
07/28/2022
Objection resolved — Addressed
07/28/2022
Objection raised — Zoning
07/28/2022
Objection resolved — Addressed
Latest 60 of 84 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offWALTER J.GRANDE P & H INC04/11/2025
DOB NOWGeneral ConstructionSigned-offLEONIDAS INTERIORS LLC04/09/2025
DOB NOWMechanical SystemsSigned-offLEONIDAS INTERIORS LLC04/08/2025
DOB NOWGeneral ConstructionSigned-offLEONIDAS INTERIORS LLC01/23/2025
DOB NOWStructuralSigned-offLEONIDAS INTERIORS LLC01/22/2025
DOB NOWMechanical SystemsSigned-offLEONIDAS INTERIORS LLC01/22/2025
DOB NOWGeneral ConstructionSigned-offLEONIDAS INTERIORS LLC09/11/2024
DOB NOWMechanical SystemsSigned-offLEONIDAS INTERIORS LLC09/11/2024
DOB NOWStructuralSigned-offLEONIDAS INTERIORS LLC09/11/2024
DOB NOWGeneral ConstructionSigned-offLEONIDAS INTERIORS LLC04/09/2024
DOB NOWStructuralSigned-offLEONIDAS INTERIORS LLC04/03/2024
DOB NOWMechanical SystemsSigned-offLEONIDAS INTERIORS LLC04/03/2024
DOB NOWStructuralSigned-offLEONIDAS INTERIORS LLC02/01/2024
DOB NOWGeneral ConstructionSigned-offLEONIDAS INTERIORS LLC01/22/2024
DOB NOWMechanical SystemsSigned-offLEONIDAS INTERIORS LLC01/22/2024
DOB NOWStructuralSigned-offLEONIDAS INTERIORS LLC08/15/2023
DOB NOWPlumbingSigned-offWALTER J.GRANDE P & H INC08/15/2023
DOB NOWMechanical SystemsSigned-offLEONIDAS INTERIORS LLC08/14/2023
DOB NOWGeneral ConstructionSigned-offLEONIDAS INTERIORS LLC08/10/2023
BISOTISSUEDFOCAL PT DESIGN & CONSTR02/21/2013
1 project · most recent 03/13/2025
General Wiring
FiledStatusContractorScope
03/13/2025CompleteMARKS ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 2
DateTypeResultReport
06/09/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/21/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 22
DateRequirementInspectorRole
05/07/2025Fire-Resistant Penetrations and JointsShahrish Shuvospecial
05/07/2025FinalShahrish Shuvoprogress
05/07/2025Mechanical SystemsShahrish Shuvospecial
02/18/2025Fire-Resistant Penetrations and JointsMatthew Bendixspecial
02/18/2025Mechanical SystemsMatthew Bendixspecial
02/18/2025FinalMatthew Bendixprogress
03/29/2024Structural Stability – Alterations of existing buildingsShahrish Shuvospecial
03/29/2024Structural Steel - DetailsShahrish Shuvospecial
03/29/2024FinalShahrish Shuvoprogress
03/29/2024Structural Wood FrameShahrish Shuvoprogress
03/29/2024Post-installed AnchorsShahrish Shuvospecial
03/29/2024Structural Steel - WeldingShahrish Shuvospecial
02/22/2024FinalShahrish Shuvoprogress
02/22/2024Fire-Resistant Penetrations and JointsShahrish Shuvospecial
11/13/2023Structural Wood FrameShahrish Shuvoprogress
11/13/2023Structural Steel - WeldingShahrish Shuvospecial
11/13/2023Structural Steel - DetailsShahrish Shuvospecial
11/13/2023Structural Stability – Alterations of existing buildingsShahrish Shuvospecial
11/13/2023Fire-Resistant Penetrations and JointsShahrish Shuvospecial
11/13/2023FinalShahrish Shuvoprogress
11/13/2023Post-installed AnchorsShahrish Shuvospecial
11/13/2023FinalShahrish Shuvoprogress
▾Documents — 50 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/29/2026B00754616-I1Request digital key ↗
08/29/2026B00754616-P1Request digital key ↗
08/29/2026B00775106-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits7
▸DOB NOWLPC Approval/Permit4
08/29/2026B00754616-I1Open ↗
08/13/2026B00754616-P1Open ↗
08/13/2026B00775106-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION2
12/18/2013320818264Open ↗
11/10/2011320393141Open ↗
▸BISWORK PERMIT APPLICATION1
02/22/2013320393141Open ↗
▸Seals & Professional Certifications18
▸DOB NOWProgress Inspector Seal & Signature6
09/02/2026B00775106-P1Open ↗
09/01/2026B00754616-I1Open ↗
09/01/2026B00773657-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/02/2026B00775106-P1Open ↗
09/01/2026B00754616-I1Open ↗
09/01/2026B00773657-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/29/2026B00754616-I1Open ↗
08/29/2026B00775106-P1Open ↗
08/29/2026B00775106-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
12/18/2013320818264Open ↗
11/10/2011320393141Open ↗
▸Safety & Tenant Protection1
▸BISSTREET TREE CHECKLIST1
12/18/2013320818264Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/29/2026B00754616-I1Open ↗
08/29/2026B00775106-I1Open ↗
08/29/2026B00775106-P1Open ↗
Showing 3 of 4 on file for this type
▸Energy Compliance1
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS1
12/18/2013320818264Open ↗
▸Approvals, Objections & Sign-offs6
▸BISLANDMARKS APPROVAL2
08/01/2013320393141Open ↗
03/29/2012320393141Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
12/18/2013320818264Open ↗
11/10/2011320393141Open ↗
▸BISThird Party Electrical Signoff Compliance Report1
08/01/2013320393141Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
12/18/2013320818264Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
12/18/2013320818264Open ↗
08/01/2013320393141Open ↗
03/29/2012320393141Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms3
▸BISEFILING COVER SHEET2
12/18/2013320818264Open ↗
11/10/2011320393141Open ↗
▸BISADDITIONAL INFORMATION1
07/16/2013320393141Open ↗
▸Other Documents2
▸DOB NOWProof of Historic Building2
08/29/2026B00754616-I1Open ↗
08/13/2026B00754616-P1Open ↗